
The amount of work in a leather factory is increased by 50%. By what percentage is it necessary to increase the number of workers to complete the new amount of work in previously planned time, if the productivity of the new labour is 25% more?
A. 60%
B. $66\dfrac{2}{3}\% $
C. 40%
D. $33\dfrac{1}{3}\% $
Answer
242.7k+ views
Hint: Let us consider that initially there were 100 men in the factory and the planned time is 1 unit. Find the amount of work by the formula ${\text{men}} \times {\text{time = work}}$. Find the required number of men for the new work according to the given relation.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Recently Updated Pages
WBJEE 2026 Registration Started: Important Dates Eligibility Syllabus Exam Pattern

Area vs Volume: Key Differences Explained for Students

Mutually Exclusive vs Independent Events: Key Differences Explained

Know The Difference Between Fluid And Liquid

Dimensions of Charge: Dimensional Formula, Derivation, SI Units & Examples

How to Calculate Moment of Inertia: Step-by-Step Guide & Formulas

Trending doubts
JEE Mains Result 2026 OUT Check Scorecard Percentile Cutoff and Toppers

JEE Main Marks vs Percentile 2026: Calculate Percentile and Rank Using Marks

JEE Main 2026 Expected Cutoff Category Wise Qualifying Marks & Percentile

JEE Main 2026: Session 1 Results Out and Session 2 Registration Open, City Intimation Slip, Exam Dates, Syllabus & Eligibility

JEE Main 2026 Jan 21 Shift 1 Question Papers with Solutions & Answer Keys – Detailed Day 1 Analysis

JEE Mains Marks vs Rank 2026 – Estimate Your Rank with JEE Scores

Other Pages
CBSE Class 10 Maths Question Paper 2026 OUT Download PDF with Solutions

Complete List of Class 10 Maths Formulas (Chapterwise)

NCERT Solutions For Class 10 Maths Chapter 12 Surface Area And Volume - 2025-26

NCERT Solutions For Class 10 Maths Chapter 11 Areas Related To Circles - 2025-26

CBSE Class 10 Maths Question Paper Set 3 2025 (Standard) – PDF, Solutions & Pattern

NCERT Solutions For Class 10 Maths Chapter 13 Statistics - 2025-26

