
The amount of work in a leather factory is increased by 50%. By what percentage is it necessary to increase the number of workers to complete the new amount of work in previously planned time, if the productivity of the new labour is 25% more?
A. 60%
B. $66\dfrac{2}{3}\% $
C. 40%
D. $33\dfrac{1}{3}\% $
Answer
232.5k+ views
Hint: Let us consider that initially there were 100 men in the factory and the planned time is 1 unit. Find the amount of work by the formula ${\text{men}} \times {\text{time = work}}$. Find the required number of men for the new work according to the given relation.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Recently Updated Pages
Mutually Exclusive vs Independent Events: Key Differences Explained

Area vs Volume: Key Differences Explained for Students

Area of an Octagon Formula Explained Simply

Absolute Pressure Formula Explained: Key Equation & Examples

Central Angle of a Circle Formula Explained Quickly

Difference Between Vapor and Gas: JEE Main 2026

Trending doubts
JEE Main Syllabus 2026: Download Detailed Subject-wise PDF

JEE Main 2026 Exam Centres (OUT) – Latest Examination Centre and Cities List

JEE Main 2026 January 21 Shift 2 Question Papers and Analysis OUT Check Student Reactions

JEE Main 2026 Dress Code for Male & Female Candidates

JEE Main 2025 24 Jan Shift 2 Question Paper with Solutions

JEE Main 2026 Exam Day: Guidelines, Dress Code & Important Documents

Other Pages
Pregnancy Week and Due Date Calculator: Find How Far Along You Are

CBSE Class 10 Maths Set 1 2025 Question Paper & Solutions

CBSE Class 10 Maths Question Paper Set 2 430/1/2 2025 (Basic): PDF, Answers & Analysis

Surface Areas and Volumes Class 10 Maths Chapter 12 CBSE Notes - 2025-26

CBSE Class 10 Maths Question Paper Set 1 (Basic) 430/5/1 – 2025 with Answers

CBSE Class 10 Maths Set 1 2025 Question Paper (Standard)

