
The amount of work in a leather factory is increased by 50%. By what percentage is it necessary to increase the number of workers to complete the new amount of work in previously planned time, if the productivity of the new labour is 25% more?
A. 60%
B. $66\dfrac{2}{3}\% $
C. 40%
D. $33\dfrac{1}{3}\% $
Answer
174.6k+ views
Hint: Let us consider that initially there were 100 men in the factory and the planned time is 1 unit. Find the amount of work by the formula ${\text{men}} \times {\text{time = work}}$. Find the required number of men for the new work according to the given relation.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Recently Updated Pages
JEE Main Physics Mock Test 2025

JEE Main Maths Mock Test 2025: FREE Online Mock Test Series

JEE Main Chemistry Mock Test 2025

JEE Main Hydrocarbons Mock Test 2025-26: Free Practice Online

JEE Main 2025-26 Mock Test: Organic Compounds Containing Nitrogen

JEE Main 2025-26 Mock Test: Organic Compounds Containing Halogens

Trending doubts
JEE Main Marks Vs Percentile Vs Rank 2025: Calculate Percentile Using Marks

JEE Mains 2025 Cutoff: Expected and Category-Wise Qualifying Marks for NITs, IIITs, and GFTIs

JEE Main 2025 Session 2: Application Form (Out), Exam Dates (Released), Eligibility, & More

NIT Cutoff Percentile for 2025

JoSAA JEE Main & Advanced 2025 Counselling: Registration Dates, Documents, Fees, Seat Allotment & Cut‑offs

JEE Main Syllabus 2025 (Updated)

Other Pages
NCERT Solutions For Class 10 Maths Chapter 11 Areas Related to Circles - 2025-26

NCERT Solutions For Class 10 Maths Chapter 13 Statistics - 2025-26

NCERT Solutions For Class 10 Maths Chapter 12 Surface Area And Volume - 2025-26

NCERT Solutions For Class 10 Maths Chapter 14 Probability - 2025-26

All Mensuration Formulas with Examples and Quick Revision

NCERT Solutions For Class 10 Maths Chapter 15 Probability in Hindi - 2025-26
