Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store
seo-qna
SearchIcon
banner

The amount of work in a leather factory is increased by 50%. By what percentage is it necessary to increase the number of workers to complete the new amount of work in previously planned time, if the productivity of the new labour is 25% more?
A. 60%
B. 6623%
C. 40%
D. 3313%

Answer
VerifiedVerified
140.7k+ views
like imagedislike image
Hint: Let us consider that initially there were 100 men in the factory and the planned time is 1 unit. Find the amount of work by the formula men×time = work. Find the required number of men for the new work according to the given relation.

Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the men×time = work
Substitute the value 100 for men and 1 for time , we get work as
100×1=100
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is 100+50=150.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula men×time = work.
men×1 = 150
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is 150100=50 .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is 500.25×50=40.
Thus the actual requirement for new men is 40.
Percentage requirement of new men is 40100×100=40%, as the initial number of labour was 100.

Thus option C is the correct answer.

Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, men×time = work. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Latest Vedantu courses for you
Grade 11 Science PCM | CBSE | SCHOOL | English
CBSE (2025-26)
calendar iconAcademic year 2025-26
language iconENGLISH
book iconUnlimited access till final school exam
tick
School Full course for CBSE students
PhysicsPhysics
ChemistryChemistry
MathsMaths
₹41,848 per year
EMI starts from ₹3,487.34 per month
Select and buy