Answer
Verified
389.4k+ views
Hint: In this question, we need to determine the additional number of days that A will require to complete the remaining work as B and C left the work after 10 days. For this, we will use the unitary method and the concept which states that the total work completed in a day is the summation of the work done by the individual workers in a day.
Complete step-by-step answer:
Let A, B and C complete the work while working alone be A, B and C respectively.
According to the question,
A and B completes a work in 30 days working together. So, the amount of work completed by A and B in a day is given as:
$\dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{{30}} - - - - (i)$
Similarly, B and C complete a work in 24 days working together. So, the amount of work completed by B and C in a day is given as:
$\dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{{24}} - - - - (ii)$
Again, A and C complete work in 20 days working together. So, the amount of work completed by A and C in a day is given as:
$\dfrac{1}{A} + \dfrac{1}{C} = \dfrac{1}{{20}} - - - - (iii)$
Summation of all the one-day work by A, B and C gives the total of one-day work completed. So, adding equation (i) , (ii) and (iii) we get
$
\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{A} + \dfrac{1}{C} = \dfrac{1}{{30}} + \dfrac{1}{{24}} + \dfrac{1}{{20}} \\
2\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{1}{{30}} + \dfrac{1}{{24}} + \dfrac{1}{{20}} \\
2\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{{20 + 25 + 30}}{{600}} \\
2\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{{75}}{{600}} \\
\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{{75}}{{2 \times 600}} \\
= \dfrac{1}{{16}} - - - - (iv) \\
$
Hence, the total piece of work done by A, B and C together in a day is $\dfrac{1}{{16}}$.
Now, it is also given in the question that A, B and C work together only for 10 days and then, B and C leave. So, total work done in 10 days by A, B and C is given as:
$
{\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right)_{one{\text{ day}}}} = \dfrac{1}{{16}} \\
{\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right)_{{\text{10 days}}}} = \dfrac{{10}}{{16}} = \dfrac{5}{8} \\
$
As, the total work is dented by 1 so, the remaining work that has to be done by A alone is given as$1 - \dfrac{5}{8} = \dfrac{{8 - 5}}{8} = \dfrac{3}{8}$
Now, substituting equation (ii) in the equation (iv) to determine the one-day work of A alone.
$
\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{1}{{16}} \\
\dfrac{1}{A} + \left( {\dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{1}{{16}} \\
\dfrac{1}{A} + \dfrac{1}{{24}} = \dfrac{1}{{16}} \\
\dfrac{1}{A} = \dfrac{1}{{16}} - \dfrac{1}{{24}} \\
= \dfrac{{3 - 2}}{{48}} \\
= \dfrac{1}{{48}} \\
$
Hence, the time taken by A to complete the work alone is 48 days.
As calculated earlier, that $\dfrac{3}{8}$ of the work needs to be done by A alone. So, by following the unitary method,
Total number of days in which A will complete the remaining work is $\dfrac{3}{8} \times 48 = 3 \times 6 = 18{\text{ days}}$
Hence, A will complete the remaining work in 18 days.
So, the correct answer is “Option A”.
Note: It is worth noting down here that, as B and C left the work so, the time of completion of the work will be more as compared to the time if they would work together all the time to complete the work.
Complete step-by-step answer:
Let A, B and C complete the work while working alone be A, B and C respectively.
According to the question,
A and B completes a work in 30 days working together. So, the amount of work completed by A and B in a day is given as:
$\dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{{30}} - - - - (i)$
Similarly, B and C complete a work in 24 days working together. So, the amount of work completed by B and C in a day is given as:
$\dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{{24}} - - - - (ii)$
Again, A and C complete work in 20 days working together. So, the amount of work completed by A and C in a day is given as:
$\dfrac{1}{A} + \dfrac{1}{C} = \dfrac{1}{{20}} - - - - (iii)$
Summation of all the one-day work by A, B and C gives the total of one-day work completed. So, adding equation (i) , (ii) and (iii) we get
$
\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{A} + \dfrac{1}{C} = \dfrac{1}{{30}} + \dfrac{1}{{24}} + \dfrac{1}{{20}} \\
2\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{1}{{30}} + \dfrac{1}{{24}} + \dfrac{1}{{20}} \\
2\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{{20 + 25 + 30}}{{600}} \\
2\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{{75}}{{600}} \\
\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{{75}}{{2 \times 600}} \\
= \dfrac{1}{{16}} - - - - (iv) \\
$
Hence, the total piece of work done by A, B and C together in a day is $\dfrac{1}{{16}}$.
Now, it is also given in the question that A, B and C work together only for 10 days and then, B and C leave. So, total work done in 10 days by A, B and C is given as:
$
{\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right)_{one{\text{ day}}}} = \dfrac{1}{{16}} \\
{\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right)_{{\text{10 days}}}} = \dfrac{{10}}{{16}} = \dfrac{5}{8} \\
$
As, the total work is dented by 1 so, the remaining work that has to be done by A alone is given as$1 - \dfrac{5}{8} = \dfrac{{8 - 5}}{8} = \dfrac{3}{8}$
Now, substituting equation (ii) in the equation (iv) to determine the one-day work of A alone.
$
\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{1}{{16}} \\
\dfrac{1}{A} + \left( {\dfrac{1}{B} + \dfrac{1}{C}} \right) = \dfrac{1}{{16}} \\
\dfrac{1}{A} + \dfrac{1}{{24}} = \dfrac{1}{{16}} \\
\dfrac{1}{A} = \dfrac{1}{{16}} - \dfrac{1}{{24}} \\
= \dfrac{{3 - 2}}{{48}} \\
= \dfrac{1}{{48}} \\
$
Hence, the time taken by A to complete the work alone is 48 days.
As calculated earlier, that $\dfrac{3}{8}$ of the work needs to be done by A alone. So, by following the unitary method,
Total number of days in which A will complete the remaining work is $\dfrac{3}{8} \times 48 = 3 \times 6 = 18{\text{ days}}$
Hence, A will complete the remaining work in 18 days.
So, the correct answer is “Option A”.
Note: It is worth noting down here that, as B and C left the work so, the time of completion of the work will be more as compared to the time if they would work together all the time to complete the work.
Recently Updated Pages
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Find the values of other five trigonometric functions class 10 maths CBSE
Trending doubts
Difference Between Plant Cell and Animal Cell
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
Summary of the poem Where the Mind is Without Fear class 8 english CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
Write an application to the principal requesting five class 10 english CBSE
What organs are located on the left side of your body class 11 biology CBSE
What is the z value for a 90 95 and 99 percent confidence class 11 maths CBSE