Answer
Verified
381.7k+ views
Hint: Assume a variable x which will represent the number of days a man will take to complete the work alone and assume a variable y which will represent the number of days a boy will take to complete the work alone. Using a unitary method, calculate the work done by man and the boy in 1 day. Use the information given in the question and convert each data for 1 day and form two equations which can be solved to get x and y.
Complete step-by-step answer:
In the question, it is given that 8 men and 12 boys can finish a piece of work in 10 days. Also, it is given that 6 men and 8 boys can finish it in 14 days. We are required to find the time taken by one man alone and that by one boy alone to finish the work.
Let us assume that 1 man can finish the work alone in x days and 1 boy can finish the work alone in y days.
Let us write the above assumed data in arrow form.
1 man $\to $ 1 work $\to $ x days
By unitary method, we can say,
1 man $\to $ $\dfrac{1}{x}$ work $\to $ 1 day
This means that 1 man can do $\dfrac{1}{x}$ work in 1 day.
So, 8 men will do $\dfrac{8}{x}$ work in 1 day. $..............\left( 1 \right)$
Also, 6 men will do $\dfrac{6}{x}$ work in 1 day ……………….$\left( 2 \right)$
Similarly, we can write,
1 boy $\to $ 1 work $\to $ y days
By unitary method, we can say,
1 boy $\to $ $\dfrac{1}{y}$ work $\to $ 1 day
This means that 1 boy can do $\dfrac{1}{y}$ work in 1 day.
So, 12 boys will do $\dfrac{12}{y}$ work in 1 day. $..............\left( 3 \right)$
Also, 8 boys will do $\dfrac{8}{y}$ work in 1 day ……………….$\left( 4 \right)$
Using $\left( 1 \right)$ and $\left( 3 \right)$, we can say that 8 men and 12 boys together can
do $\dfrac{8}{x}+\dfrac{12}{y}$ work in 1 day.
It is given in the question that 8 men and 12 boys can do 1 work in 10 days. So, we can say
that 8 men and 12 boys can do $\dfrac{1}{10}$ work in 1 day. From this, we can say,
$\dfrac{8}{x}+\dfrac{12}{y}=\dfrac{1}{10}..............\left( 5 \right)$
Using $\left( 2 \right)$ and $\left( 4 \right)$, we can say that 6 men and 8 boys together can do $\dfrac{6}{x}+\dfrac{8}{y}$ work in 1 day.
It is given in the question that 6 men and 8 boys can do 1 work in 14 days. So, we can say that 6 men and 8 boys can do $\dfrac{1}{14}$ work in 1 day. From this, we can say,
$\dfrac{6}{x}+\dfrac{8}{y}=\dfrac{1}{14}..............\left( 6 \right)$
Multiplying equation $\left( 5 \right)$ by 4 and equation $\left( 6 \right)$ by 6, we get,
$\dfrac{32}{x}+\dfrac{48}{y}=\dfrac{4}{10}$
$\dfrac{36}{x}+\dfrac{48}{y}=\dfrac{6}{14}$
Subtracting the above two equations, we get,
$\begin{align}
& \left( \dfrac{32}{x}+\dfrac{48}{y} \right)-\left( \dfrac{36}{x}+\dfrac{48}{y} \right)=\dfrac{4}{10}-\dfrac{6}{14} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{56-60}{140} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{-4}{140} \\
& \Rightarrow x=140 \\
\end{align}$
Substituting x=140 in equation $\left( 5 \right)$, we get,
\[\begin{align}
& \dfrac{8}{140}+\dfrac{12}{y}=\dfrac{1}{10} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{1}{10}-\dfrac{8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{14-8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{6}{140} \\
& \Rightarrow y=280 \\
\end{align}\]
Hence, a man can complete the whole work alone in 140 days and a boy can complete the whole work alone in 280 days.
Note: There is a possibility that one may commit a mistake while using unitary method. To avoid this mistake, one should think logically while applying a unitary method. For example, if 1 man is completing the $\dfrac{1}{x}$ work in 1 day, then it can be noticed that the more will be the men, the more will be the work done. That is why we multiplied the work by 8 when we wanted to find the work done by 8 men in 1 day.
Complete step-by-step answer:
In the question, it is given that 8 men and 12 boys can finish a piece of work in 10 days. Also, it is given that 6 men and 8 boys can finish it in 14 days. We are required to find the time taken by one man alone and that by one boy alone to finish the work.
Let us assume that 1 man can finish the work alone in x days and 1 boy can finish the work alone in y days.
Let us write the above assumed data in arrow form.
1 man $\to $ 1 work $\to $ x days
By unitary method, we can say,
1 man $\to $ $\dfrac{1}{x}$ work $\to $ 1 day
This means that 1 man can do $\dfrac{1}{x}$ work in 1 day.
So, 8 men will do $\dfrac{8}{x}$ work in 1 day. $..............\left( 1 \right)$
Also, 6 men will do $\dfrac{6}{x}$ work in 1 day ……………….$\left( 2 \right)$
Similarly, we can write,
1 boy $\to $ 1 work $\to $ y days
By unitary method, we can say,
1 boy $\to $ $\dfrac{1}{y}$ work $\to $ 1 day
This means that 1 boy can do $\dfrac{1}{y}$ work in 1 day.
So, 12 boys will do $\dfrac{12}{y}$ work in 1 day. $..............\left( 3 \right)$
Also, 8 boys will do $\dfrac{8}{y}$ work in 1 day ……………….$\left( 4 \right)$
Using $\left( 1 \right)$ and $\left( 3 \right)$, we can say that 8 men and 12 boys together can
do $\dfrac{8}{x}+\dfrac{12}{y}$ work in 1 day.
It is given in the question that 8 men and 12 boys can do 1 work in 10 days. So, we can say
that 8 men and 12 boys can do $\dfrac{1}{10}$ work in 1 day. From this, we can say,
$\dfrac{8}{x}+\dfrac{12}{y}=\dfrac{1}{10}..............\left( 5 \right)$
Using $\left( 2 \right)$ and $\left( 4 \right)$, we can say that 6 men and 8 boys together can do $\dfrac{6}{x}+\dfrac{8}{y}$ work in 1 day.
It is given in the question that 6 men and 8 boys can do 1 work in 14 days. So, we can say that 6 men and 8 boys can do $\dfrac{1}{14}$ work in 1 day. From this, we can say,
$\dfrac{6}{x}+\dfrac{8}{y}=\dfrac{1}{14}..............\left( 6 \right)$
Multiplying equation $\left( 5 \right)$ by 4 and equation $\left( 6 \right)$ by 6, we get,
$\dfrac{32}{x}+\dfrac{48}{y}=\dfrac{4}{10}$
$\dfrac{36}{x}+\dfrac{48}{y}=\dfrac{6}{14}$
Subtracting the above two equations, we get,
$\begin{align}
& \left( \dfrac{32}{x}+\dfrac{48}{y} \right)-\left( \dfrac{36}{x}+\dfrac{48}{y} \right)=\dfrac{4}{10}-\dfrac{6}{14} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{56-60}{140} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{-4}{140} \\
& \Rightarrow x=140 \\
\end{align}$
Substituting x=140 in equation $\left( 5 \right)$, we get,
\[\begin{align}
& \dfrac{8}{140}+\dfrac{12}{y}=\dfrac{1}{10} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{1}{10}-\dfrac{8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{14-8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{6}{140} \\
& \Rightarrow y=280 \\
\end{align}\]
Hence, a man can complete the whole work alone in 140 days and a boy can complete the whole work alone in 280 days.
Note: There is a possibility that one may commit a mistake while using unitary method. To avoid this mistake, one should think logically while applying a unitary method. For example, if 1 man is completing the $\dfrac{1}{x}$ work in 1 day, then it can be noticed that the more will be the men, the more will be the work done. That is why we multiplied the work by 8 when we wanted to find the work done by 8 men in 1 day.
Recently Updated Pages
How many sigma and pi bonds are present in HCequiv class 11 chemistry CBSE
Mark and label the given geoinformation on the outline class 11 social science CBSE
When people say No pun intended what does that mea class 8 english CBSE
Name the states which share their boundary with Indias class 9 social science CBSE
Give an account of the Northern Plains of India class 9 social science CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
Trending doubts
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
In Indian rupees 1 trillion is equal to how many c class 8 maths CBSE
Which are the Top 10 Largest Countries of the World?
How do you graph the function fx 4x class 9 maths CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
Difference Between Plant Cell and Animal Cell
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Why is there a time difference of about 5 hours between class 10 social science CBSE