If 8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.
Answer
286k+ views
Hint: Assume a variable x which will represent the number of days a man will take to complete the work alone and assume a variable y which will represent the number of days a boy will take to complete the work alone. Using a unitary method, calculate the work done by man and the boy in 1 day. Use the information given in the question and convert each data for 1 day and form two equations which can be solved to get x and y.
Complete step-by-step answer:
In the question, it is given that 8 men and 12 boys can finish a piece of work in 10 days. Also, it is given that 6 men and 8 boys can finish it in 14 days. We are required to find the time taken by one man alone and that by one boy alone to finish the work.
Let us assume that 1 man can finish the work alone in x days and 1 boy can finish the work alone in y days.
Let us write the above assumed data in arrow form.
1 man $\to $ 1 work $\to $ x days
By unitary method, we can say,
1 man $\to $ $\dfrac{1}{x}$ work $\to $ 1 day
This means that 1 man can do $\dfrac{1}{x}$ work in 1 day.
So, 8 men will do $\dfrac{8}{x}$ work in 1 day. $..............\left( 1 \right)$
Also, 6 men will do $\dfrac{6}{x}$ work in 1 day ……………….$\left( 2 \right)$
Similarly, we can write,
1 boy $\to $ 1 work $\to $ y days
By unitary method, we can say,
1 boy $\to $ $\dfrac{1}{y}$ work $\to $ 1 day
This means that 1 boy can do $\dfrac{1}{y}$ work in 1 day.
So, 12 boys will do $\dfrac{12}{y}$ work in 1 day. $..............\left( 3 \right)$
Also, 8 boys will do $\dfrac{8}{y}$ work in 1 day ……………….$\left( 4 \right)$
Using $\left( 1 \right)$ and $\left( 3 \right)$, we can say that 8 men and 12 boys together can
do $\dfrac{8}{x}+\dfrac{12}{y}$ work in 1 day.
It is given in the question that 8 men and 12 boys can do 1 work in 10 days. So, we can say
that 8 men and 12 boys can do $\dfrac{1}{10}$ work in 1 day. From this, we can say,
$\dfrac{8}{x}+\dfrac{12}{y}=\dfrac{1}{10}..............\left( 5 \right)$
Using $\left( 2 \right)$ and $\left( 4 \right)$, we can say that 6 men and 8 boys together can do $\dfrac{6}{x}+\dfrac{8}{y}$ work in 1 day.
It is given in the question that 6 men and 8 boys can do 1 work in 14 days. So, we can say that 6 men and 8 boys can do $\dfrac{1}{14}$ work in 1 day. From this, we can say,
$\dfrac{6}{x}+\dfrac{8}{y}=\dfrac{1}{14}..............\left( 6 \right)$
Multiplying equation $\left( 5 \right)$ by 4 and equation $\left( 6 \right)$ by 6, we get,
$\dfrac{32}{x}+\dfrac{48}{y}=\dfrac{4}{10}$
$\dfrac{36}{x}+\dfrac{48}{y}=\dfrac{6}{14}$
Subtracting the above two equations, we get,
$\begin{align}
& \left( \dfrac{32}{x}+\dfrac{48}{y} \right)-\left( \dfrac{36}{x}+\dfrac{48}{y} \right)=\dfrac{4}{10}-\dfrac{6}{14} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{56-60}{140} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{-4}{140} \\
& \Rightarrow x=140 \\
\end{align}$
Substituting x=140 in equation $\left( 5 \right)$, we get,
\[\begin{align}
& \dfrac{8}{140}+\dfrac{12}{y}=\dfrac{1}{10} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{1}{10}-\dfrac{8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{14-8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{6}{140} \\
& \Rightarrow y=280 \\
\end{align}\]
Hence, a man can complete the whole work alone in 140 days and a boy can complete the whole work alone in 280 days.
Note: There is a possibility that one may commit a mistake while using unitary method. To avoid this mistake, one should think logically while applying a unitary method. For example, if 1 man is completing the $\dfrac{1}{x}$ work in 1 day, then it can be noticed that the more will be the men, the more will be the work done. That is why we multiplied the work by 8 when we wanted to find the work done by 8 men in 1 day.
Complete step-by-step answer:
In the question, it is given that 8 men and 12 boys can finish a piece of work in 10 days. Also, it is given that 6 men and 8 boys can finish it in 14 days. We are required to find the time taken by one man alone and that by one boy alone to finish the work.
Let us assume that 1 man can finish the work alone in x days and 1 boy can finish the work alone in y days.
Let us write the above assumed data in arrow form.
1 man $\to $ 1 work $\to $ x days
By unitary method, we can say,
1 man $\to $ $\dfrac{1}{x}$ work $\to $ 1 day
This means that 1 man can do $\dfrac{1}{x}$ work in 1 day.
So, 8 men will do $\dfrac{8}{x}$ work in 1 day. $..............\left( 1 \right)$
Also, 6 men will do $\dfrac{6}{x}$ work in 1 day ……………….$\left( 2 \right)$
Similarly, we can write,
1 boy $\to $ 1 work $\to $ y days
By unitary method, we can say,
1 boy $\to $ $\dfrac{1}{y}$ work $\to $ 1 day
This means that 1 boy can do $\dfrac{1}{y}$ work in 1 day.
So, 12 boys will do $\dfrac{12}{y}$ work in 1 day. $..............\left( 3 \right)$
Also, 8 boys will do $\dfrac{8}{y}$ work in 1 day ……………….$\left( 4 \right)$
Using $\left( 1 \right)$ and $\left( 3 \right)$, we can say that 8 men and 12 boys together can
do $\dfrac{8}{x}+\dfrac{12}{y}$ work in 1 day.
It is given in the question that 8 men and 12 boys can do 1 work in 10 days. So, we can say
that 8 men and 12 boys can do $\dfrac{1}{10}$ work in 1 day. From this, we can say,
$\dfrac{8}{x}+\dfrac{12}{y}=\dfrac{1}{10}..............\left( 5 \right)$
Using $\left( 2 \right)$ and $\left( 4 \right)$, we can say that 6 men and 8 boys together can do $\dfrac{6}{x}+\dfrac{8}{y}$ work in 1 day.
It is given in the question that 6 men and 8 boys can do 1 work in 14 days. So, we can say that 6 men and 8 boys can do $\dfrac{1}{14}$ work in 1 day. From this, we can say,
$\dfrac{6}{x}+\dfrac{8}{y}=\dfrac{1}{14}..............\left( 6 \right)$
Multiplying equation $\left( 5 \right)$ by 4 and equation $\left( 6 \right)$ by 6, we get,
$\dfrac{32}{x}+\dfrac{48}{y}=\dfrac{4}{10}$
$\dfrac{36}{x}+\dfrac{48}{y}=\dfrac{6}{14}$
Subtracting the above two equations, we get,
$\begin{align}
& \left( \dfrac{32}{x}+\dfrac{48}{y} \right)-\left( \dfrac{36}{x}+\dfrac{48}{y} \right)=\dfrac{4}{10}-\dfrac{6}{14} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{56-60}{140} \\
& \Rightarrow \dfrac{-4}{x}=\dfrac{-4}{140} \\
& \Rightarrow x=140 \\
\end{align}$
Substituting x=140 in equation $\left( 5 \right)$, we get,
\[\begin{align}
& \dfrac{8}{140}+\dfrac{12}{y}=\dfrac{1}{10} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{1}{10}-\dfrac{8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{14-8}{140} \\
& \Rightarrow \dfrac{12}{y}=\dfrac{6}{140} \\
& \Rightarrow y=280 \\
\end{align}\]
Hence, a man can complete the whole work alone in 140 days and a boy can complete the whole work alone in 280 days.
Note: There is a possibility that one may commit a mistake while using unitary method. To avoid this mistake, one should think logically while applying a unitary method. For example, if 1 man is completing the $\dfrac{1}{x}$ work in 1 day, then it can be noticed that the more will be the men, the more will be the work done. That is why we multiplied the work by 8 when we wanted to find the work done by 8 men in 1 day.
Recently Updated Pages
Define absolute refractive index of a medium

Find out what do the algal bloom and redtides sign class 10 biology CBSE

Prove that the function fleft x right xn is continuous class 12 maths CBSE

Find the values of other five trigonometric functions class 10 maths CBSE

Find the values of other five trigonometric ratios class 10 maths CBSE

Find the values of other five trigonometric functions class 10 maths CBSE

Trending doubts
Which of the following Chief Justice of India has acted class 10 social science CBSE

Green glands are excretory organs of A Crustaceans class 11 biology CBSE

What if photosynthesis does not occur in plants class 11 biology CBSE

What is 1 divided by 0 class 8 maths CBSE

Fill the blanks with the suitable prepositions 1 The class 9 english CBSE

Difference Between Plant Cell and Animal Cell

10 slogans on organ donation class 8 english CBSE

Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE

What is the past tense of read class 10 english CBSE
