Given, 8 men can dig a pit in 20 days. If a man works one and a half as much again as a boy, then 4 men and 8 boys can dig it in
A. 10 days
B. 12 days
C. 15 days
D. 17 days
Answer
446.4k+ views
Hint: First we will calculate the total work then we will calculate the total work done by 4 men and 8 boys together. Then by dividing the total work by work done by 4 men and 8 boys together we will get the number of days.
Complete step by step solution:
We have been given that 8 men can dig a pit in 20 days and a man works one and a half as much again as a boy.
We have to find out how many days 4 men and 8 boys can dig it.
Now, we have given that a man works one and a half as much again as a boy.
So if the work done by a boy will be $=1$
Then the work done by a man will be $=1+\dfrac{1}{2}$
So we will get the ratio of work done by a man and boy as $3:2$
Now, the total work will be
$\begin{align}
& \Rightarrow 8\times 3\times 20 \\
& \Rightarrow 480 \\
\end{align}$
Now, the total work done by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow 4\times 3+8\times 2 \\
& \Rightarrow 12+16 \\
& \Rightarrow 28 \\
\end{align}$
Now, time taken to dig a pit by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow \dfrac{480}{28} \\
& \Rightarrow 17.14 \\
\end{align}$
So the number of days 4 men and 8 boys take to dig a pit are 17 days.
Note:
Here in this particular question we get the answer as decimal. But we have to find the number of days so we convert the decimal number into the whole number by approximating the value to the nearest number. We cannot take a number of days into decimal.
Complete step by step solution:
We have been given that 8 men can dig a pit in 20 days and a man works one and a half as much again as a boy.
We have to find out how many days 4 men and 8 boys can dig it.
Now, we have given that a man works one and a half as much again as a boy.
So if the work done by a boy will be $=1$
Then the work done by a man will be $=1+\dfrac{1}{2}$
So we will get the ratio of work done by a man and boy as $3:2$
Now, the total work will be
$\begin{align}
& \Rightarrow 8\times 3\times 20 \\
& \Rightarrow 480 \\
\end{align}$
Now, the total work done by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow 4\times 3+8\times 2 \\
& \Rightarrow 12+16 \\
& \Rightarrow 28 \\
\end{align}$
Now, time taken to dig a pit by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow \dfrac{480}{28} \\
& \Rightarrow 17.14 \\
\end{align}$
So the number of days 4 men and 8 boys take to dig a pit are 17 days.
Note:
Here in this particular question we get the answer as decimal. But we have to find the number of days so we convert the decimal number into the whole number by approximating the value to the nearest number. We cannot take a number of days into decimal.
Recently Updated Pages
What percentage of the area in India is covered by class 10 social science CBSE

The area of a 6m wide road outside a garden in all class 10 maths CBSE

What is the electric flux through a cube of side 1 class 10 physics CBSE

If one root of x2 x k 0 maybe the square of the other class 10 maths CBSE

The radius and height of a cylinder are in the ratio class 10 maths CBSE

An almirah is sold for 5400 Rs after allowing a discount class 10 maths CBSE

Trending doubts
For Frost what do fire and ice stand for Here are some class 10 english CBSE

What did the military generals do How did their attitude class 10 english CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

What did being free mean to Mandela as a boy and as class 10 english CBSE

Why is there a time difference of about 5 hours between class 10 social science CBSE

What did Valli find about the bus journey How did she class 10 english CBSE