Given, 8 men can dig a pit in 20 days. If a man works one and a half as much again as a boy, then 4 men and 8 boys can dig it in
A. 10 days
B. 12 days
C. 15 days
D. 17 days
Answer
572.4k+ views
Hint: First we will calculate the total work then we will calculate the total work done by 4 men and 8 boys together. Then by dividing the total work by work done by 4 men and 8 boys together we will get the number of days.
Complete step by step solution:
We have been given that 8 men can dig a pit in 20 days and a man works one and a half as much again as a boy.
We have to find out how many days 4 men and 8 boys can dig it.
Now, we have given that a man works one and a half as much again as a boy.
So if the work done by a boy will be $=1$
Then the work done by a man will be $=1+\dfrac{1}{2}$
So we will get the ratio of work done by a man and boy as $3:2$
Now, the total work will be
$\begin{align}
& \Rightarrow 8\times 3\times 20 \\
& \Rightarrow 480 \\
\end{align}$
Now, the total work done by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow 4\times 3+8\times 2 \\
& \Rightarrow 12+16 \\
& \Rightarrow 28 \\
\end{align}$
Now, time taken to dig a pit by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow \dfrac{480}{28} \\
& \Rightarrow 17.14 \\
\end{align}$
So the number of days 4 men and 8 boys take to dig a pit are 17 days.
Note:
Here in this particular question we get the answer as decimal. But we have to find the number of days so we convert the decimal number into the whole number by approximating the value to the nearest number. We cannot take a number of days into decimal.
Complete step by step solution:
We have been given that 8 men can dig a pit in 20 days and a man works one and a half as much again as a boy.
We have to find out how many days 4 men and 8 boys can dig it.
Now, we have given that a man works one and a half as much again as a boy.
So if the work done by a boy will be $=1$
Then the work done by a man will be $=1+\dfrac{1}{2}$
So we will get the ratio of work done by a man and boy as $3:2$
Now, the total work will be
$\begin{align}
& \Rightarrow 8\times 3\times 20 \\
& \Rightarrow 480 \\
\end{align}$
Now, the total work done by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow 4\times 3+8\times 2 \\
& \Rightarrow 12+16 \\
& \Rightarrow 28 \\
\end{align}$
Now, time taken to dig a pit by 4 men and 8 boys will be
$\begin{align}
& \Rightarrow \dfrac{480}{28} \\
& \Rightarrow 17.14 \\
\end{align}$
So the number of days 4 men and 8 boys take to dig a pit are 17 days.
Note:
Here in this particular question we get the answer as decimal. But we have to find the number of days so we convert the decimal number into the whole number by approximating the value to the nearest number. We cannot take a number of days into decimal.
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 Computer Science: Engaging Questions & Answers for Success

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

In cricket, what is the term for a bowler taking five wickets in an innings?

Who Won 36 Oscar Awards? Record Holder Revealed

What is the median of the first 10 natural numbers class 10 maths CBSE

Why is it 530 pm in india when it is 1200 afternoon class 10 social science CBSE

What is deficiency disease class 10 biology CBSE