
A is twice as good as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A. 12
B. 15
C. 17
D. 21
Answer
602.7k+ views
Hint: Here, we will first calculate A’s one day work and B’s one day work by assuming A takes x days and B take 2x day, and equate them with one day work when both A and B do the same work together. Then solve the equation obtained to get the number of days taken by A to complete the work alone.
Complete step by step answer:
Given, A is twice good as B to complete the work.
Therefore, B takes twice the number of days taken by A to complete the work.
Let A take x days to complete the work, then according to question, B takes 2x days to complete the same work.
Also given that both A and B together complete the work in 14 days.
Work done in one day = Reciprocal of days taken to complete the total work
A’s one day work = $\dfrac{1}{x}$
B’s one day work = $\dfrac{1}{{2x}}$
(A + B)’s one day work = $\dfrac{1}{{14}}$
According to the question,
$\dfrac{1}{x} + \dfrac{1}{{2x}} = \dfrac{1}{{14}}$
Solving equation,
$\dfrac{{2 + 1}}{{2x}} = \dfrac{1}{{14}}$
\[ \Rightarrow \dfrac{3}{{2x}} = \dfrac{1}{{14}}\]
On cross-multiplying, we get
$2x = 42$
$ \Rightarrow x = \dfrac{{42}}{2} = 21$
Therefore, A takes 21 days to complete the work, and B takes 2x i.e. 2 × 21 = 42 days to complete the work.
Hence, the correct option is (D).
Note:
In this type of question, always calculate and compare one day's work by taking reciprocal of the total time taken to do the work. As if a particular work is done in x days and the work done in one day will be $\dfrac{1}{x}$ part of the total work. Never calculate by considering the number of days to complete the total work. And also after finding the unknown value, but that value in the equation formed as it must satisfy the equation.
Complete step by step answer:
Given, A is twice good as B to complete the work.
Therefore, B takes twice the number of days taken by A to complete the work.
Let A take x days to complete the work, then according to question, B takes 2x days to complete the same work.
Also given that both A and B together complete the work in 14 days.
Work done in one day = Reciprocal of days taken to complete the total work
A’s one day work = $\dfrac{1}{x}$
B’s one day work = $\dfrac{1}{{2x}}$
(A + B)’s one day work = $\dfrac{1}{{14}}$
According to the question,
$\dfrac{1}{x} + \dfrac{1}{{2x}} = \dfrac{1}{{14}}$
Solving equation,
$\dfrac{{2 + 1}}{{2x}} = \dfrac{1}{{14}}$
\[ \Rightarrow \dfrac{3}{{2x}} = \dfrac{1}{{14}}\]
On cross-multiplying, we get
$2x = 42$
$ \Rightarrow x = \dfrac{{42}}{2} = 21$
Therefore, A takes 21 days to complete the work, and B takes 2x i.e. 2 × 21 = 42 days to complete the work.
Hence, the correct option is (D).
Note:
In this type of question, always calculate and compare one day's work by taking reciprocal of the total time taken to do the work. As if a particular work is done in x days and the work done in one day will be $\dfrac{1}{x}$ part of the total work. Never calculate by considering the number of days to complete the total work. And also after finding the unknown value, but that value in the equation formed as it must satisfy the equation.
Recently Updated Pages
Basicity of sulphurous acid and sulphuric acid are

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Computer Science: Engaging Questions & Answers for Success

Class 10 Question and Answer - Your Ultimate Solutions Guide

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Trending doubts
Who is known as the "Little Master" in Indian cricket history?

A boat goes 24 km upstream and 28 km downstream in class 10 maths CBSE

Who Won 36 Oscar Awards? Record Holder Revealed

Why is there a time difference of about 5 hours between class 10 social science CBSE

Explain the Treaty of Vienna of 1815 class 10 social science CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

