A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, find the time taken by B to finish the work.
Answer
661.2k+ views
Hint:
Consider the time taken by B as ‘x’. A takes 6 days less than B, so time taken by A is (x - 6). So work done by \[B=\dfrac{1}{x}\]and \[A=\dfrac{1}{x-6}\]. Total work done by (A + B) is \[\dfrac{1}{4}\]. Solve the equation formed to get the time taken by B to finish the work.
Complete step-by-step answer:
Suppose B alone takes x days to finish the work. Then A alone can finish the work in (x - 6) days.
Now we know A’s one day work\[=\dfrac{1}{x-6}\].
B’s work per day\[=\dfrac{1}{x}\].
The total work done by A and B in one day\[=\dfrac{1}{x}+\dfrac{1}{x-6}-(1)\]
\[A+B=\dfrac{1}{x}+\dfrac{1}{x-6}\].
It’s said that A and B can finish a work together in 4 days.
\[\therefore A+B=\dfrac{1}{4}-(2)\]
Now, Equating equation (1) and equation (2),
\[\dfrac{1}{x}+\dfrac{1}{x-6}=\dfrac{1}{4}\]
Simplifying the LHS, \[\dfrac{\left( x-6 \right)+x}{x\left( x-6 \right)}=\dfrac{1}{4}\]
\[\Rightarrow \dfrac{2x-6}{x\left( x-6 \right)}=\dfrac{1}{4}\]
Now cross multiplying them, then the equation becomes,
\[4\left( 2x-6 \right)=x\left( x-6 \right)\]
Opening the brackets and simplifying them,
\[\begin{align}
& 8x-24={{x}^{2}}-6x \\
& \Rightarrow {{x}^{2}}-6x-8x+24=0 \\
& {{x}^{2}}-x\left( 6+8 \right)+24=0 \\
& {{x}^{2}}-14x+24=0-(3) \\
\end{align}\]
Equation (3) is similar to the general quadratic equation, \[a{{x}^{2}}+bx+c=0\].
Comparing both general equation and equation (3), we get the values of constants a = 1, b = -14, c = 24.
Now, applying the above value in the quadratic formula,
\[\begin{align}
& \dfrac{-b\pm \sqrt{{{b}^{2}}-4ac}}{2a}=\dfrac{-\left( -14 \right)\pm \sqrt{{{\left( -14 \right)}^{2}}-4\times 1\times 24}}{2\times 1} \\
& =\dfrac{14\pm \sqrt{196-96}}{2}=\dfrac{14\pm \sqrt{100}}{2}=\dfrac{14\pm 10}{2} \\
\end{align}\]
The roots are \[\left( \dfrac{14+10}{2} \right)\]and \[\left( \dfrac{14-10}{2} \right)\]= 12 and 2.
The value of x cannot be less than 6.
If B takes the time of 2 days, then the time taken by A becomes, \[x-6=2-6=-4\]days.
i.e. time taken cannot be negative.
\[\therefore x=12\].
i.e. It would take B a period of 12 days to finish the job.
Note:
If we were asked to find the time taken by A to finish the work alone then we got x=12 i.e. the time taken by B alone to do a work. So, time taken by A is 12 – 6 = 6 days. As A takes 6 days less than the time taken by B. If we are adding time taken by (A + B) together\[=\dfrac{1}{6}+\dfrac{1}{12}=\dfrac{12+6}{12\times 6}=\dfrac{1}{4}\].
Consider the time taken by B as ‘x’. A takes 6 days less than B, so time taken by A is (x - 6). So work done by \[B=\dfrac{1}{x}\]and \[A=\dfrac{1}{x-6}\]. Total work done by (A + B) is \[\dfrac{1}{4}\]. Solve the equation formed to get the time taken by B to finish the work.
Complete step-by-step answer:
Suppose B alone takes x days to finish the work. Then A alone can finish the work in (x - 6) days.
Now we know A’s one day work\[=\dfrac{1}{x-6}\].
B’s work per day\[=\dfrac{1}{x}\].
The total work done by A and B in one day\[=\dfrac{1}{x}+\dfrac{1}{x-6}-(1)\]
\[A+B=\dfrac{1}{x}+\dfrac{1}{x-6}\].
It’s said that A and B can finish a work together in 4 days.
\[\therefore A+B=\dfrac{1}{4}-(2)\]
Now, Equating equation (1) and equation (2),
\[\dfrac{1}{x}+\dfrac{1}{x-6}=\dfrac{1}{4}\]
Simplifying the LHS, \[\dfrac{\left( x-6 \right)+x}{x\left( x-6 \right)}=\dfrac{1}{4}\]
\[\Rightarrow \dfrac{2x-6}{x\left( x-6 \right)}=\dfrac{1}{4}\]
Now cross multiplying them, then the equation becomes,
\[4\left( 2x-6 \right)=x\left( x-6 \right)\]
Opening the brackets and simplifying them,
\[\begin{align}
& 8x-24={{x}^{2}}-6x \\
& \Rightarrow {{x}^{2}}-6x-8x+24=0 \\
& {{x}^{2}}-x\left( 6+8 \right)+24=0 \\
& {{x}^{2}}-14x+24=0-(3) \\
\end{align}\]
Equation (3) is similar to the general quadratic equation, \[a{{x}^{2}}+bx+c=0\].
Comparing both general equation and equation (3), we get the values of constants a = 1, b = -14, c = 24.
Now, applying the above value in the quadratic formula,
\[\begin{align}
& \dfrac{-b\pm \sqrt{{{b}^{2}}-4ac}}{2a}=\dfrac{-\left( -14 \right)\pm \sqrt{{{\left( -14 \right)}^{2}}-4\times 1\times 24}}{2\times 1} \\
& =\dfrac{14\pm \sqrt{196-96}}{2}=\dfrac{14\pm \sqrt{100}}{2}=\dfrac{14\pm 10}{2} \\
\end{align}\]
The roots are \[\left( \dfrac{14+10}{2} \right)\]and \[\left( \dfrac{14-10}{2} \right)\]= 12 and 2.
The value of x cannot be less than 6.
If B takes the time of 2 days, then the time taken by A becomes, \[x-6=2-6=-4\]days.
i.e. time taken cannot be negative.
\[\therefore x=12\].
i.e. It would take B a period of 12 days to finish the job.
Note:
If we were asked to find the time taken by A to finish the work alone then we got x=12 i.e. the time taken by B alone to do a work. So, time taken by A is 12 – 6 = 6 days. As A takes 6 days less than the time taken by B. If we are adding time taken by (A + B) together\[=\dfrac{1}{6}+\dfrac{1}{12}=\dfrac{12+6}{12\times 6}=\dfrac{1}{4}\].
Recently Updated Pages
Master Class 11 English: Engaging Questions & Answers for Success

Master Class 11 Social Science: Engaging Questions & Answers for Success

Master Class 11 Maths: Engaging Questions & Answers for Success

Master Class 11 Biology: Engaging Questions & Answers for Success

Master Class 11 Physics: Engaging Questions & Answers for Success

Master Class 11 Chemistry: Engaging Questions & Answers for Success

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

What is the Total Duration of Football Match?

First Cotton Mill of India

In which year voting age was reduced from 21 to 18?

10 examples of evaporation in daily life with explanations

What planets have no moons Which one has only one moon class 10 physics CBSE

