A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job, if 6 men leave after working for 6 days?
$\left( a \right)$ 10 days
$\left( b \right)$ 12 days
$\left( c \right)$ 6 days
$\left( d \right)$ 24 days
Answer
612.6k+ views
Hint: In this particular question use the concept that if 12 men can do a work in 12 days so the 1 day work of 12 men is $\dfrac{1}{{12}}$, therefore one day work of 1 man is $\dfrac{1}{{12 \times 12}}$,so the 6 day work of 12 men is $\dfrac{{6 \times 12}}{{12 \times 12}} = \dfrac{1}{2}$, so use these concept to reach the solution of the question.
Complete step-by-step answer:
Given data:
A job can be completed by 12 men in 12 days.
Now we have to find out how many extra days will be needed to complete the job, if 6 men leave after working for 6 days.
Let the work = 1
Now as the work is completed in 12 days by 12 men.
So the 1 day work of 12 men = $\dfrac{1}{{12}}$.
So the 1 day work of 1 man = $\dfrac{1}{{12 \times 12}}$
So the 6 day work of 1 man = $\dfrac{6}{{12 \times 12}}$.
So the 6 day work of 12 men = $\dfrac{{6 \times 12}}{{12 \times 12}} = \dfrac{1}{2}$.
So the remaining work after 6 days work of 6 men = total work – 6 day work of 12 men.
Therefore, the remaining work after 6 days work of 6 men = 1 – $\dfrac{1}{2}$ = $\dfrac{1}{2}$
So $\dfrac{1}{2}$ work is remaining.
Now after 6 days 6 workers go on leave, so the remaining work is done by the remaining 6 workers.
Let the number of days taken by remaining 6 workers be X.
So, the 12 men can complete 1 work in 12 days which is equal to 6 men can complete $\dfrac{1}{2}$work in X days.
Therefore, $\dfrac{1}{{12 \times 12}} = \dfrac{{\dfrac{1}{2}}}{{6 \times x}}$
Now simplify it we have,
$ \Rightarrow 6x = \dfrac{1}{2}\left( {144} \right)$
$ \Rightarrow x = \dfrac{{72}}{6} = 12$ days.
So the total number of days to finish the work this time = 12 + 6 = 18 days
So the number of extra days which is needed to complete the work = 18 – 12 = 6 days.
Hence option (c) is the correct answer.
Note: Whenever we face such types of questions the key concept we have to remember is that always recall that 12 men can complete 1 work in 12 days which is equal to the 6 men can complete $\dfrac{1}{2}$work in X days, so just covert this information into equation as above and simplify we will get the number of days in which the remaining work is finished, so the total work is finished is the sum of the previous days in which all 12 workers working and the number of days in which 6 workers are working so the extra number of days is the difference of current scenario days in which total work is finished into two parts and the number of days in which total work is finished in only one part.
Complete step-by-step answer:
Given data:
A job can be completed by 12 men in 12 days.
Now we have to find out how many extra days will be needed to complete the job, if 6 men leave after working for 6 days.
Let the work = 1
Now as the work is completed in 12 days by 12 men.
So the 1 day work of 12 men = $\dfrac{1}{{12}}$.
So the 1 day work of 1 man = $\dfrac{1}{{12 \times 12}}$
So the 6 day work of 1 man = $\dfrac{6}{{12 \times 12}}$.
So the 6 day work of 12 men = $\dfrac{{6 \times 12}}{{12 \times 12}} = \dfrac{1}{2}$.
So the remaining work after 6 days work of 6 men = total work – 6 day work of 12 men.
Therefore, the remaining work after 6 days work of 6 men = 1 – $\dfrac{1}{2}$ = $\dfrac{1}{2}$
So $\dfrac{1}{2}$ work is remaining.
Now after 6 days 6 workers go on leave, so the remaining work is done by the remaining 6 workers.
Let the number of days taken by remaining 6 workers be X.
So, the 12 men can complete 1 work in 12 days which is equal to 6 men can complete $\dfrac{1}{2}$work in X days.
Therefore, $\dfrac{1}{{12 \times 12}} = \dfrac{{\dfrac{1}{2}}}{{6 \times x}}$
Now simplify it we have,
$ \Rightarrow 6x = \dfrac{1}{2}\left( {144} \right)$
$ \Rightarrow x = \dfrac{{72}}{6} = 12$ days.
So the total number of days to finish the work this time = 12 + 6 = 18 days
So the number of extra days which is needed to complete the work = 18 – 12 = 6 days.
Hence option (c) is the correct answer.
Note: Whenever we face such types of questions the key concept we have to remember is that always recall that 12 men can complete 1 work in 12 days which is equal to the 6 men can complete $\dfrac{1}{2}$work in X days, so just covert this information into equation as above and simplify we will get the number of days in which the remaining work is finished, so the total work is finished is the sum of the previous days in which all 12 workers working and the number of days in which 6 workers are working so the extra number of days is the difference of current scenario days in which total work is finished into two parts and the number of days in which total work is finished in only one part.
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred

Master Class 11 Social Science: Engaging Questions & Answers for Success

Master Class 11 Physics: Engaging Questions & Answers for Success

Master Class 11 Maths: Engaging Questions & Answers for Success

Master Class 11 Economics: Engaging Questions & Answers for Success

Master Class 11 Computer Science: Engaging Questions & Answers for Success

Trending doubts
One Metric ton is equal to kg A 10000 B 1000 C 100 class 11 physics CBSE

There are 720 permutations of the digits 1 2 3 4 5 class 11 maths CBSE

State and prove Bernoullis theorem class 11 physics CBSE

Draw a diagram of a plant cell and label at least eight class 11 biology CBSE

Difference Between Prokaryotic Cells and Eukaryotic Cells

1 Quintal is equal to a 110 kg b 10 kg c 100kg d 1000 class 11 physics CBSE

