
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Answer
578.7k+ views
Hint: We see that the amount of work before $\left( {{W}_{1}} \right)$ and after$\left( {{W}_{2}} \right)$ the change in schedule to complete the part is same. If we assume the number of persons and amount of time before the change in schedule as ${{x}_{1}},{{t}_{1}}$ and after the schedule as ${{x}_{2}},{{t}_{2}}$. We have ${{W}_{1}}={{x}_{1}}{{t}_{1}}={{x}_{2}}{{t}_{2}}={{W}_{2}}$. We put the gien values, solve the equation and find ${{t}_{2}}$.
Complete step-by-step solution:
We see that the amount of time for the work or productivity of the building part of a stadium was initially 9 months and then later the contractor has to complete the same amount of the work in 5 months.
Let us denote the number of persons required to complete the part as $x$ and the amount of time as ${{t}_{1}}$ initially before the change of schedule. We are given that ${{x}_{1}}=560$ and ${{t}_{1}}=9$ months. So the total productivity or work initially before the change in schedule set up was ${{W}_{1}}={{x}_{1}}\times {{t}_{1}}=560\times 9=4940$\[\]
We see that later on schedule changed and the work was ordered to complete in 5 months. Let us assume the number of persons required to complete the work in 5 months as ${{x}_{2}}$ and the time period as ${{t}_{2}}$. We are given ${{t}_{2}}=5$ months. The total productivity or work after the change in schedule is ${{W}_{2}}={{x}_{2}}\times {{t}_{2}}={{x}_{2}}\times 5=5{{x}_{2}}$.\[\]
The amount of work is same before and after the change in schedule . So we have
\[\begin{align}
& {{W}_{1}}={{W}_{2}} \\
& \Rightarrow 4940=5{{x}_{2}} \\
& \Rightarrow {{x}_{2}}=\dfrac{4940}{5}=988 \\
\end{align}\]
So the number of persons he should employ to finish the working 5 months is 988.
Note: We note that it is assumed that when the questions say “LATER ON” the work has not started. Here we used equal product in work-time problems because of productivity but in case of rate of work we have to use equal ratio which is ${{r}_{1}}={{r}_{2}}\Rightarrow \dfrac{{{W}_{1}}}{{{t}_{1}}}=\dfrac{{{W}_{2}}}{{{t}_{2}}}$. We also use equal ratio in case of speed $s=\dfrac{d}{t}$ and product in case of distance $ d=st.$
Complete step-by-step solution:
We see that the amount of time for the work or productivity of the building part of a stadium was initially 9 months and then later the contractor has to complete the same amount of the work in 5 months.
Let us denote the number of persons required to complete the part as $x$ and the amount of time as ${{t}_{1}}$ initially before the change of schedule. We are given that ${{x}_{1}}=560$ and ${{t}_{1}}=9$ months. So the total productivity or work initially before the change in schedule set up was ${{W}_{1}}={{x}_{1}}\times {{t}_{1}}=560\times 9=4940$\[\]
We see that later on schedule changed and the work was ordered to complete in 5 months. Let us assume the number of persons required to complete the work in 5 months as ${{x}_{2}}$ and the time period as ${{t}_{2}}$. We are given ${{t}_{2}}=5$ months. The total productivity or work after the change in schedule is ${{W}_{2}}={{x}_{2}}\times {{t}_{2}}={{x}_{2}}\times 5=5{{x}_{2}}$.\[\]
The amount of work is same before and after the change in schedule . So we have
\[\begin{align}
& {{W}_{1}}={{W}_{2}} \\
& \Rightarrow 4940=5{{x}_{2}} \\
& \Rightarrow {{x}_{2}}=\dfrac{4940}{5}=988 \\
\end{align}\]
So the number of persons he should employ to finish the working 5 months is 988.
Note: We note that it is assumed that when the questions say “LATER ON” the work has not started. Here we used equal product in work-time problems because of productivity but in case of rate of work we have to use equal ratio which is ${{r}_{1}}={{r}_{2}}\Rightarrow \dfrac{{{W}_{1}}}{{{t}_{1}}}=\dfrac{{{W}_{2}}}{{{t}_{2}}}$. We also use equal ratio in case of speed $s=\dfrac{d}{t}$ and product in case of distance $ d=st.$
Recently Updated Pages
The number of solutions in x in 02pi for which sqrt class 12 maths CBSE

Write any two methods of preparation of phenol Give class 12 chemistry CBSE

Differentiate between action potential and resting class 12 biology CBSE

Two plane mirrors arranged at right angles to each class 12 physics CBSE

Which of the following molecules is are chiral A I class 12 chemistry CBSE

Name different types of neurons and give one function class 12 biology CBSE

Trending doubts
What are the 12 elements of nature class 8 chemistry CBSE

What are gulf countries and why they are called Gulf class 8 social science CBSE

Write a letter to the Municipal Commissioner to inform class 8 english CBSE

Write a book review which you have recently read in class 8 english CBSE

Write a short biography of Dr APJ Abdul Kalam under class 8 english CBSE

A train travels a distance of 480km at a uniform speed class 8 maths CBSE


