A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Answer
648k+ views
Hint: We see that the amount of work before $\left( {{W}_{1}} \right)$ and after$\left( {{W}_{2}} \right)$ the change in schedule to complete the part is same. If we assume the number of persons and amount of time before the change in schedule as ${{x}_{1}},{{t}_{1}}$ and after the schedule as ${{x}_{2}},{{t}_{2}}$. We have ${{W}_{1}}={{x}_{1}}{{t}_{1}}={{x}_{2}}{{t}_{2}}={{W}_{2}}$. We put the gien values, solve the equation and find ${{t}_{2}}$.
Complete step-by-step solution:
We see that the amount of time for the work or productivity of the building part of a stadium was initially 9 months and then later the contractor has to complete the same amount of the work in 5 months.
Let us denote the number of persons required to complete the part as $x$ and the amount of time as ${{t}_{1}}$ initially before the change of schedule. We are given that ${{x}_{1}}=560$ and ${{t}_{1}}=9$ months. So the total productivity or work initially before the change in schedule set up was ${{W}_{1}}={{x}_{1}}\times {{t}_{1}}=560\times 9=4940$\[\]
We see that later on schedule changed and the work was ordered to complete in 5 months. Let us assume the number of persons required to complete the work in 5 months as ${{x}_{2}}$ and the time period as ${{t}_{2}}$. We are given ${{t}_{2}}=5$ months. The total productivity or work after the change in schedule is ${{W}_{2}}={{x}_{2}}\times {{t}_{2}}={{x}_{2}}\times 5=5{{x}_{2}}$.\[\]
The amount of work is same before and after the change in schedule . So we have
\[\begin{align}
& {{W}_{1}}={{W}_{2}} \\
& \Rightarrow 4940=5{{x}_{2}} \\
& \Rightarrow {{x}_{2}}=\dfrac{4940}{5}=988 \\
\end{align}\]
So the number of persons he should employ to finish the working 5 months is 988.
Note: We note that it is assumed that when the questions say “LATER ON” the work has not started. Here we used equal product in work-time problems because of productivity but in case of rate of work we have to use equal ratio which is ${{r}_{1}}={{r}_{2}}\Rightarrow \dfrac{{{W}_{1}}}{{{t}_{1}}}=\dfrac{{{W}_{2}}}{{{t}_{2}}}$. We also use equal ratio in case of speed $s=\dfrac{d}{t}$ and product in case of distance $ d=st.$
Complete step-by-step solution:
We see that the amount of time for the work or productivity of the building part of a stadium was initially 9 months and then later the contractor has to complete the same amount of the work in 5 months.
Let us denote the number of persons required to complete the part as $x$ and the amount of time as ${{t}_{1}}$ initially before the change of schedule. We are given that ${{x}_{1}}=560$ and ${{t}_{1}}=9$ months. So the total productivity or work initially before the change in schedule set up was ${{W}_{1}}={{x}_{1}}\times {{t}_{1}}=560\times 9=4940$\[\]
We see that later on schedule changed and the work was ordered to complete in 5 months. Let us assume the number of persons required to complete the work in 5 months as ${{x}_{2}}$ and the time period as ${{t}_{2}}$. We are given ${{t}_{2}}=5$ months. The total productivity or work after the change in schedule is ${{W}_{2}}={{x}_{2}}\times {{t}_{2}}={{x}_{2}}\times 5=5{{x}_{2}}$.\[\]
The amount of work is same before and after the change in schedule . So we have
\[\begin{align}
& {{W}_{1}}={{W}_{2}} \\
& \Rightarrow 4940=5{{x}_{2}} \\
& \Rightarrow {{x}_{2}}=\dfrac{4940}{5}=988 \\
\end{align}\]
So the number of persons he should employ to finish the working 5 months is 988.
Note: We note that it is assumed that when the questions say “LATER ON” the work has not started. Here we used equal product in work-time problems because of productivity but in case of rate of work we have to use equal ratio which is ${{r}_{1}}={{r}_{2}}\Rightarrow \dfrac{{{W}_{1}}}{{{t}_{1}}}=\dfrac{{{W}_{2}}}{{{t}_{2}}}$. We also use equal ratio in case of speed $s=\dfrac{d}{t}$ and product in case of distance $ d=st.$
Recently Updated Pages
Which will be the least stable resonating structure class 11 chemistry CBSE

Explain the structure of megasporangium class 12 biology CBSE

Differentiate between voluntary action and reflex class 10 biology CBSE

How many 5 digit telephone numbers can be construc-class-11-maths-CBSE

How do you find the angle of the resultant vector class 11 physics CBSE

Why is chloroform kept in dark coloured bottles class 12 chemistry CBSE

Trending doubts
How many sides does a circle have a 10 sides b 20 sides class 8 maths CBSE

What is BLO What is the full form of BLO class 8 social science CBSE

Citizens of India can vote at the age of A 18 years class 8 social science CBSE

Full form of STD, ISD and PCO

One cusec is equal to how many liters class 8 maths CBSE

10 slogans on organ donation class 8 english CBSE


