Answer
Verified
437.1k+ views
Hint: First, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required. Then, we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days. Then, to get the amount of work done in one day by A, B and C, divide it by 2.
Complete step-by-step answer:
In this question, we are supposed to find the number of days taken by A, B and C together to finish the work when the conditions are given that A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days.
So, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required.
Then, by using this condition, we get the following condition for the work done by A and B as:
$ \dfrac{1}{12} $
Similarly, we get the following condition for the work done by B and C as:
$ \dfrac{1}{15} $
Again, we get the following condition for the work done by C and A as:
$ \dfrac{1}{20} $
So, if we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days.
So, the two days work of A, B and C is given by:
$ \dfrac{1}{12}+\dfrac{1}{15}+\dfrac{1}{20} $
Then, solve the above expression for getting the total value of work done by A, B and C in two days as:
$ \begin{align}
& \dfrac{5+4+3}{60}=\dfrac{12}{60} \\
& \Rightarrow \dfrac{1}{5} \\
\end{align} $
So, the amount of work done by A, B and C in two days is $ \dfrac{1}{5} $ .
Then to get the amount of work done in one day by A, B and C is given by:
$ \dfrac{1}{5}\times \dfrac{1}{2}=\dfrac{1}{10} $
So, A, B and C all together complete the work in 10 days.
So, the correct answer is “Option A”.
Note: Now, to solve these types of questions we need to know some of the basics of the work and time concept as we can make mistakes in the fact that more days are required to complete more work but less number of people are required to complete more work. So, the above fact defines that work is directly proportional to number of days but inversely proportional to the men required.
Complete step-by-step answer:
In this question, we are supposed to find the number of days taken by A, B and C together to finish the work when the conditions are given that A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days.
So, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required.
Then, by using this condition, we get the following condition for the work done by A and B as:
$ \dfrac{1}{12} $
Similarly, we get the following condition for the work done by B and C as:
$ \dfrac{1}{15} $
Again, we get the following condition for the work done by C and A as:
$ \dfrac{1}{20} $
So, if we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days.
So, the two days work of A, B and C is given by:
$ \dfrac{1}{12}+\dfrac{1}{15}+\dfrac{1}{20} $
Then, solve the above expression for getting the total value of work done by A, B and C in two days as:
$ \begin{align}
& \dfrac{5+4+3}{60}=\dfrac{12}{60} \\
& \Rightarrow \dfrac{1}{5} \\
\end{align} $
So, the amount of work done by A, B and C in two days is $ \dfrac{1}{5} $ .
Then to get the amount of work done in one day by A, B and C is given by:
$ \dfrac{1}{5}\times \dfrac{1}{2}=\dfrac{1}{10} $
So, A, B and C all together complete the work in 10 days.
So, the correct answer is “Option A”.
Note: Now, to solve these types of questions we need to know some of the basics of the work and time concept as we can make mistakes in the fact that more days are required to complete more work but less number of people are required to complete more work. So, the above fact defines that work is directly proportional to number of days but inversely proportional to the men required.
Recently Updated Pages
Mark and label the given geoinformation on the outline class 11 social science CBSE
When people say No pun intended what does that mea class 8 english CBSE
Name the states which share their boundary with Indias class 9 social science CBSE
Give an account of the Northern Plains of India class 9 social science CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
Advantages and disadvantages of science
Trending doubts
Bimbisara was the founder of dynasty A Nanda B Haryanka class 6 social science CBSE
Which are the Top 10 Largest Countries of the World?
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Differentiate between homogeneous and heterogeneous class 12 chemistry CBSE
10 examples of evaporation in daily life with explanations
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
How do you graph the function fx 4x class 9 maths CBSE
Difference Between Plant Cell and Animal Cell