A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days then the number of days taken by A, B and C together to finish the work are:
(a) 10 days
(b) 12 days
(c) 14 days
(d) 15 days
Answer
Verified
475.2k+ views
Hint: First, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required. Then, we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days. Then, to get the amount of work done in one day by A, B and C, divide it by 2.
Complete step-by-step answer:
In this question, we are supposed to find the number of days taken by A, B and C together to finish the work when the conditions are given that A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days.
So, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required.
Then, by using this condition, we get the following condition for the work done by A and B as:
$ \dfrac{1}{12} $
Similarly, we get the following condition for the work done by B and C as:
$ \dfrac{1}{15} $
Again, we get the following condition for the work done by C and A as:
$ \dfrac{1}{20} $
So, if we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days.
So, the two days work of A, B and C is given by:
$ \dfrac{1}{12}+\dfrac{1}{15}+\dfrac{1}{20} $
Then, solve the above expression for getting the total value of work done by A, B and C in two days as:
$ \begin{align}
& \dfrac{5+4+3}{60}=\dfrac{12}{60} \\
& \Rightarrow \dfrac{1}{5} \\
\end{align} $
So, the amount of work done by A, B and C in two days is $ \dfrac{1}{5} $ .
Then to get the amount of work done in one day by A, B and C is given by:
$ \dfrac{1}{5}\times \dfrac{1}{2}=\dfrac{1}{10} $
So, A, B and C all together complete the work in 10 days.
So, the correct answer is “Option A”.
Note: Now, to solve these types of questions we need to know some of the basics of the work and time concept as we can make mistakes in the fact that more days are required to complete more work but less number of people are required to complete more work. So, the above fact defines that work is directly proportional to number of days but inversely proportional to the men required.
Complete step-by-step answer:
In this question, we are supposed to find the number of days taken by A, B and C together to finish the work when the conditions are given that A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days.
So, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required.
Then, by using this condition, we get the following condition for the work done by A and B as:
$ \dfrac{1}{12} $
Similarly, we get the following condition for the work done by B and C as:
$ \dfrac{1}{15} $
Again, we get the following condition for the work done by C and A as:
$ \dfrac{1}{20} $
So, if we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days.
So, the two days work of A, B and C is given by:
$ \dfrac{1}{12}+\dfrac{1}{15}+\dfrac{1}{20} $
Then, solve the above expression for getting the total value of work done by A, B and C in two days as:
$ \begin{align}
& \dfrac{5+4+3}{60}=\dfrac{12}{60} \\
& \Rightarrow \dfrac{1}{5} \\
\end{align} $
So, the amount of work done by A, B and C in two days is $ \dfrac{1}{5} $ .
Then to get the amount of work done in one day by A, B and C is given by:
$ \dfrac{1}{5}\times \dfrac{1}{2}=\dfrac{1}{10} $
So, A, B and C all together complete the work in 10 days.
So, the correct answer is “Option A”.
Note: Now, to solve these types of questions we need to know some of the basics of the work and time concept as we can make mistakes in the fact that more days are required to complete more work but less number of people are required to complete more work. So, the above fact defines that work is directly proportional to number of days but inversely proportional to the men required.
Recently Updated Pages
Master Class 12 Business Studies: Engaging Questions & Answers for Success
Master Class 12 English: Engaging Questions & Answers for Success
Master Class 12 Social Science: Engaging Questions & Answers for Success
Master Class 12 Chemistry: Engaging Questions & Answers for Success
Class 12 Question and Answer - Your Ultimate Solutions Guide
Master Class 11 English: Engaging Questions & Answers for Success
Trending doubts
When people say No pun intended what does that mea class 8 english CBSE
What is BLO What is the full form of BLO class 8 social science CBSE
Which king started the organization of the Kumbh fair class 8 social science CBSE
Advantages and disadvantages of science
Write a letter to the Municipal Commissioner to inform class 8 english CBSE
Summary of the poem Where the Mind is Without Fear class 8 english CBSE