Answer
Verified
396k+ views
Hint: First, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required. Then, we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days. Then, to get the amount of work done in one day by A, B and C, divide it by 2.
Complete step-by-step answer:
In this question, we are supposed to find the number of days taken by A, B and C together to finish the work when the conditions are given that A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days.
So, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required.
Then, by using this condition, we get the following condition for the work done by A and B as:
$ \dfrac{1}{12} $
Similarly, we get the following condition for the work done by B and C as:
$ \dfrac{1}{15} $
Again, we get the following condition for the work done by C and A as:
$ \dfrac{1}{20} $
So, if we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days.
So, the two days work of A, B and C is given by:
$ \dfrac{1}{12}+\dfrac{1}{15}+\dfrac{1}{20} $
Then, solve the above expression for getting the total value of work done by A, B and C in two days as:
$ \begin{align}
& \dfrac{5+4+3}{60}=\dfrac{12}{60} \\
& \Rightarrow \dfrac{1}{5} \\
\end{align} $
So, the amount of work done by A, B and C in two days is $ \dfrac{1}{5} $ .
Then to get the amount of work done in one day by A, B and C is given by:
$ \dfrac{1}{5}\times \dfrac{1}{2}=\dfrac{1}{10} $
So, A, B and C all together complete the work in 10 days.
So, the correct answer is “Option A”.
Note: Now, to solve these types of questions we need to know some of the basics of the work and time concept as we can make mistakes in the fact that more days are required to complete more work but less number of people are required to complete more work. So, the above fact defines that work is directly proportional to number of days but inversely proportional to the men required.
Complete step-by-step answer:
In this question, we are supposed to find the number of days taken by A, B and C together to finish the work when the conditions are given that A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days.
So, before proceeding for this, we must know the following condition that the work done is always directly proportional to the number of days required.
Then, by using this condition, we get the following condition for the work done by A and B as:
$ \dfrac{1}{12} $
Similarly, we get the following condition for the work done by B and C as:
$ \dfrac{1}{15} $
Again, we get the following condition for the work done by C and A as:
$ \dfrac{1}{20} $
So, if we add all the above cases, we can see that A, B, C all the coming two times which indicate that the addition of these three equations gives the amount of work done by A, B and C in two days.
So, the two days work of A, B and C is given by:
$ \dfrac{1}{12}+\dfrac{1}{15}+\dfrac{1}{20} $
Then, solve the above expression for getting the total value of work done by A, B and C in two days as:
$ \begin{align}
& \dfrac{5+4+3}{60}=\dfrac{12}{60} \\
& \Rightarrow \dfrac{1}{5} \\
\end{align} $
So, the amount of work done by A, B and C in two days is $ \dfrac{1}{5} $ .
Then to get the amount of work done in one day by A, B and C is given by:
$ \dfrac{1}{5}\times \dfrac{1}{2}=\dfrac{1}{10} $
So, A, B and C all together complete the work in 10 days.
So, the correct answer is “Option A”.
Note: Now, to solve these types of questions we need to know some of the basics of the work and time concept as we can make mistakes in the fact that more days are required to complete more work but less number of people are required to complete more work. So, the above fact defines that work is directly proportional to number of days but inversely proportional to the men required.
Recently Updated Pages
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Find the values of other five trigonometric functions class 10 maths CBSE
Trending doubts
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Two charges are placed at a certain distance apart class 12 physics CBSE
Difference Between Plant Cell and Animal Cell
What organs are located on the left side of your body class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
The planet nearest to earth is A Mercury B Venus C class 6 social science CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
What is BLO What is the full form of BLO class 8 social science CBSE