
Raman alone can finish a piece of work in 15 days, and Suman alone can do it in 18 days. If both of them work together, how much time will they take to finish the work?
Answer
611.4k+ views
Hint: The total amount of work to be done remains constant irrespective of the factor of who is doing the work. Let the work capacities of the two workers be x and y respectively. So, the total work to be finished comes to be 15x, in terms of x and 18y, in terms of y. The work capacity when both works together is x+y, which you need to use in the final equation.
Complete step by step answer:
Let the work done by Raman per day be x.
Let the work done by Suman per day be y.
Total work done in n number days is given by:
$n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
Now, try to interpret the statement given in the question in mathematical terms using the above formula, we get:
$\text{Total work that needs to be completed=15x}................\text{(i)}$ .
Also;
$\text{Total work that needs to be completed=18y}$ .
Total work is independent of the worker doing the work.
$\therefore 15x=18y$
$\Rightarrow 5x=6y$
$\Rightarrow \dfrac{5x}{6}=y............(ii)$
Let the number of days taken to finish the work when both workers work together be t days.
If both Suman and Raman work together.
$\text{Total work that needs to be completed = }n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
$\Rightarrow \text{Total work that needs to be completed = t}(x+y)$ .
Substituting Total work from equation (i).
$\text{15x = t}(x+y)$
On substituting the value of y from equation (ii), we get:
$\text{15x = t}(x+\dfrac{5x}{6})$
$\Rightarrow \text{15 = t}(1+\dfrac{5}{6})$
$\Rightarrow \text{15 = }\left( \dfrac{6+5}{6} \right)t$
$\Rightarrow \text{15 = }\left( \dfrac{11}{6} \right)t$
$\therefore t=\dfrac{90}{11}=8.182\text{ Days}$ .
Converting 0.182 days to hours = $0.182\times 24=4.368\text{ hours}$ .
Converting 0.368 hours to minutes = $.368\times 60=22.08\text{ minutes}$ .
So, we can conclude that if both Raman and Suman work together, it will take them 8 complete days along with 4 hours and 22 minutes of the ${{9}^{th}}$ day.
Note: Questions including work, have two things to be wisely selected. One is the elements of the problem that you are treating as variables, and the other is the unit of work. You can either let work done per unit time of each worker as variables or the total work to be a variable. The choice of unit and element for variable decides the complexity of solving.
Complete step by step answer:
Let the work done by Raman per day be x.
Let the work done by Suman per day be y.
Total work done in n number days is given by:
$n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
Now, try to interpret the statement given in the question in mathematical terms using the above formula, we get:
$\text{Total work that needs to be completed=15x}................\text{(i)}$ .
Also;
$\text{Total work that needs to be completed=18y}$ .
Total work is independent of the worker doing the work.
$\therefore 15x=18y$
$\Rightarrow 5x=6y$
$\Rightarrow \dfrac{5x}{6}=y............(ii)$
Let the number of days taken to finish the work when both workers work together be t days.
If both Suman and Raman work together.
$\text{Total work that needs to be completed = }n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
$\Rightarrow \text{Total work that needs to be completed = t}(x+y)$ .
Substituting Total work from equation (i).
$\text{15x = t}(x+y)$
On substituting the value of y from equation (ii), we get:
$\text{15x = t}(x+\dfrac{5x}{6})$
$\Rightarrow \text{15 = t}(1+\dfrac{5}{6})$
$\Rightarrow \text{15 = }\left( \dfrac{6+5}{6} \right)t$
$\Rightarrow \text{15 = }\left( \dfrac{11}{6} \right)t$
$\therefore t=\dfrac{90}{11}=8.182\text{ Days}$ .
Converting 0.182 days to hours = $0.182\times 24=4.368\text{ hours}$ .
Converting 0.368 hours to minutes = $.368\times 60=22.08\text{ minutes}$ .
So, we can conclude that if both Raman and Suman work together, it will take them 8 complete days along with 4 hours and 22 minutes of the ${{9}^{th}}$ day.
Note: Questions including work, have two things to be wisely selected. One is the elements of the problem that you are treating as variables, and the other is the unit of work. You can either let work done per unit time of each worker as variables or the total work to be a variable. The choice of unit and element for variable decides the complexity of solving.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
What is the median of the first 10 natural numbers class 10 maths CBSE

Which women's tennis player has 24 Grand Slam singles titles?

Who is the Brand Ambassador of Incredible India?

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

A moving boat is observed from the top of a 150 m high class 10 maths CBSE

