
In how many days can 10 women finish a work? 10 men can complete the work in 6days. 10 men and 10 women can together complete the work in $3\dfrac{3}{7}$ days. If 10 men work for three days and thereafter 10 women replace them, the remaining work is complete in 4 days.
Answer
507.9k+ views
Hint: In the given question, we are given various situations of work done. Men and women were given some work, so for the same we are given various situations like time taken by 10 men to complete work is 6 days and if 10 men and women work together then it is $3\dfrac{3}{7}$days and further after defining number of men and women we are given situation and are asked to find the time taken by 10 women.
Complete step-by-step solution:
According to the question, we need to find the work done by 10 women and time taken by men and women and men alone to do the same work is given.
Now, work done by 10 women in one day is $\dfrac{7}{24}-\dfrac{1}{6}=\dfrac{1}{8}$
Therefore, 10 women can complete the work in 8 days.
Now, by using second and third condition, let 10 men can finish work in x days and 10 women can finish work in y days then $\Rightarrow \dfrac{1}{x}+\dfrac{1}{y}=\dfrac{7}{24}$ and from second and third condition, $\dfrac{3}{x}+\dfrac{4}{y}=1$ and we know x is 6 days.
Therefore,
$\begin{align}
& \dfrac{4}{y}=\dfrac{1}{2} \\
& \Rightarrow y=8 \\
\end{align}$
Hence, the time taken by 10 women to complete the work is 8 days.
Note: In such questions, we need to be aware of the concept of work done and need to find the value in one unit for every man and woman and the one-day task in order to correctly interpret the question and get the correct answer.
Complete step-by-step solution:
According to the question, we need to find the work done by 10 women and time taken by men and women and men alone to do the same work is given.
Now, work done by 10 women in one day is $\dfrac{7}{24}-\dfrac{1}{6}=\dfrac{1}{8}$
Therefore, 10 women can complete the work in 8 days.
Now, by using second and third condition, let 10 men can finish work in x days and 10 women can finish work in y days then $\Rightarrow \dfrac{1}{x}+\dfrac{1}{y}=\dfrac{7}{24}$ and from second and third condition, $\dfrac{3}{x}+\dfrac{4}{y}=1$ and we know x is 6 days.
Therefore,
$\begin{align}
& \dfrac{4}{y}=\dfrac{1}{2} \\
& \Rightarrow y=8 \\
\end{align}$
Hence, the time taken by 10 women to complete the work is 8 days.
Note: In such questions, we need to be aware of the concept of work done and need to find the value in one unit for every man and woman and the one-day task in order to correctly interpret the question and get the correct answer.
Recently Updated Pages
The number of solutions in x in 02pi for which sqrt class 12 maths CBSE

Write any two methods of preparation of phenol Give class 12 chemistry CBSE

Differentiate between action potential and resting class 12 biology CBSE

Two plane mirrors arranged at right angles to each class 12 physics CBSE

Which of the following molecules is are chiral A I class 12 chemistry CBSE

Name different types of neurons and give one function class 12 biology CBSE

Trending doubts
What is BLO What is the full form of BLO class 8 social science CBSE

What are the 12 elements of nature class 8 chemistry CBSE

Full form of STD, ISD and PCO

What are gulf countries and why they are called Gulf class 8 social science CBSE

Citizens of India can vote at the age of A 18 years class 8 social science CBSE

What is the difference between rai and mustard see class 8 biology CBSE

