
If (x+1) men will do the work in (x+1) days, then find the number of days in which (x+2) men can do the same work?
Answer
615.9k+ views
Hint- Here, we will proceed by finding the number of man-days in both the cases mentioned in the problem statement and then using the concept that the total number of man-days will always remain constant.
Complete step-by-step solution -
Given, a specific amount of work is completed by (x+1) men in (x+1) days.
Here, we have to find the number of days taken to complete the same amount of work when (x+2) men are doing the work.
Let this number of days taken to complete the same amount of work when (x+2) men are doing the work be y days.
As we know that the number of men multiplied by the number of days that they take to complete the work will give the number of man-days required to do the work. The total number of man-days required to complete a specific task is always constant.
For the first case,
Number of men = (x+1) men
Number of days = (x+1) days
Total number of man-days = (Number of men)$ \times $(Number of days)
$ \Rightarrow $Total number of man-days = (x+1)$ \times $(x+1) = ${\left( {x + 1} \right)^2}$
For the second case,
Number of men = (x+2) men
Number of days = y days
Total number of man-days = (Number of men)$ \times $(Number of days)
$ \Rightarrow $Total number of man-days = (x+2)$ \times $(y) = y(x+2)
Since, the total number of man-days needs to be constant (i.e., equal for both the above discussed cases)
So, \[{\left( {x + 1} \right)^2} = y\left( {x + 2} \right)\]
\[ \Rightarrow y = \dfrac{{{{\left( {x + 1} \right)}^2}}}{{\left( {x + 2} \right)}}\]
Therefore, the number of days in which (x+2) men can do the same work is equal to \[\dfrac{{{{\left( {x + 1} \right)}^2}}}{{\left( {x + 2} \right)}}\] days.
Note- This man-days concept states that for same amount of work to be done, the number of men and number of days are inversely proportional to each other i.e., if the number of men increases then the number of days required to complete the same work decreases and if the number of men decreases then the number of days required to complete the same work increases.
Complete step-by-step solution -
Given, a specific amount of work is completed by (x+1) men in (x+1) days.
Here, we have to find the number of days taken to complete the same amount of work when (x+2) men are doing the work.
Let this number of days taken to complete the same amount of work when (x+2) men are doing the work be y days.
As we know that the number of men multiplied by the number of days that they take to complete the work will give the number of man-days required to do the work. The total number of man-days required to complete a specific task is always constant.
For the first case,
Number of men = (x+1) men
Number of days = (x+1) days
Total number of man-days = (Number of men)$ \times $(Number of days)
$ \Rightarrow $Total number of man-days = (x+1)$ \times $(x+1) = ${\left( {x + 1} \right)^2}$
For the second case,
Number of men = (x+2) men
Number of days = y days
Total number of man-days = (Number of men)$ \times $(Number of days)
$ \Rightarrow $Total number of man-days = (x+2)$ \times $(y) = y(x+2)
Since, the total number of man-days needs to be constant (i.e., equal for both the above discussed cases)
So, \[{\left( {x + 1} \right)^2} = y\left( {x + 2} \right)\]
\[ \Rightarrow y = \dfrac{{{{\left( {x + 1} \right)}^2}}}{{\left( {x + 2} \right)}}\]
Therefore, the number of days in which (x+2) men can do the same work is equal to \[\dfrac{{{{\left( {x + 1} \right)}^2}}}{{\left( {x + 2} \right)}}\] days.
Note- This man-days concept states that for same amount of work to be done, the number of men and number of days are inversely proportional to each other i.e., if the number of men increases then the number of days required to complete the same work decreases and if the number of men decreases then the number of days required to complete the same work increases.
Recently Updated Pages
Basicity of sulphurous acid and sulphuric acid are

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Computer Science: Engaging Questions & Answers for Success

Class 10 Question and Answer - Your Ultimate Solutions Guide

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Trending doubts
Who is known as the "Little Master" in Indian cricket history?

A boat goes 24 km upstream and 28 km downstream in class 10 maths CBSE

Who Won 36 Oscar Awards? Record Holder Revealed

Why is there a time difference of about 5 hours between class 10 social science CBSE

Explain the Treaty of Vienna of 1815 class 10 social science CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

