
If 20 men working together can finish a job in 20 days, then find the number of days taken by 25 men of the same capacity to finish the job.
Answer
506.7k+ views
Hint: It is given that 20 men can finish a job in 20 days. Calculate the time required by 1 man to finish that job. The time required by one man to finish that particular job will be \[20\times 20\] . Then, calculate the time required by 25 men to finish that job by dividing the time taken by 1 man to finish that job, by 25 and then solve further.
Complete step-by-step answer:
According to the question it is given that the time required by 20 men to finish the job is 20 days.It is asked to find the number of days required by 25 men to finish that particular job.
Time required by 20 men to finish a job = 20 days.
So, the time required by 1 man to finish that particular job = \[20\times 20\] days.
Therefore, the time required by 25 men to finish that particular job = \[\dfrac{20\times 20}{25}\] .
On solving we get,
\[\begin{align}
& =\dfrac{20\times 20}{25} \\
& =16 \\
\end{align}\]
Hence, the time required to finish that job by 25 men is 16 days.
Note: In this question, while calculating the time required by 1 man to finish the job one might get it as \[\dfrac{20}{20}\] . If we do so, then we will get the time required to finish the job by 1 man less than the time required by 20 men to finish that job which is practically impossible. It should be written as \[20\times 20\] .
Complete step-by-step answer:
According to the question it is given that the time required by 20 men to finish the job is 20 days.It is asked to find the number of days required by 25 men to finish that particular job.
Time required by 20 men to finish a job = 20 days.
So, the time required by 1 man to finish that particular job = \[20\times 20\] days.
Therefore, the time required by 25 men to finish that particular job = \[\dfrac{20\times 20}{25}\] .
On solving we get,
\[\begin{align}
& =\dfrac{20\times 20}{25} \\
& =16 \\
\end{align}\]
Hence, the time required to finish that job by 25 men is 16 days.
Note: In this question, while calculating the time required by 1 man to finish the job one might get it as \[\dfrac{20}{20}\] . If we do so, then we will get the time required to finish the job by 1 man less than the time required by 20 men to finish that job which is practically impossible. It should be written as \[20\times 20\] .
Recently Updated Pages
The correct geometry and hybridization for XeF4 are class 11 chemistry CBSE

Water softening by Clarks process uses ACalcium bicarbonate class 11 chemistry CBSE

With reference to graphite and diamond which of the class 11 chemistry CBSE

A certain household has consumed 250 units of energy class 11 physics CBSE

The lightest metal known is A beryllium B lithium C class 11 chemistry CBSE

What is the formula mass of the iodine molecule class 11 chemistry CBSE

Trending doubts
When Sambhaji Maharaj died a 11 February 1689 b 11 class 8 social science CBSE

Write the smallest number divisible by both 306 and class 8 maths CBSE

What is 1 divided by 0 class 8 maths CBSE

A circle can have parallel tangents at the most class 8 maths CBSE

State the differences between manure and fertilize class 8 biology CBSE

What is the collective noun for soldiers class 8 english CBSE
