
A takes 10 days less than the time taken by B to finish a piece of work if both A and B together can finish the work in 12 days the time taken by B to finish the work is
$
(a){\text{ 20 days}} \\
(b){\text{ 30 days}} \\
(c){\text{ 40 days}} \\
(d){\text{ 50 days}} \\
$
Answer
618.9k+ views
Hint: In this question there is a relation given between the time taken by A and B to finish a work, so let the days taken by B to finish the work alone be some variable. Use the information provided in the question to formulate an equation in order to solve this variable.
Complete step-by-step answer:
Let B alone finish the work in x days.
And it is given that A takes 10 days less to finish the work from B.
Therefore A can finish the work in (x - 10) days.
So A’s one day work is $ = \dfrac{1}{{x - 10}}$………………… (1)
And B’s one day work is $ = \dfrac{1}{x}$……………………… (2)
Now it is given that both A and B together can finish the work in 12 days.
Therefore together A and B one day work is =$\dfrac{1}{{12}}$.
So A’s one day work + B’s one day work = together A and B one day work.
$ \Rightarrow \dfrac{1}{{x - 10}} + \dfrac{1}{x} = \dfrac{1}{{12}}$
Now simplify the above equation we have,
$ \Rightarrow x + x - 10 = \dfrac{{x\left( {x - 10} \right)}}{{12}}$
$ \Rightarrow 24x - 120 = {x^2} - 10x$
$ \Rightarrow {x^2} - 34x + 120 = 0$
Now factorize the above equation we have,
$ \Rightarrow {x^2} - 4x - 30x + 120 = 0$
$ \Rightarrow x\left( {x - 4} \right) - 30\left( {x - 4} \right) = 0$
$ \Rightarrow \left( {x - 4} \right)\left( {x - 30} \right) = 0$
$ \Rightarrow x = 4,30$
As x = 4 cannot possible because they together finish the work in 12 days,
Therefore the possible value of x is 30 days.
So, B can finish the work in 30 days.
Hence option (B) is correct.
Note: Whenever we come across such basic day and time questions the key concept to understand is that the work done by a person in one day in addition to the work done by another person in one day will surely be equal to the overall work done on that particular day. This concept will help getting on the right track while solving problems of such type.
Complete step-by-step answer:
Let B alone finish the work in x days.
And it is given that A takes 10 days less to finish the work from B.
Therefore A can finish the work in (x - 10) days.
So A’s one day work is $ = \dfrac{1}{{x - 10}}$………………… (1)
And B’s one day work is $ = \dfrac{1}{x}$……………………… (2)
Now it is given that both A and B together can finish the work in 12 days.
Therefore together A and B one day work is =$\dfrac{1}{{12}}$.
So A’s one day work + B’s one day work = together A and B one day work.
$ \Rightarrow \dfrac{1}{{x - 10}} + \dfrac{1}{x} = \dfrac{1}{{12}}$
Now simplify the above equation we have,
$ \Rightarrow x + x - 10 = \dfrac{{x\left( {x - 10} \right)}}{{12}}$
$ \Rightarrow 24x - 120 = {x^2} - 10x$
$ \Rightarrow {x^2} - 34x + 120 = 0$
Now factorize the above equation we have,
$ \Rightarrow {x^2} - 4x - 30x + 120 = 0$
$ \Rightarrow x\left( {x - 4} \right) - 30\left( {x - 4} \right) = 0$
$ \Rightarrow \left( {x - 4} \right)\left( {x - 30} \right) = 0$
$ \Rightarrow x = 4,30$
As x = 4 cannot possible because they together finish the work in 12 days,
Therefore the possible value of x is 30 days.
So, B can finish the work in 30 days.
Hence option (B) is correct.
Note: Whenever we come across such basic day and time questions the key concept to understand is that the work done by a person in one day in addition to the work done by another person in one day will surely be equal to the overall work done on that particular day. This concept will help getting on the right track while solving problems of such type.
Recently Updated Pages
Master Class 7 English: Engaging Questions & Answers for Success

Master Class 7 Maths: Engaging Questions & Answers for Success

Master Class 7 Science: Engaging Questions & Answers for Success

Class 7 Question and Answer - Your Ultimate Solutions Guide

Master Class 9 General Knowledge: Engaging Questions & Answers for Success

Master Class 9 Social Science: Engaging Questions & Answers for Success

Trending doubts
The value of 6 more than 7 is A 1 B 1 C 13 D 13 class 7 maths CBSE

Convert 200 Million dollars in rupees class 7 maths CBSE

List of coprime numbers from 1 to 100 class 7 maths CBSE

AIM To prepare stained temporary mount of onion peel class 7 biology CBSE

The plural of Chief is Chieves A True B False class 7 english CBSE

Write a letter to the editor of the national daily class 7 english CBSE


