
A takes 10 days less than the time taken by B to finish a piece of work if both A and B together can finish the work in 12 days the time taken by B to finish the work is
$
(a){\text{ 20 days}} \\
(b){\text{ 30 days}} \\
(c){\text{ 40 days}} \\
(d){\text{ 50 days}} \\
$
Answer
592.5k+ views
Hint: In this question there is a relation given between the time taken by A and B to finish a work, so let the days taken by B to finish the work alone be some variable. Use the information provided in the question to formulate an equation in order to solve this variable.
Complete step-by-step answer:
Let B alone finish the work in x days.
And it is given that A takes 10 days less to finish the work from B.
Therefore A can finish the work in (x - 10) days.
So A’s one day work is $ = \dfrac{1}{{x - 10}}$………………… (1)
And B’s one day work is $ = \dfrac{1}{x}$……………………… (2)
Now it is given that both A and B together can finish the work in 12 days.
Therefore together A and B one day work is =$\dfrac{1}{{12}}$.
So A’s one day work + B’s one day work = together A and B one day work.
$ \Rightarrow \dfrac{1}{{x - 10}} + \dfrac{1}{x} = \dfrac{1}{{12}}$
Now simplify the above equation we have,
$ \Rightarrow x + x - 10 = \dfrac{{x\left( {x - 10} \right)}}{{12}}$
$ \Rightarrow 24x - 120 = {x^2} - 10x$
$ \Rightarrow {x^2} - 34x + 120 = 0$
Now factorize the above equation we have,
$ \Rightarrow {x^2} - 4x - 30x + 120 = 0$
$ \Rightarrow x\left( {x - 4} \right) - 30\left( {x - 4} \right) = 0$
$ \Rightarrow \left( {x - 4} \right)\left( {x - 30} \right) = 0$
$ \Rightarrow x = 4,30$
As x = 4 cannot possible because they together finish the work in 12 days,
Therefore the possible value of x is 30 days.
So, B can finish the work in 30 days.
Hence option (B) is correct.
Note: Whenever we come across such basic day and time questions the key concept to understand is that the work done by a person in one day in addition to the work done by another person in one day will surely be equal to the overall work done on that particular day. This concept will help getting on the right track while solving problems of such type.
Complete step-by-step answer:
Let B alone finish the work in x days.
And it is given that A takes 10 days less to finish the work from B.
Therefore A can finish the work in (x - 10) days.
So A’s one day work is $ = \dfrac{1}{{x - 10}}$………………… (1)
And B’s one day work is $ = \dfrac{1}{x}$……………………… (2)
Now it is given that both A and B together can finish the work in 12 days.
Therefore together A and B one day work is =$\dfrac{1}{{12}}$.
So A’s one day work + B’s one day work = together A and B one day work.
$ \Rightarrow \dfrac{1}{{x - 10}} + \dfrac{1}{x} = \dfrac{1}{{12}}$
Now simplify the above equation we have,
$ \Rightarrow x + x - 10 = \dfrac{{x\left( {x - 10} \right)}}{{12}}$
$ \Rightarrow 24x - 120 = {x^2} - 10x$
$ \Rightarrow {x^2} - 34x + 120 = 0$
Now factorize the above equation we have,
$ \Rightarrow {x^2} - 4x - 30x + 120 = 0$
$ \Rightarrow x\left( {x - 4} \right) - 30\left( {x - 4} \right) = 0$
$ \Rightarrow \left( {x - 4} \right)\left( {x - 30} \right) = 0$
$ \Rightarrow x = 4,30$
As x = 4 cannot possible because they together finish the work in 12 days,
Therefore the possible value of x is 30 days.
So, B can finish the work in 30 days.
Hence option (B) is correct.
Note: Whenever we come across such basic day and time questions the key concept to understand is that the work done by a person in one day in addition to the work done by another person in one day will surely be equal to the overall work done on that particular day. This concept will help getting on the right track while solving problems of such type.
Recently Updated Pages
Master Class 11 Chemistry: Engaging Questions & Answers for Success

Master Class 12 English: Engaging Questions & Answers for Success

Master Class 12 Social Science: Engaging Questions & Answers for Success

Master Class 12 Chemistry: Engaging Questions & Answers for Success

If overrightarrow a overrightarrow b overrightarrow class 12 maths CBSE

If a b and c are unit coplanar vectors then left 2a class 12 maths CBSE

Trending doubts
Full Form of IASDMIPSIFSIRSPOLICE class 7 social science CBSE

The Chinese traveler Hiuen Tsang called the Prince class 7 social science CBSE

Convert 200 Million dollars in rupees class 7 maths CBSE

What are the controls affecting the climate of Ind class 7 social science CBSE

List of coprime numbers from 1 to 100 class 7 maths CBSE

What were the major teachings of Baba Guru Nanak class 7 social science CBSE


