
A takes 10 days less than the time taken by B to finish a piece of work if both A and B together can finish the work in 12 days the time taken by B to finish the work is
$
(a){\text{ 20 days}} \\
(b){\text{ 30 days}} \\
(c){\text{ 40 days}} \\
(d){\text{ 50 days}} \\
$
Answer
606k+ views
Hint: In this question there is a relation given between the time taken by A and B to finish a work, so let the days taken by B to finish the work alone be some variable. Use the information provided in the question to formulate an equation in order to solve this variable.
Complete step-by-step answer:
Let B alone finish the work in x days.
And it is given that A takes 10 days less to finish the work from B.
Therefore A can finish the work in (x - 10) days.
So A’s one day work is $ = \dfrac{1}{{x - 10}}$………………… (1)
And B’s one day work is $ = \dfrac{1}{x}$……………………… (2)
Now it is given that both A and B together can finish the work in 12 days.
Therefore together A and B one day work is =$\dfrac{1}{{12}}$.
So A’s one day work + B’s one day work = together A and B one day work.
$ \Rightarrow \dfrac{1}{{x - 10}} + \dfrac{1}{x} = \dfrac{1}{{12}}$
Now simplify the above equation we have,
$ \Rightarrow x + x - 10 = \dfrac{{x\left( {x - 10} \right)}}{{12}}$
$ \Rightarrow 24x - 120 = {x^2} - 10x$
$ \Rightarrow {x^2} - 34x + 120 = 0$
Now factorize the above equation we have,
$ \Rightarrow {x^2} - 4x - 30x + 120 = 0$
$ \Rightarrow x\left( {x - 4} \right) - 30\left( {x - 4} \right) = 0$
$ \Rightarrow \left( {x - 4} \right)\left( {x - 30} \right) = 0$
$ \Rightarrow x = 4,30$
As x = 4 cannot possible because they together finish the work in 12 days,
Therefore the possible value of x is 30 days.
So, B can finish the work in 30 days.
Hence option (B) is correct.
Note: Whenever we come across such basic day and time questions the key concept to understand is that the work done by a person in one day in addition to the work done by another person in one day will surely be equal to the overall work done on that particular day. This concept will help getting on the right track while solving problems of such type.
Complete step-by-step answer:
Let B alone finish the work in x days.
And it is given that A takes 10 days less to finish the work from B.
Therefore A can finish the work in (x - 10) days.
So A’s one day work is $ = \dfrac{1}{{x - 10}}$………………… (1)
And B’s one day work is $ = \dfrac{1}{x}$……………………… (2)
Now it is given that both A and B together can finish the work in 12 days.
Therefore together A and B one day work is =$\dfrac{1}{{12}}$.
So A’s one day work + B’s one day work = together A and B one day work.
$ \Rightarrow \dfrac{1}{{x - 10}} + \dfrac{1}{x} = \dfrac{1}{{12}}$
Now simplify the above equation we have,
$ \Rightarrow x + x - 10 = \dfrac{{x\left( {x - 10} \right)}}{{12}}$
$ \Rightarrow 24x - 120 = {x^2} - 10x$
$ \Rightarrow {x^2} - 34x + 120 = 0$
Now factorize the above equation we have,
$ \Rightarrow {x^2} - 4x - 30x + 120 = 0$
$ \Rightarrow x\left( {x - 4} \right) - 30\left( {x - 4} \right) = 0$
$ \Rightarrow \left( {x - 4} \right)\left( {x - 30} \right) = 0$
$ \Rightarrow x = 4,30$
As x = 4 cannot possible because they together finish the work in 12 days,
Therefore the possible value of x is 30 days.
So, B can finish the work in 30 days.
Hence option (B) is correct.
Note: Whenever we come across such basic day and time questions the key concept to understand is that the work done by a person in one day in addition to the work done by another person in one day will surely be equal to the overall work done on that particular day. This concept will help getting on the right track while solving problems of such type.
Recently Updated Pages
You are awaiting your class 10th results Meanwhile class 7 english CBSE

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Trending doubts
Convert 200 Million dollars in rupees class 7 maths CBSE

i What trees does Mr Wonka mention Which tree does class 7 english CBSE

What are the controls affecting the climate of Ind class 7 social science CBSE

What was the main occupation of early Aryans of rig class 7 social science CBSE

Write a letter to the editor of the national daily class 7 english CBSE

Welcome speech for Christmas day celebration class 7 english CBSE


