A started work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them working alone to finish the whole work?
A. 5 days, 8.5 days
B. 2.5 days, 7.5 days
C. 5 days. 15 days
D. 3 days, 15 days
Answer
653.4k+ views
Hint: In the above question, first of all, we will suppose A and B can do the work in x and y days. Then, we will find the work done by A or B in the given days by using the simply unitary method and write the sum of work that is equal to 1.
Complete step-by-step answer:
We have been given that, A started a work and left after working for 2 days and the remaining work is completed by B in 9 days. Also, if A left the work after working for 3 days, B would have finished the remaining work in 6 days.
Let us suppose, A and B can do the work in x and y days respectively.
Now, we know that the sum of work done by A and B is equal to 1.
In x days work done by \[\text{A }=\text{ 1}\]
In 1 day work done by \[\text{A }=\dfrac{1}{x}\]
So, in 2 day work done by \[\text{A }=\dfrac{2}{x}\]
Similarly, in 3 day work done by \[\text{A }=\dfrac{3}{x}\]
Again, In y days work done by \[\text{B }=\text{ 1}\]
In 1 day work done by \[\text{B }=\dfrac{1}{y}\]
So, in 9 days work done by \[\text{B }=\dfrac{9}{y}\]
Similarly, in 6 days work done by \[\text{B }=\dfrac{6}{y}\]
According to question, we have,
\[\begin{align}
& \dfrac{2}{x}+\dfrac{9}{y}=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (i)} \\
& \dfrac{3}{x}+\dfrac{6}{y}=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (ii)} \\
\end{align}\]
Let us suppose, \[\dfrac{1}{x}=a\text{ and }\dfrac{1}{y}=b,\] then, the equations become,
\[\begin{align}
& 2a+9b=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (iii)} \\
& 3a+6b=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (iv)} \\
\end{align}\]
On performing \[(iv)\times 2-(iii)\times 3,\] we get,
\[\begin{align}
& \left( 6a+12b \right)-\left( 6a+27b \right)=2-3 \\
& 6a+12b-6a-27b=-1 \\
\end{align}\]
On cancelling similar terms, we get,
\[\begin{align}
& -15b=-1 \\
& b=\dfrac{1}{15} \\
\end{align}\]
Since, \[b=\dfrac{1}{y}\]
\[\begin{align}
& \dfrac{1}{y}=\dfrac{1}{15} \\
& y=15\text{ }days \\
\end{align}\]
On substituting \[b=\dfrac{1}{15}\] in equation (iii), we get,
\[\begin{align}
& \Rightarrow 2a+9\times \dfrac{1}{15}=1 \\
& \Rightarrow 2a+\dfrac{3}{5}=1 \\
& \Rightarrow 2a=1-\dfrac{3}{5} \\
& \Rightarrow 2a=\dfrac{5-3}{5} \\
& \Rightarrow 2a=\dfrac{2}{5} \\
& \Rightarrow a=\dfrac{1}{5} \\
\end{align}\]
Since, \[a=\dfrac{1}{x}\]
\[\begin{align}
& \dfrac{1}{x}=\dfrac{1}{3} \\
& x=5\text{ days} \\
\end{align}\]
Therefore, A and B finish the work in 5 days and 15 days respectively. So, the correct option is C.
Note: While solving the equation \[\dfrac{1}{x}\text{ and }\dfrac{1}{y}\] it is better to take \[\dfrac{1}{x}\text{=a and }\dfrac{1}{y}=b\]. Otherwise, it is very difficult to solve the equation also, it will take you a lot of time. Also, remember that after solving the equation in a and b you have to further substitute the value of a and b in terms of x and y, which will give us the final answer.
Complete step-by-step answer:
We have been given that, A started a work and left after working for 2 days and the remaining work is completed by B in 9 days. Also, if A left the work after working for 3 days, B would have finished the remaining work in 6 days.
Let us suppose, A and B can do the work in x and y days respectively.
Now, we know that the sum of work done by A and B is equal to 1.
In x days work done by \[\text{A }=\text{ 1}\]
In 1 day work done by \[\text{A }=\dfrac{1}{x}\]
So, in 2 day work done by \[\text{A }=\dfrac{2}{x}\]
Similarly, in 3 day work done by \[\text{A }=\dfrac{3}{x}\]
Again, In y days work done by \[\text{B }=\text{ 1}\]
In 1 day work done by \[\text{B }=\dfrac{1}{y}\]
So, in 9 days work done by \[\text{B }=\dfrac{9}{y}\]
Similarly, in 6 days work done by \[\text{B }=\dfrac{6}{y}\]
According to question, we have,
\[\begin{align}
& \dfrac{2}{x}+\dfrac{9}{y}=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (i)} \\
& \dfrac{3}{x}+\dfrac{6}{y}=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (ii)} \\
\end{align}\]
Let us suppose, \[\dfrac{1}{x}=a\text{ and }\dfrac{1}{y}=b,\] then, the equations become,
\[\begin{align}
& 2a+9b=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (iii)} \\
& 3a+6b=1\text{ }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. }\text{. (iv)} \\
\end{align}\]
On performing \[(iv)\times 2-(iii)\times 3,\] we get,
\[\begin{align}
& \left( 6a+12b \right)-\left( 6a+27b \right)=2-3 \\
& 6a+12b-6a-27b=-1 \\
\end{align}\]
On cancelling similar terms, we get,
\[\begin{align}
& -15b=-1 \\
& b=\dfrac{1}{15} \\
\end{align}\]
Since, \[b=\dfrac{1}{y}\]
\[\begin{align}
& \dfrac{1}{y}=\dfrac{1}{15} \\
& y=15\text{ }days \\
\end{align}\]
On substituting \[b=\dfrac{1}{15}\] in equation (iii), we get,
\[\begin{align}
& \Rightarrow 2a+9\times \dfrac{1}{15}=1 \\
& \Rightarrow 2a+\dfrac{3}{5}=1 \\
& \Rightarrow 2a=1-\dfrac{3}{5} \\
& \Rightarrow 2a=\dfrac{5-3}{5} \\
& \Rightarrow 2a=\dfrac{2}{5} \\
& \Rightarrow a=\dfrac{1}{5} \\
\end{align}\]
Since, \[a=\dfrac{1}{x}\]
\[\begin{align}
& \dfrac{1}{x}=\dfrac{1}{3} \\
& x=5\text{ days} \\
\end{align}\]
Therefore, A and B finish the work in 5 days and 15 days respectively. So, the correct option is C.
Note: While solving the equation \[\dfrac{1}{x}\text{ and }\dfrac{1}{y}\] it is better to take \[\dfrac{1}{x}\text{=a and }\dfrac{1}{y}=b\]. Otherwise, it is very difficult to solve the equation also, it will take you a lot of time. Also, remember that after solving the equation in a and b you have to further substitute the value of a and b in terms of x and y, which will give us the final answer.
Recently Updated Pages
Master Class 11 English: Engaging Questions & Answers for Success

Master Class 11 Social Science: Engaging Questions & Answers for Success

Master Class 11 Maths: Engaging Questions & Answers for Success

Master Class 11 Biology: Engaging Questions & Answers for Success

Master Class 11 Physics: Engaging Questions & Answers for Success

Master Class 11 Chemistry: Engaging Questions & Answers for Success

Trending doubts
Difference Between Prokaryotic Cells and Eukaryotic Cells

Find the value of the expression given below sin 30circ class 11 maths CBSE

One Metric ton is equal to kg A 10000 B 1000 C 100 class 11 physics CBSE

Two of the body parts which do not appear in MRI are class 11 biology CBSE

10 examples of friction in our daily life

Draw a diagram of nephron and explain its structur class 11 biology CBSE

