
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. B can do the work in
(A) 12 days
(B) 15 days
(C) 20 days
(D) 30 days
Answer
588.6k+ views
Hint: Assume that A finishes the work in x days. It s given that A is thrice as good a workman as B so, A must be able to finish the work in one-third of the time taken by B. So, \[\text{Time taken by A}\,\text{to finish the work =}\dfrac{\text{Time taken by B}\,\text{to finish the work }}{3}\] . Using this, get the time taken by B to finish the work. Since the time taken by A is 10 less than the time taken by B to finish the work, we have to add 10 days in the time taken by A to make it equal to the time taken by B to finish the work. So,
\[\text{Time taken to finish the work by A+10=Time taken to finish the work by B}\] . Now, using this equation, get the value of x. Now, put the value of x in 3x which is equal to the time taken by B to finish the work.
Complete step-by-step answer:
According to the question, it is given that A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes.
First of all, let us assume that A finishes the work in x days ……………………..(1)
Since A is thrice as good a workman as B so, A must be able to finish the work in one-third of the time taken by B. Mathematically, we can express it as,
\[\text{Time taken by A}\,\text{to finish the work =}\dfrac{\text{Time taken by B}\,\text{to finish the work }}{3}\]……………………..(2)
Now, from equation (1) and equation (2), we get
\[\begin{align}
& \Rightarrow x\text{=}\dfrac{\text{Time taken by B}\,\text{to finish the work }}{3} \\
& \Rightarrow 3x=\text{Time taken by B}\,\text{to finish the work} \\
\end{align}\]
The time taken by B to finish the work is \[3x\] days ………………………..(3)
From equation (1) and equation (3), we have the time taken by A and B to finish the work.
It is given that A takes 10 days less than B to finish the work. Since the time taken by A is 10 less than the time taken by B to finish the work, we have to add 10 days in the time taken by A to make it equal to the time taken by B to finish the work. So,
\[\text{Time taken to finish the work by A+10=Time taken to finish the work by B}\] ………………………(4)
Now, from equation (1), equation (3), and equation (4), we get
\[\begin{align}
& \Rightarrow x\text{+10=}3x \\
& \Rightarrow 10=3x-x \\
& \Rightarrow 10=2x \\
\end{align}\]
\[\Rightarrow \dfrac{10}{2}=x\]
\[\Rightarrow 5=x\] ………………………..(5)
Putting the value of x from equation (5), in equation (3), we get
The time taken by B to finish the work = \[3x=3\times 5\] = 15 days.
Therefore, the time taken by B to finish the work is 15 days.
Hence, option (B) is the correct one.
Note: In this question, it is given that A is thrice as good a workman as B. So, one might think that the time taken by A to finish the work is also three times the time taken by B to finish that work. This is wrong because A is thrice as good a workman as B so, A must be able to finish the work in one-third of the time taken by B.
\[\text{Time taken to finish the work by A+10=Time taken to finish the work by B}\] . Now, using this equation, get the value of x. Now, put the value of x in 3x which is equal to the time taken by B to finish the work.
Complete step-by-step answer:
According to the question, it is given that A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes.
First of all, let us assume that A finishes the work in x days ……………………..(1)
Since A is thrice as good a workman as B so, A must be able to finish the work in one-third of the time taken by B. Mathematically, we can express it as,
\[\text{Time taken by A}\,\text{to finish the work =}\dfrac{\text{Time taken by B}\,\text{to finish the work }}{3}\]……………………..(2)
Now, from equation (1) and equation (2), we get
\[\begin{align}
& \Rightarrow x\text{=}\dfrac{\text{Time taken by B}\,\text{to finish the work }}{3} \\
& \Rightarrow 3x=\text{Time taken by B}\,\text{to finish the work} \\
\end{align}\]
The time taken by B to finish the work is \[3x\] days ………………………..(3)
From equation (1) and equation (3), we have the time taken by A and B to finish the work.
It is given that A takes 10 days less than B to finish the work. Since the time taken by A is 10 less than the time taken by B to finish the work, we have to add 10 days in the time taken by A to make it equal to the time taken by B to finish the work. So,
\[\text{Time taken to finish the work by A+10=Time taken to finish the work by B}\] ………………………(4)
Now, from equation (1), equation (3), and equation (4), we get
\[\begin{align}
& \Rightarrow x\text{+10=}3x \\
& \Rightarrow 10=3x-x \\
& \Rightarrow 10=2x \\
\end{align}\]
\[\Rightarrow \dfrac{10}{2}=x\]
\[\Rightarrow 5=x\] ………………………..(5)
Putting the value of x from equation (5), in equation (3), we get
The time taken by B to finish the work = \[3x=3\times 5\] = 15 days.
Therefore, the time taken by B to finish the work is 15 days.
Hence, option (B) is the correct one.
Note: In this question, it is given that A is thrice as good a workman as B. So, one might think that the time taken by A to finish the work is also three times the time taken by B to finish that work. This is wrong because A is thrice as good a workman as B so, A must be able to finish the work in one-third of the time taken by B.
Recently Updated Pages
What happens to glucose which enters nephron along class 10 biology CBSE

Write a dialogue with at least ten utterances between class 10 english CBSE

A circle is inscribed in an equilateral triangle and class 10 maths CBSE

When the JanmiKudian Act was passed that granted the class 10 social science CBSE

A sector containing an angle of 120 circ is cut off class 10 maths CBSE

The sum of digits of a two digit number is 13 If t-class-10-maths-ICSE

Trending doubts
The shortest day of the year in India

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

What is the missing number in the sequence 259142027 class 10 maths CBSE

