
A does half as much work as B in three fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it?
\[\begin{align}
& \text{A}.\text{3}0\text{ days} \\
& \text{B}.\text{35 days} \\
& \text{C}.\text{4}0\text{ days} \\
& \text{D}.\text{None of these} \\
\end{align}\]
Answer
503.4k+ views
Hint: For this question, we will first suppose days taken by B as x using the information we will calculate the number of days taken by A. Then we calculate both A and B's one day work in terms of x. Then we will equate both their one day’s work equal to $ \dfrac{1}{18} $ (As per question). Solving the equation, we will find the value of x and hence our required answer.
Complete step by step answer:
Let us suppose that B completes its work in x days. Now, we are given that A takes $ {{\dfrac{3}{4}}^{th}} $ time of B's work to complete half of the work.
So we can say that A takes $ \dfrac{3}{4}\times x $ days to complete half of the work.
So for the full work, it will take twice the number of days to complete half the work.
Therefore, number of days that A take to complete work $ \dfrac{3}{4}\times x\times 2=\dfrac{3}{2}x\text{ days} $ .
Now let us calculate their one-day work.
Days taken by A to complete total work $ \dfrac{3}{2}x\text{ days} $ .
So we can say, A's one day work $ \dfrac{2}{3x}\text{ days} $ .
Similarly, B's one day work $ \dfrac{1}{x} $ .
Now we are given that A and B together take 18 days to complete the whole work. Therefore, their combined one day work becomes $ \dfrac{1}{18} $ .
According to all the information, thus we can say that A's one day work + B's one day work = $ \dfrac{1}{18} $.
Therefore, $ \dfrac{2}{3x}+\dfrac{1}{x}=\dfrac{1}{18} $ .
Taking LCM as 3x we get, $ \dfrac{2+3}{3x}=\dfrac{1}{18}\Rightarrow \dfrac{5}{3x}=\dfrac{1}{18} $ .
Cross multiplying we get, $ 18\times 5=3x $ .
Dividing both sides by 3 we get, $ \dfrac{18\times 5}{3}=x\Rightarrow x=6\times 5\Rightarrow x=30 $ .
Therefore, the time taken by B to complete the work is 30 days.
Hence option A is the correct answer.
Note:
Students can make the mistake of taking $ \dfrac{3}{2}x+x $ as 18. But this is wrong as this sum requires inverse proportion because as the amount of work per day increases, the lesser the number of days is required. Take care in the calculation.
Complete step by step answer:
Let us suppose that B completes its work in x days. Now, we are given that A takes $ {{\dfrac{3}{4}}^{th}} $ time of B's work to complete half of the work.
So we can say that A takes $ \dfrac{3}{4}\times x $ days to complete half of the work.
So for the full work, it will take twice the number of days to complete half the work.
Therefore, number of days that A take to complete work $ \dfrac{3}{4}\times x\times 2=\dfrac{3}{2}x\text{ days} $ .
Now let us calculate their one-day work.
Days taken by A to complete total work $ \dfrac{3}{2}x\text{ days} $ .
So we can say, A's one day work $ \dfrac{2}{3x}\text{ days} $ .
Similarly, B's one day work $ \dfrac{1}{x} $ .
Now we are given that A and B together take 18 days to complete the whole work. Therefore, their combined one day work becomes $ \dfrac{1}{18} $ .
According to all the information, thus we can say that A's one day work + B's one day work = $ \dfrac{1}{18} $.
Therefore, $ \dfrac{2}{3x}+\dfrac{1}{x}=\dfrac{1}{18} $ .
Taking LCM as 3x we get, $ \dfrac{2+3}{3x}=\dfrac{1}{18}\Rightarrow \dfrac{5}{3x}=\dfrac{1}{18} $ .
Cross multiplying we get, $ 18\times 5=3x $ .
Dividing both sides by 3 we get, $ \dfrac{18\times 5}{3}=x\Rightarrow x=6\times 5\Rightarrow x=30 $ .
Therefore, the time taken by B to complete the work is 30 days.
Hence option A is the correct answer.
Note:
Students can make the mistake of taking $ \dfrac{3}{2}x+x $ as 18. But this is wrong as this sum requires inverse proportion because as the amount of work per day increases, the lesser the number of days is required. Take care in the calculation.
Recently Updated Pages
Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Class 10 Question and Answer - Your Ultimate Solutions Guide

Master Class 10 Computer Science: Engaging Questions & Answers for Success

Trending doubts
Why is there a time difference of about 5 hours between class 10 social science CBSE

When and how did Canada eventually gain its independence class 10 social science CBSE

Fill the blanks with proper collective nouns 1 A of class 10 english CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

Write examples of herbivores carnivores and omnivo class 10 biology CBSE

Which planet is known as the Watery Planet AJupiter class 10 social science CBSE
