“A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If he uses 4 people instead of three, how long should they take to complete the job?”
Answer
616.2k+ views
Hint: This question is solved using the Time and Work concept. Time and work problems deal with the simultaneous performance involving the efficiency of an individual or a group and the time taken by them to complete a piece of work.
Whenever some work is done, the total work itself can be taken as one unit.
Inverse Proportion: Two quantities A and B are said to be in inverse proportion if there is an increase in the quantity A, there will be a decrease in the quantity B and vice-versa. In other words, the product of their corresponding values should remain constant. This means that,
$A \times B = k$
where k is a positive number, then the quantities A and B are said to vary inversely.
So, if we increase the number of people on a job, then it will take less time to complete the job.
Complete step-by-step answer:
Let the number of days required by 4 persons to complete the job be x.
As we increase the number of persons, time taken would decrease.
We can say that,
$\begin{gathered}
{\text{Persons required (P)}} \propto \dfrac{1}{{{\text{Days to complete the job (D)}}}} \\
\Rightarrow P \propto \dfrac{1}{D} \\
\Rightarrow P = \dfrac{k}{D} \\
\Rightarrow P \times D = k \\
\end{gathered} $
where k is constant of proportionality.
Hence, the number of days and the number of persons required to complete the job are inversely proportional to each other.
$\begin{gathered}
\therefore {P_1}{D_1} = {P_2}{D_2} \\
3 \times 4 = 3 \times x \\
x = \dfrac{{3 \times 4}}{3} \\
x = 4 \\
\end{gathered} $
∴It would require 4 days to complete the job.
Note: Here, students must note that in these types of questions, first of all, it is very important to find what these quantities are and whether they are inversely proportional or directly proportional. And also remember the value of k that is constant will remain the same, and values of the quantities will change.
Whenever some work is done, the total work itself can be taken as one unit.
Inverse Proportion: Two quantities A and B are said to be in inverse proportion if there is an increase in the quantity A, there will be a decrease in the quantity B and vice-versa. In other words, the product of their corresponding values should remain constant. This means that,
$A \times B = k$
where k is a positive number, then the quantities A and B are said to vary inversely.
So, if we increase the number of people on a job, then it will take less time to complete the job.
Complete step-by-step answer:
Let the number of days required by 4 persons to complete the job be x.
| Number of days | 4 | x |
| Number of persons | 3 | 4 |
As we increase the number of persons, time taken would decrease.
We can say that,
$\begin{gathered}
{\text{Persons required (P)}} \propto \dfrac{1}{{{\text{Days to complete the job (D)}}}} \\
\Rightarrow P \propto \dfrac{1}{D} \\
\Rightarrow P = \dfrac{k}{D} \\
\Rightarrow P \times D = k \\
\end{gathered} $
where k is constant of proportionality.
Hence, the number of days and the number of persons required to complete the job are inversely proportional to each other.
$\begin{gathered}
\therefore {P_1}{D_1} = {P_2}{D_2} \\
3 \times 4 = 3 \times x \\
x = \dfrac{{3 \times 4}}{3} \\
x = 4 \\
\end{gathered} $
∴It would require 4 days to complete the job.
Note: Here, students must note that in these types of questions, first of all, it is very important to find what these quantities are and whether they are inversely proportional or directly proportional. And also remember the value of k that is constant will remain the same, and values of the quantities will change.
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred

Master Class 8 Social Science: Engaging Questions & Answers for Success

Master Class 8 Science: Engaging Questions & Answers for Success

Master Class 8 Maths: Engaging Questions & Answers for Success

Class 8 Question and Answer - Your Ultimate Solutions Guide

Master Class 9 Social Science: Engaging Questions & Answers for Success

Trending doubts
What is BLO What is the full form of BLO class 8 social science CBSE

Give me the opposite gender of Duck class 8 english CBSE

Citizens of India can vote at the age of A 18 years class 8 social science CBSE

Advantages and disadvantages of science

Full form of STD, ISD and PCO

What are gulf countries and why they are called Gulf class 8 social science CBSE

