
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B went away. In how many days will A finish the remaining work?
A. 14 days
B. 17 days
C. 12 days
D. 10 days
Answer
517.8k+ views
Hint: We will first find out the work done by A and B in 1 day. Then we will find the total work done by A and B together in 1 day. As it is given that they worked together for 2 days, we will find the work completed by them in two days. Then we will find the remaining fraction of work by subtracting it from 1.
Complete step by step solution:
In the question we are given that A can finish a piece of work in 15 days and B can do it in 10 days. It is given that they worked together for 2 days and then B goes away and we are asked to find the number of days in which A will finish the remaining work.
So, in the question it is given that A can finish the whole work in 15 days, so we can conclude that,
In 1 day A can complete $\dfrac{1}{15}$ of the work.
It is also given that B can finish the whole work in 10 days. So, from this we can conclude that,
In 1 day B can complete $\dfrac{1}{10}$ of the work.
So, if both A and B work together, then we can say that,
In 1 day A and B together can complete $\left( \dfrac{1}{15}+\dfrac{1}{10} \right)$ of the work.
So, we will first simplify this by taking the LCM and get,
$\left( \dfrac{1}{15}+\dfrac{1}{10} \right)=\left( \dfrac{2+3}{30} \right)=\dfrac{5}{30}=\dfrac{1}{6}$
Thus, we can say that A and B together can complete $\dfrac{1}{6}$ of the work in 1 day.
Now, it is given that they worked together for 2 days. So, the work they complete together in 2 days will be, $2\times \dfrac{1}{6}=\dfrac{1}{3}$. Hence, after 2 days the work completed is $\dfrac{1}{3}$. So, the total work left to be completed is given as, $1-\dfrac{1}{3}=\dfrac{2}{3}$. So, we can say that $\dfrac{2}{3}$ amount of work has to be done by A.
We know that A can complete $\dfrac{1}{15}$ of the work in 1 day. So, A can complete the whole work in 15 days.
So, A can complete $\dfrac{2}{3}$ of the work left to be completed in $\left( \dfrac{2}{3}\times 15 \right)=10$ days.
Therefore, the correct option is option D.
Note: The possible mistakes that the students can make in this question is by considering the total number of days, that is (15+10) = 25 as the total amount of work, so they will write the remaining amount of work to be done by A as $25-\dfrac{1}{3}$ and will end up getting the wrong answers. Another mistake is that in the end, after finding the final answer, that is 10 days, they may add another 2 days, that is when A and B both worked together, with it and will get the answer as 12 days and will write option (C) as the answer but this is not correct.
Complete step by step solution:
In the question we are given that A can finish a piece of work in 15 days and B can do it in 10 days. It is given that they worked together for 2 days and then B goes away and we are asked to find the number of days in which A will finish the remaining work.
So, in the question it is given that A can finish the whole work in 15 days, so we can conclude that,
In 1 day A can complete $\dfrac{1}{15}$ of the work.
It is also given that B can finish the whole work in 10 days. So, from this we can conclude that,
In 1 day B can complete $\dfrac{1}{10}$ of the work.
So, if both A and B work together, then we can say that,
In 1 day A and B together can complete $\left( \dfrac{1}{15}+\dfrac{1}{10} \right)$ of the work.
So, we will first simplify this by taking the LCM and get,
$\left( \dfrac{1}{15}+\dfrac{1}{10} \right)=\left( \dfrac{2+3}{30} \right)=\dfrac{5}{30}=\dfrac{1}{6}$
Thus, we can say that A and B together can complete $\dfrac{1}{6}$ of the work in 1 day.
Now, it is given that they worked together for 2 days. So, the work they complete together in 2 days will be, $2\times \dfrac{1}{6}=\dfrac{1}{3}$. Hence, after 2 days the work completed is $\dfrac{1}{3}$. So, the total work left to be completed is given as, $1-\dfrac{1}{3}=\dfrac{2}{3}$. So, we can say that $\dfrac{2}{3}$ amount of work has to be done by A.
We know that A can complete $\dfrac{1}{15}$ of the work in 1 day. So, A can complete the whole work in 15 days.
So, A can complete $\dfrac{2}{3}$ of the work left to be completed in $\left( \dfrac{2}{3}\times 15 \right)=10$ days.
Therefore, the correct option is option D.
Note: The possible mistakes that the students can make in this question is by considering the total number of days, that is (15+10) = 25 as the total amount of work, so they will write the remaining amount of work to be done by A as $25-\dfrac{1}{3}$ and will end up getting the wrong answers. Another mistake is that in the end, after finding the final answer, that is 10 days, they may add another 2 days, that is when A and B both worked together, with it and will get the answer as 12 days and will write option (C) as the answer but this is not correct.
Recently Updated Pages
Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Computer Science: Engaging Questions & Answers for Success

Trending doubts
The shortest day of the year in India

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

State and prove converse of BPT Basic Proportionality class 10 maths CBSE

