$A$ can do $\dfrac{2}{3}$ of a certain work in $16$ days and $B$ can do $\dfrac{1}{4}$ of the same work in $3$ days. In how many days can both finish the work, working together?
Answer
595.5k+ views
Hint:Since they are individually doing the same work, we can find their capacities. We need to find the work done by them in a single day. Then we can calculate the number of days needed to finish the work.
Formula used:If $x$ is the number of days and w is the work done per day, then total work done is $wx$.
Complete step-by-step answer:
Given that $A$ can complete $\dfrac{2}{3}$of the given work in $16$ days.
So $A$ can complete the total work (that is $\dfrac{3}{3} = 1$ of the work) in $16 \times \dfrac{3}{2} = 24$ days.
Also given $B$ can complete $\dfrac{1}{4}$ of the same work in $3$ days.
So $B$ can complete the total work in $3 \times 4 = 12$days.
Therefore, the work done by $A,B$ in a single day is $\dfrac{1}{{24}},\dfrac{1}{{12}}$ respectively.
$ \Rightarrow {w_A} = \dfrac{1}{{24}},{w_B} = \dfrac{1}{{12}}$
So the total work done by them in a single day is $w = {w_A} + {w_B} = \dfrac{1}{{24}} + \dfrac{1}{{12}} = \dfrac{1}{{24}} + \dfrac{2}{{24}} = \dfrac{3}{{24}} = \dfrac{1}{8}$
Let they take $x$ days to complete the whole work, working together.
We have to find $x$.
If $x$ is the number of days and $w$ is the work done per day, then total work done is $wx$.
Here, $w = \dfrac{1}{8}$ and total work can be considered as $1$.
$ \Rightarrow \dfrac{1}{8}x = 1$
$ \Rightarrow x = 1 \times 8 = 8$
So $A$ and $B$ need $8$ days to finish the work, working together.
Note:The point should be noted is that work done is proportional to the time taken. The more is the time, the more is the work. But the more is the number of workers, the less is the time taken.
Formula used:If $x$ is the number of days and w is the work done per day, then total work done is $wx$.
Complete step-by-step answer:
Given that $A$ can complete $\dfrac{2}{3}$of the given work in $16$ days.
So $A$ can complete the total work (that is $\dfrac{3}{3} = 1$ of the work) in $16 \times \dfrac{3}{2} = 24$ days.
Also given $B$ can complete $\dfrac{1}{4}$ of the same work in $3$ days.
So $B$ can complete the total work in $3 \times 4 = 12$days.
Therefore, the work done by $A,B$ in a single day is $\dfrac{1}{{24}},\dfrac{1}{{12}}$ respectively.
$ \Rightarrow {w_A} = \dfrac{1}{{24}},{w_B} = \dfrac{1}{{12}}$
So the total work done by them in a single day is $w = {w_A} + {w_B} = \dfrac{1}{{24}} + \dfrac{1}{{12}} = \dfrac{1}{{24}} + \dfrac{2}{{24}} = \dfrac{3}{{24}} = \dfrac{1}{8}$
Let they take $x$ days to complete the whole work, working together.
We have to find $x$.
If $x$ is the number of days and $w$ is the work done per day, then total work done is $wx$.
Here, $w = \dfrac{1}{8}$ and total work can be considered as $1$.
$ \Rightarrow \dfrac{1}{8}x = 1$
$ \Rightarrow x = 1 \times 8 = 8$
So $A$ and $B$ need $8$ days to finish the work, working together.
Note:The point should be noted is that work done is proportional to the time taken. The more is the time, the more is the work. But the more is the number of workers, the less is the time taken.
Recently Updated Pages
Master Class 11 Business Studies: Engaging Questions & Answers for Success

Master Class 11 Computer Science: Engaging Questions & Answers for Success

Master Class 11 Economics: Engaging Questions & Answers for Success

Master Class 11 Social Science: Engaging Questions & Answers for Success

Master Class 11 English: Engaging Questions & Answers for Success

Master Class 11 Chemistry: Engaging Questions & Answers for Success

Trending doubts
Draw a diagram of nephron and explain its structur class 11 biology CBSE

Explain zero factorial class 11 maths CBSE

Chemical formula of Bleaching powder is A Ca2OCl2 B class 11 chemistry CBSE

Name the part of the brain responsible for the precision class 11 biology CBSE

The growth of tendril in pea plants is due to AEffect class 11 biology CBSE

One Metric ton is equal to kg A 10000 B 1000 C 100 class 11 physics CBSE