$A$ can do $\dfrac{2}{3}$ of a certain work in $16$ days and $B$ can do $\dfrac{1}{4}$ of the same work in $3$ days. In how many days can both finish the work, working together?
Answer
573.3k+ views
Hint:Since they are individually doing the same work, we can find their capacities. We need to find the work done by them in a single day. Then we can calculate the number of days needed to finish the work.
Formula used:If $x$ is the number of days and w is the work done per day, then total work done is $wx$.
Complete step-by-step answer:
Given that $A$ can complete $\dfrac{2}{3}$of the given work in $16$ days.
So $A$ can complete the total work (that is $\dfrac{3}{3} = 1$ of the work) in $16 \times \dfrac{3}{2} = 24$ days.
Also given $B$ can complete $\dfrac{1}{4}$ of the same work in $3$ days.
So $B$ can complete the total work in $3 \times 4 = 12$days.
Therefore, the work done by $A,B$ in a single day is $\dfrac{1}{{24}},\dfrac{1}{{12}}$ respectively.
$ \Rightarrow {w_A} = \dfrac{1}{{24}},{w_B} = \dfrac{1}{{12}}$
So the total work done by them in a single day is $w = {w_A} + {w_B} = \dfrac{1}{{24}} + \dfrac{1}{{12}} = \dfrac{1}{{24}} + \dfrac{2}{{24}} = \dfrac{3}{{24}} = \dfrac{1}{8}$
Let they take $x$ days to complete the whole work, working together.
We have to find $x$.
If $x$ is the number of days and $w$ is the work done per day, then total work done is $wx$.
Here, $w = \dfrac{1}{8}$ and total work can be considered as $1$.
$ \Rightarrow \dfrac{1}{8}x = 1$
$ \Rightarrow x = 1 \times 8 = 8$
So $A$ and $B$ need $8$ days to finish the work, working together.
Note:The point should be noted is that work done is proportional to the time taken. The more is the time, the more is the work. But the more is the number of workers, the less is the time taken.
Formula used:If $x$ is the number of days and w is the work done per day, then total work done is $wx$.
Complete step-by-step answer:
Given that $A$ can complete $\dfrac{2}{3}$of the given work in $16$ days.
So $A$ can complete the total work (that is $\dfrac{3}{3} = 1$ of the work) in $16 \times \dfrac{3}{2} = 24$ days.
Also given $B$ can complete $\dfrac{1}{4}$ of the same work in $3$ days.
So $B$ can complete the total work in $3 \times 4 = 12$days.
Therefore, the work done by $A,B$ in a single day is $\dfrac{1}{{24}},\dfrac{1}{{12}}$ respectively.
$ \Rightarrow {w_A} = \dfrac{1}{{24}},{w_B} = \dfrac{1}{{12}}$
So the total work done by them in a single day is $w = {w_A} + {w_B} = \dfrac{1}{{24}} + \dfrac{1}{{12}} = \dfrac{1}{{24}} + \dfrac{2}{{24}} = \dfrac{3}{{24}} = \dfrac{1}{8}$
Let they take $x$ days to complete the whole work, working together.
We have to find $x$.
If $x$ is the number of days and $w$ is the work done per day, then total work done is $wx$.
Here, $w = \dfrac{1}{8}$ and total work can be considered as $1$.
$ \Rightarrow \dfrac{1}{8}x = 1$
$ \Rightarrow x = 1 \times 8 = 8$
So $A$ and $B$ need $8$ days to finish the work, working together.
Note:The point should be noted is that work done is proportional to the time taken. The more is the time, the more is the work. But the more is the number of workers, the less is the time taken.
Recently Updated Pages
Why are manures considered better than fertilizers class 11 biology CBSE

Find the coordinates of the midpoint of the line segment class 11 maths CBSE

Distinguish between static friction limiting friction class 11 physics CBSE

The Chairman of the constituent Assembly was A Jawaharlal class 11 social science CBSE

The first National Commission on Labour NCL submitted class 11 social science CBSE

Number of all subshell of n + l 7 is A 4 B 5 C 6 D class 11 chemistry CBSE

Trending doubts
What is meant by exothermic and endothermic reactions class 11 chemistry CBSE

10 examples of friction in our daily life

One Metric ton is equal to kg A 10000 B 1000 C 100 class 11 physics CBSE

1 Quintal is equal to a 110 kg b 10 kg c 100kg d 1000 class 11 physics CBSE

Difference Between Prokaryotic Cells and Eukaryotic Cells

What are Quantum numbers Explain the quantum number class 11 chemistry CBSE