A can do a work in 12 hours, B can do it in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$ How much does he earn from the whole job?
Answer
573k+ views
Hint: To solve this question first we will calculate the total work by taking the LCM of time taken to complete the work by A and B. Then we will calculate individually the total work done by A and B. Then by multiplying the total work by A’s hourly earning we will get the desired answer.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Recently Updated Pages
Which will be the least stable resonating structure class 11 chemistry CBSE

Explain the structure of megasporangium class 12 biology CBSE

Differentiate between voluntary action and reflex class 10 biology CBSE

How many 5 digit telephone numbers can be construc-class-11-maths-CBSE

How do you find the angle of the resultant vector class 11 physics CBSE

Why is chloroform kept in dark coloured bottles class 12 chemistry CBSE

Trending doubts
How many sides does a circle have a 10 sides b 20 sides class 8 maths CBSE

One cusec is equal to how many liters class 8 maths CBSE

10 slogans on organ donation class 8 english CBSE

Which Indian state shares the longest international class 8 social science CBSE

Who commanded the Hector the first British trading class 8 social science CBSE

Crops which are grown in the winter season are known class 8 biology CBSE

