
A can do a work in 12 hours, B can do it in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$ How much does he earn from the whole job?
Answer
505.8k+ views
Hint: To solve this question first we will calculate the total work by taking the LCM of time taken to complete the work by A and B. Then we will calculate individually the total work done by A and B. Then by multiplying the total work by A’s hourly earning we will get the desired answer.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Complete step by step answer:
We have been given that A can do a work in 12 hours, B can do in 14 hours. They work alternatively starting from A. A earns Rs. $15/hr.$
We have to find the total earning A gets from the job.
Now, let us first calculate the total work by taking the LCM of time taken to complete the work by A and B. then we will get
$\Rightarrow \text{Total work}=\text{LCM of }\left( 12,14 \right)$
Now, the LCM of 12 and 14 will be
$\begin{align}
& 2\left| \!{\underline {\,
12,14 \,}} \right. \\
& 2\left| \!{\underline {\,
6,7 \,}} \right. \\
& 3\left| \!{\underline {\,
3,7 \,}} \right. \\
& 7\left| \!{\underline {\,
1,7 \,}} \right. \\
& \text{ }\left| \!{\underline {\,
1,1 \,}} \right. \\
\end{align}$
LCM of 12 and 14 will be 84.
So the total work will be 84 units.
Now, the work done by A will be
$\begin{align}
& \Rightarrow \dfrac{84}{12} \\
& \Rightarrow 7units \\
\end{align}$
Now, the work done by B will be
$\begin{align}
& \Rightarrow \dfrac{84}{14} \\
& \Rightarrow 6 units \\
\end{align}$
Now, given in the question they work alternatively starting from A. So on the first day A completes 7 units and the next day B completes 6 units. It means in 2 days A and B complete $7+6=13units$.
Let us consider A worked 6 days and B worked 6 days so in 12 days the total work done by them will be
$\begin{align}
& \Rightarrow 13\times 6 \\
& \Rightarrow 78 units \\
\end{align}$
Now, the next day i.e. on the seventh day it’s A’s turn and he completed the remaining work i.e. $6units$ in $\dfrac{6}{7}hours$.
Now, A earns Rs. $15/hr.$ So the total amount he earns from the job will be
$\begin{align}
& \Rightarrow 12\times 15\times 3+15\times \dfrac{6}{7} \\
& \Rightarrow 540+13approx \\
& \Rightarrow 553 \\
\end{align}$
Hence A gets Rs. 553 approx from the whole job.
Note: The key concept to solve this type of question is to first calculate the total work if not given in the question. Then calculate the work done by a person in one day. Then solve further according to the demand of the question.
Recently Updated Pages
The number of solutions in x in 02pi for which sqrt class 12 maths CBSE

Write any two methods of preparation of phenol Give class 12 chemistry CBSE

Differentiate between action potential and resting class 12 biology CBSE

Two plane mirrors arranged at right angles to each class 12 physics CBSE

Which of the following molecules is are chiral A I class 12 chemistry CBSE

Name different types of neurons and give one function class 12 biology CBSE

Trending doubts
What is BLO What is the full form of BLO class 8 social science CBSE

Give me the opposite gender of Duck class 8 english CBSE

Full form of STD, ISD and PCO

Citizens of India can vote at the age of A 18 years class 8 social science CBSE

Application to your principal for the character ce class 8 english CBSE

What is the difference between rai and mustard see class 8 biology CBSE

