Answer
Verified
399.6k+ views
Hint: We will find the work done by A in 1 day, then we will find the work done by B in 1 day using the unitary method. In the last step, we will find the work done by both of them in 1 day and the time required by both of them to complete the work. Finally, we will equate the obtained equation to 15 and solve the quadratic equation to get the value of x.
Complete step-by-step answer:
It is given in the question that A can do a piece of work in ‘x’ days and B can do the same work in ‘x+16’ days. If both working together can do it in 15 days. And we have been asked to find the value of x.
We will use the unitary method to find the work done by A and B in 1 day. Basically, the unitary method is a mathematical approach in which we will first find the value of 1 unit and then multiply it with the required value to get the desired values.
As A can do all the work in x days. So, work done by A in 1 day, is $\dfrac{1}{x}$.
Also, B can do all the work in (x+16) days, so the work done by B in 1 day is $\dfrac{1}{\left( x+16 \right)}$.
If both A and B work together, then work done in 1 day will be,
\[\dfrac{1}{x}+\dfrac{1}{\left( x+16 \right)}\]
On taking the LCM, we get,
\[\begin{align}
& =\dfrac{x+16+x}{x\left( x+16 \right)} \\
& =\dfrac{2x+16}{{{x}^{2}}+16x} \\
\end{align}\]
As \[\dfrac{2x+16}{{{x}^{2}}+16x}\] gives us the work done by A and B in 1 day, the total time taken by A and B to complete the work is given by the reverse of \[\dfrac{2x+16}{{{x}^{2}}+16x}\]. It is because the reverse of $\dfrac{1}{x}$ is x and the reverse of $\dfrac{1}{\left( x+16 \right)}$ is (x+16), which gives us the data regarding the time taken by A and B individually to complete the given work.
So, the time taken by both A and B to complete the work is, \[\dfrac{{{x}^{2}}+16x}{2x+16}\].
We also know that both A and B require 15 days to complete the work.
So, \[\dfrac{{{x}^{2}}+16x}{2x+16}\] must be equal to 15 days. So, we can write,
\[\dfrac{{{x}^{2}}+16x}{2x+16}=15\]
On cross multiplying, we get,
\[\begin{align}
& {{x}^{2}}+16x=15\left( 2x+16 \right) \\
& {{x}^{2}}+16x=30x+240 \\
\end{align}\]
On transposing 30x + 240 from RHS to LHS, we get,
\[\begin{align}
& {{x}^{2}}+16x-30x-240=0 \\
& {{x}^{2}}-14x-240=0 \\
\end{align}\]
We can also write -14x as -24x + 10x, so we get,
\[\begin{align}
& {{x}^{2}}-24x+10x-240=0 \\
& x\left( x-24 \right)+10\left( x-24 \right) \\
& \left( x+10 \right)\left( x-24 \right)=0 \\
& x=-10,24 \\
\end{align}\]
We know that work done cannot be negative, so we will neglect -10.
Thus, the value of x = 24.
So, A can do the work in 24 days.
Hence, option (a) is the correct answer.
Note: Many students make mistake by equating \[\dfrac{2x+16}{{{x}^{2}}+16x}\] with 15, this is wrong, as \[\dfrac{2x+16}{{{x}^{2}}+16x}\] gives us the value of the work done by A and B in one day and 15 days is the total time taken to complete the work. So, this mistake must be avoided. Also, after finding the value of x = 24 days, that is the time taken by A to complete the work, we can also find the time taken by B to do the work as (x+16) = (24+16) = 40 days.
Complete step-by-step answer:
It is given in the question that A can do a piece of work in ‘x’ days and B can do the same work in ‘x+16’ days. If both working together can do it in 15 days. And we have been asked to find the value of x.
We will use the unitary method to find the work done by A and B in 1 day. Basically, the unitary method is a mathematical approach in which we will first find the value of 1 unit and then multiply it with the required value to get the desired values.
As A can do all the work in x days. So, work done by A in 1 day, is $\dfrac{1}{x}$.
Also, B can do all the work in (x+16) days, so the work done by B in 1 day is $\dfrac{1}{\left( x+16 \right)}$.
If both A and B work together, then work done in 1 day will be,
\[\dfrac{1}{x}+\dfrac{1}{\left( x+16 \right)}\]
On taking the LCM, we get,
\[\begin{align}
& =\dfrac{x+16+x}{x\left( x+16 \right)} \\
& =\dfrac{2x+16}{{{x}^{2}}+16x} \\
\end{align}\]
As \[\dfrac{2x+16}{{{x}^{2}}+16x}\] gives us the work done by A and B in 1 day, the total time taken by A and B to complete the work is given by the reverse of \[\dfrac{2x+16}{{{x}^{2}}+16x}\]. It is because the reverse of $\dfrac{1}{x}$ is x and the reverse of $\dfrac{1}{\left( x+16 \right)}$ is (x+16), which gives us the data regarding the time taken by A and B individually to complete the given work.
So, the time taken by both A and B to complete the work is, \[\dfrac{{{x}^{2}}+16x}{2x+16}\].
We also know that both A and B require 15 days to complete the work.
So, \[\dfrac{{{x}^{2}}+16x}{2x+16}\] must be equal to 15 days. So, we can write,
\[\dfrac{{{x}^{2}}+16x}{2x+16}=15\]
On cross multiplying, we get,
\[\begin{align}
& {{x}^{2}}+16x=15\left( 2x+16 \right) \\
& {{x}^{2}}+16x=30x+240 \\
\end{align}\]
On transposing 30x + 240 from RHS to LHS, we get,
\[\begin{align}
& {{x}^{2}}+16x-30x-240=0 \\
& {{x}^{2}}-14x-240=0 \\
\end{align}\]
We can also write -14x as -24x + 10x, so we get,
\[\begin{align}
& {{x}^{2}}-24x+10x-240=0 \\
& x\left( x-24 \right)+10\left( x-24 \right) \\
& \left( x+10 \right)\left( x-24 \right)=0 \\
& x=-10,24 \\
\end{align}\]
We know that work done cannot be negative, so we will neglect -10.
Thus, the value of x = 24.
So, A can do the work in 24 days.
Hence, option (a) is the correct answer.
Note: Many students make mistake by equating \[\dfrac{2x+16}{{{x}^{2}}+16x}\] with 15, this is wrong, as \[\dfrac{2x+16}{{{x}^{2}}+16x}\] gives us the value of the work done by A and B in one day and 15 days is the total time taken to complete the work. So, this mistake must be avoided. Also, after finding the value of x = 24 days, that is the time taken by A to complete the work, we can also find the time taken by B to do the work as (x+16) = (24+16) = 40 days.
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Trending doubts
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
Two charges are placed at a certain distance apart class 12 physics CBSE
Difference Between Plant Cell and Animal Cell
What organs are located on the left side of your body class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE
The planet nearest to earth is A Mercury B Venus C class 6 social science CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
What is BLO What is the full form of BLO class 8 social science CBSE