Answer
Verified
447.3k+ views
Hint: These type of problems are solved by following some rule which are-
Suppose if a person can finish a work in $n$ days. Then work done by that person in $1$ day \[ = \] $1/{n^{th}}$part of work.
Suppose that work done by a person in $1$ day is $\dfrac{1}{n}$ then time taken by that person to finish the whole work$ = n$ days.
Complete step-by-step answer:
In the question it is given that
Time taken by $A$ to finish the work $ = 24$ days
Work done by $A$ in 1 day$ = \dfrac{1}{{24}}$
Time taken by $(A + B)$ to finish the work$ = 16$ days
Work done by $(A + B)$in $1$ day$ = \dfrac{1}{{16}}$
Time taken by $\left( {A + B + C} \right)$ to finish the work$ = 10\dfrac{2}{3}$days
$ = \dfrac{{32}}{3}$ days
Work done by $\left( {A + B + C} \right)$ in 1 day$ = \dfrac{3}{{32}}$
Now we can calculate the work done by the $C$ which is
Work done by $\left( {A + B + C} \right)$ in 1 day$ - $Work done by $(A + B)$ in 1 day \[ = \dfrac{3}{{32}} - \dfrac{1}{{16}}\]
$ = \dfrac{{3 - 2}}{{32}} = \dfrac{1}{{32}}$
Now work done by the $C$ in 1 day$ = \dfrac{1}{{32}}$
Further the work done by the $\left( {A + C} \right)$ in 1 day$ = $Work done by $A$ in 1 day$ + $work done by the $C$ in 1 day
$ = \dfrac{1}{{24}} + \dfrac{1}{{32}}$
$ = \dfrac{{4 + 3}}{{96}} = \dfrac{7}{{96}}$
Then the time taken by$\left( {A + C} \right)$to finish work$ = \dfrac{1}{{\left( {\dfrac{7}{{96}}} \right)}}$days
$ = \dfrac{1}{7} \times 96 = \dfrac{{96}}{7}$
$ = 13\dfrac{5}{7}$ days
So, the correct answer is “Option C”.
Note: In these types of questions we can add or subtract quantities of only work done. We cannot add or subtract time which is taken to finish work. We need to avoid any type of calculation mistake.
Suppose if a person can finish a work in $n$ days. Then work done by that person in $1$ day \[ = \] $1/{n^{th}}$part of work.
Suppose that work done by a person in $1$ day is $\dfrac{1}{n}$ then time taken by that person to finish the whole work$ = n$ days.
Complete step-by-step answer:
In the question it is given that
Time taken by $A$ to finish the work $ = 24$ days
Work done by $A$ in 1 day$ = \dfrac{1}{{24}}$
Time taken by $(A + B)$ to finish the work$ = 16$ days
Work done by $(A + B)$in $1$ day$ = \dfrac{1}{{16}}$
Time taken by $\left( {A + B + C} \right)$ to finish the work$ = 10\dfrac{2}{3}$days
$ = \dfrac{{32}}{3}$ days
Work done by $\left( {A + B + C} \right)$ in 1 day$ = \dfrac{3}{{32}}$
Now we can calculate the work done by the $C$ which is
Work done by $\left( {A + B + C} \right)$ in 1 day$ - $Work done by $(A + B)$ in 1 day \[ = \dfrac{3}{{32}} - \dfrac{1}{{16}}\]
$ = \dfrac{{3 - 2}}{{32}} = \dfrac{1}{{32}}$
Now work done by the $C$ in 1 day$ = \dfrac{1}{{32}}$
Further the work done by the $\left( {A + C} \right)$ in 1 day$ = $Work done by $A$ in 1 day$ + $work done by the $C$ in 1 day
$ = \dfrac{1}{{24}} + \dfrac{1}{{32}}$
$ = \dfrac{{4 + 3}}{{96}} = \dfrac{7}{{96}}$
Then the time taken by$\left( {A + C} \right)$to finish work$ = \dfrac{1}{{\left( {\dfrac{7}{{96}}} \right)}}$days
$ = \dfrac{1}{7} \times 96 = \dfrac{{96}}{7}$
$ = 13\dfrac{5}{7}$ days
So, the correct answer is “Option C”.
Note: In these types of questions we can add or subtract quantities of only work done. We cannot add or subtract time which is taken to finish work. We need to avoid any type of calculation mistake.
Recently Updated Pages
what is the correct chronological order of the following class 10 social science CBSE
Which of the following was not the actual cause for class 10 social science CBSE
Which of the following statements is not correct A class 10 social science CBSE
Which of the following leaders was not present in the class 10 social science CBSE
Garampani Sanctuary is located at A Diphu Assam B Gangtok class 10 social science CBSE
Which one of the following places is not covered by class 10 social science CBSE
Trending doubts
Which are the Top 10 Largest Countries of the World?
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
How do you graph the function fx 4x class 9 maths CBSE
In Indian rupees 1 trillion is equal to how many c class 8 maths CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Give 10 examples for herbs , shrubs , climbers , creepers
Why is there a time difference of about 5 hours between class 10 social science CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
What is BLO What is the full form of BLO class 8 social science CBSE