Answer
Verified
371.7k+ views
Hint: We use the unitary method for direct variation and find the amount of work A and B can complete separately in 1 day and 7 days. We find the amount of work A and B together can complete in 7 days. We find how many days B will take after A fell ill at the ${{7}^{\text{th}}}$ day and add it 7 to get the number of days required to complete the work.
Complete step-by-step solution
We are given the question that A can do a piece of work in 14 days while B can do it in 21 days. We assume the complete piece of work as 1. \[\]
We use the unitary method of direct variation to find the value of a single unit as the amount of work in one day.
So A can finish in 1 day is $\dfrac{1}{14}$ of total work. Similarly, B can finish in 1 day is $\dfrac{1}{21}$ of the total piece of work. \[\]
We are further given the question that they begin together and work at it for 7 days. Then A and B had to complete the work. Now we multiply the value of a single unit and find the work they can do in 7 days. So A can finish $7\times \dfrac{1}{4}=\dfrac{7}{4}$ of the total work in 7 days and B can finish $7\times \dfrac{1}{21}=\dfrac{7}{21}$of total work in 7 days. \[\]
So the part of work that can be done by A and B together is the sum of their part of work they can finish in 7 days that is $\dfrac{7}{14}+\dfrac{7}{21}=\dfrac{1}{2}+\dfrac{1}{3}=\dfrac{2+3}{6}=\dfrac{5}{6}$ of the total work. \[\]
Now after A left the work because of illness, the left amount of work has to be done by B. So the part of the work left now is $1-\dfrac{5}{6}=\dfrac{1}{6}$ of total work. \[\]
We are given that B can complete total work means 1 work in 21 days. So B can complete $\dfrac{1}{6}$ part of total work in $21\times \dfrac{1}{6}=\dfrac{21}{6}=3.5$ days. \[\]
So the number of days that are required to complete the work is $7+3.5=10.5$days.
Note: We know that the unitary method is a technique for solving a problem by first finding the value of a single unit by dividing indirect variation or multiplying in indirect variation. We must be careful that men and work problems are an indirect variation problem but time and work problems like we solved here are direct variation problems. If a person can complete the work in $n$ days and the efficiency in percentage is given by $\dfrac{100}{n}$.
Complete step-by-step solution
We are given the question that A can do a piece of work in 14 days while B can do it in 21 days. We assume the complete piece of work as 1. \[\]
We use the unitary method of direct variation to find the value of a single unit as the amount of work in one day.
So A can finish in 1 day is $\dfrac{1}{14}$ of total work. Similarly, B can finish in 1 day is $\dfrac{1}{21}$ of the total piece of work. \[\]
We are further given the question that they begin together and work at it for 7 days. Then A and B had to complete the work. Now we multiply the value of a single unit and find the work they can do in 7 days. So A can finish $7\times \dfrac{1}{4}=\dfrac{7}{4}$ of the total work in 7 days and B can finish $7\times \dfrac{1}{21}=\dfrac{7}{21}$of total work in 7 days. \[\]
So the part of work that can be done by A and B together is the sum of their part of work they can finish in 7 days that is $\dfrac{7}{14}+\dfrac{7}{21}=\dfrac{1}{2}+\dfrac{1}{3}=\dfrac{2+3}{6}=\dfrac{5}{6}$ of the total work. \[\]
Now after A left the work because of illness, the left amount of work has to be done by B. So the part of the work left now is $1-\dfrac{5}{6}=\dfrac{1}{6}$ of total work. \[\]
We are given that B can complete total work means 1 work in 21 days. So B can complete $\dfrac{1}{6}$ part of total work in $21\times \dfrac{1}{6}=\dfrac{21}{6}=3.5$ days. \[\]
So the number of days that are required to complete the work is $7+3.5=10.5$days.
Note: We know that the unitary method is a technique for solving a problem by first finding the value of a single unit by dividing indirect variation or multiplying in indirect variation. We must be careful that men and work problems are an indirect variation problem but time and work problems like we solved here are direct variation problems. If a person can complete the work in $n$ days and the efficiency in percentage is given by $\dfrac{100}{n}$.
Recently Updated Pages
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Find the values of other five trigonometric functions class 10 maths CBSE
Trending doubts
State the differences between manure and fertilize class 8 biology CBSE
Why are xylem and phloem called complex tissues aBoth class 11 biology CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Difference Between Plant Cell and Animal Cell
What would happen if plasma membrane ruptures or breaks class 11 biology CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
What precautions do you take while observing the nucleus class 11 biology CBSE
What would happen to the life of a cell if there was class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE