
A can do a piece of work in 14 days and B in 21 days. They begin together, but 3 days before the completion of the work, A leaves off. In how many days is the work complete?
(a) $10$ days
(b) $10\dfrac{1}{5}$ days
(c) $15$ days
(d) $7$ days
Answer
601.8k+ views
Hint: We will first find the fraction of work they do in one day, each alone and together. And, we will calculate the work done in the last 3 days. Then we will use this data to solve the question.
Complete step-by-step answer:
According to question,
A completes the work in 14 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{14} \right)}^{th}}$ of the total work in one day.
And, B completes the work in 21 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{21} \right)}^{th}}$ of the total work in one day.
Now, if they work together, then the fraction of total work done by them in one day must be$=\dfrac{1}{14}+\dfrac{1}{21}$
Taking LCM and then adding, we get,
$\begin{align}
& =\dfrac{1\times 3}{14\times 3}+\dfrac{1\times 2}{21\times 2} \\
& =\dfrac{3}{42}+\dfrac{2}{42} \\
& =\dfrac{3+2}{42} \\
& =\dfrac{5}{42} \\
\end{align}$
Now, B has worked alone in the last 3 days after A leaves, to complete the work.
Also, fraction of total work done by B in 3 days = $3\times \dfrac{1}{21}$
=$\dfrac{1}{7}$.
Therefore, remaining fraction of work, that A and B have completed together = $1-\dfrac{1}{7}$
Taking LCM and then subtracting,
$\begin{align}
& =\dfrac{1\times 7}{1\times 7}-\dfrac{1}{7} \\
& =\dfrac{7-1}{7} \\
& =\dfrac{6}{7} \\
\end{align}$
Here, we have,
Number of days taken by A and B together to complete \[{{\left( \dfrac{5}{42} \right)}^{th}}\] of the total work = 1 day.
Therefore, the number of days taken by A and B together to complete the whole work = $\dfrac{42}{5}$ days.
Hence, number of days taken by A and B together to complete \[{{\left( \dfrac{6}{7} \right)}^{th}}\] of the total work,
$=\dfrac{42}{5}\times \dfrac{6}{7}$ days
Simplifying, we get,
$=\dfrac{6\times 6}{5}$ days
$=\dfrac{36}{5}$ days.
Therefore, time taken to complete the whole work,
$=\dfrac{36}{5}$ days + $3$ days
Taking LCM,
$=\left( \dfrac{36}{5}+\dfrac{3\times 5}{1\times 5} \right)$ days
$=\dfrac{36+15}{5}$ days
$=\dfrac{51}{5}$ days.
$=10\dfrac{1}{5}$ days
Hence, the correct answer is option (b).
Note: In such types of questions, do not confuse fraction of work with number of works. And keep in mind that if we are considering a fraction of work, then whole work will be represented by 1.
Complete step-by-step answer:
According to question,
A completes the work in 14 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{14} \right)}^{th}}$ of the total work in one day.
And, B completes the work in 21 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{21} \right)}^{th}}$ of the total work in one day.
Now, if they work together, then the fraction of total work done by them in one day must be$=\dfrac{1}{14}+\dfrac{1}{21}$
Taking LCM and then adding, we get,
$\begin{align}
& =\dfrac{1\times 3}{14\times 3}+\dfrac{1\times 2}{21\times 2} \\
& =\dfrac{3}{42}+\dfrac{2}{42} \\
& =\dfrac{3+2}{42} \\
& =\dfrac{5}{42} \\
\end{align}$
Now, B has worked alone in the last 3 days after A leaves, to complete the work.
Also, fraction of total work done by B in 3 days = $3\times \dfrac{1}{21}$
=$\dfrac{1}{7}$.
Therefore, remaining fraction of work, that A and B have completed together = $1-\dfrac{1}{7}$
Taking LCM and then subtracting,
$\begin{align}
& =\dfrac{1\times 7}{1\times 7}-\dfrac{1}{7} \\
& =\dfrac{7-1}{7} \\
& =\dfrac{6}{7} \\
\end{align}$
Here, we have,
Number of days taken by A and B together to complete \[{{\left( \dfrac{5}{42} \right)}^{th}}\] of the total work = 1 day.
Therefore, the number of days taken by A and B together to complete the whole work = $\dfrac{42}{5}$ days.
Hence, number of days taken by A and B together to complete \[{{\left( \dfrac{6}{7} \right)}^{th}}\] of the total work,
$=\dfrac{42}{5}\times \dfrac{6}{7}$ days
Simplifying, we get,
$=\dfrac{6\times 6}{5}$ days
$=\dfrac{36}{5}$ days.
Therefore, time taken to complete the whole work,
$=\dfrac{36}{5}$ days + $3$ days
Taking LCM,
$=\left( \dfrac{36}{5}+\dfrac{3\times 5}{1\times 5} \right)$ days
$=\dfrac{36+15}{5}$ days
$=\dfrac{51}{5}$ days.
$=10\dfrac{1}{5}$ days
Hence, the correct answer is option (b).
Note: In such types of questions, do not confuse fraction of work with number of works. And keep in mind that if we are considering a fraction of work, then whole work will be represented by 1.
Recently Updated Pages
Two men on either side of the cliff 90m height observe class 10 maths CBSE

What happens to glucose which enters nephron along class 10 biology CBSE

Cutting of the Chinese melon means A The business and class 10 social science CBSE

Write a dialogue with at least ten utterances between class 10 english CBSE

Show an aquatic food chain using the following organisms class 10 biology CBSE

A circle is inscribed in an equilateral triangle and class 10 maths CBSE

Trending doubts
Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

Which of the following does not have a fundamental class 10 physics CBSE

State and prove converse of BPT Basic Proportionality class 10 maths CBSE

