Answer
Verified
418.8k+ views
Hint: We will first find the fraction of work they do in one day, each alone and together. And, we will calculate the work done in the last 3 days. Then we will use this data to solve the question.
Complete step-by-step answer:
According to question,
A completes the work in 14 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{14} \right)}^{th}}$ of the total work in one day.
And, B completes the work in 21 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{21} \right)}^{th}}$ of the total work in one day.
Now, if they work together, then the fraction of total work done by them in one day must be$=\dfrac{1}{14}+\dfrac{1}{21}$
Taking LCM and then adding, we get,
$\begin{align}
& =\dfrac{1\times 3}{14\times 3}+\dfrac{1\times 2}{21\times 2} \\
& =\dfrac{3}{42}+\dfrac{2}{42} \\
& =\dfrac{3+2}{42} \\
& =\dfrac{5}{42} \\
\end{align}$
Now, B has worked alone in the last 3 days after A leaves, to complete the work.
Also, fraction of total work done by B in 3 days = $3\times \dfrac{1}{21}$
=$\dfrac{1}{7}$.
Therefore, remaining fraction of work, that A and B have completed together = $1-\dfrac{1}{7}$
Taking LCM and then subtracting,
$\begin{align}
& =\dfrac{1\times 7}{1\times 7}-\dfrac{1}{7} \\
& =\dfrac{7-1}{7} \\
& =\dfrac{6}{7} \\
\end{align}$
Here, we have,
Number of days taken by A and B together to complete \[{{\left( \dfrac{5}{42} \right)}^{th}}\] of the total work = 1 day.
Therefore, the number of days taken by A and B together to complete the whole work = $\dfrac{42}{5}$ days.
Hence, number of days taken by A and B together to complete \[{{\left( \dfrac{6}{7} \right)}^{th}}\] of the total work,
$=\dfrac{42}{5}\times \dfrac{6}{7}$ days
Simplifying, we get,
$=\dfrac{6\times 6}{5}$ days
$=\dfrac{36}{5}$ days.
Therefore, time taken to complete the whole work,
$=\dfrac{36}{5}$ days + $3$ days
Taking LCM,
$=\left( \dfrac{36}{5}+\dfrac{3\times 5}{1\times 5} \right)$ days
$=\dfrac{36+15}{5}$ days
$=\dfrac{51}{5}$ days.
$=10\dfrac{1}{5}$ days
Hence, the correct answer is option (b).
Note: In such types of questions, do not confuse fraction of work with number of works. And keep in mind that if we are considering a fraction of work, then whole work will be represented by 1.
Complete step-by-step answer:
According to question,
A completes the work in 14 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{14} \right)}^{th}}$ of the total work in one day.
And, B completes the work in 21 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{21} \right)}^{th}}$ of the total work in one day.
Now, if they work together, then the fraction of total work done by them in one day must be$=\dfrac{1}{14}+\dfrac{1}{21}$
Taking LCM and then adding, we get,
$\begin{align}
& =\dfrac{1\times 3}{14\times 3}+\dfrac{1\times 2}{21\times 2} \\
& =\dfrac{3}{42}+\dfrac{2}{42} \\
& =\dfrac{3+2}{42} \\
& =\dfrac{5}{42} \\
\end{align}$
Now, B has worked alone in the last 3 days after A leaves, to complete the work.
Also, fraction of total work done by B in 3 days = $3\times \dfrac{1}{21}$
=$\dfrac{1}{7}$.
Therefore, remaining fraction of work, that A and B have completed together = $1-\dfrac{1}{7}$
Taking LCM and then subtracting,
$\begin{align}
& =\dfrac{1\times 7}{1\times 7}-\dfrac{1}{7} \\
& =\dfrac{7-1}{7} \\
& =\dfrac{6}{7} \\
\end{align}$
Here, we have,
Number of days taken by A and B together to complete \[{{\left( \dfrac{5}{42} \right)}^{th}}\] of the total work = 1 day.
Therefore, the number of days taken by A and B together to complete the whole work = $\dfrac{42}{5}$ days.
Hence, number of days taken by A and B together to complete \[{{\left( \dfrac{6}{7} \right)}^{th}}\] of the total work,
$=\dfrac{42}{5}\times \dfrac{6}{7}$ days
Simplifying, we get,
$=\dfrac{6\times 6}{5}$ days
$=\dfrac{36}{5}$ days.
Therefore, time taken to complete the whole work,
$=\dfrac{36}{5}$ days + $3$ days
Taking LCM,
$=\left( \dfrac{36}{5}+\dfrac{3\times 5}{1\times 5} \right)$ days
$=\dfrac{36+15}{5}$ days
$=\dfrac{51}{5}$ days.
$=10\dfrac{1}{5}$ days
Hence, the correct answer is option (b).
Note: In such types of questions, do not confuse fraction of work with number of works. And keep in mind that if we are considering a fraction of work, then whole work will be represented by 1.
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Trending doubts
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Difference Between Plant Cell and Animal Cell
Select the word that is correctly spelled a Twelveth class 10 english CBSE
Fill the blanks with the suitable prepositions 1 The class 9 english CBSE
What is the z value for a 90 95 and 99 percent confidence class 11 maths CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
What organs are located on the left side of your body class 11 biology CBSE
What is BLO What is the full form of BLO class 8 social science CBSE
Change the following sentences into negative and interrogative class 10 english CBSE