
A can do a piece of work in 14 days and B in 21 days. They begin together, but 3 days before the completion of the work, A leaves off. In how many days is the work complete?
(a) $10$ days
(b) $10\dfrac{1}{5}$ days
(c) $15$ days
(d) $7$ days
Answer
612k+ views
Hint: We will first find the fraction of work they do in one day, each alone and together. And, we will calculate the work done in the last 3 days. Then we will use this data to solve the question.
Complete step-by-step answer:
According to question,
A completes the work in 14 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{14} \right)}^{th}}$ of the total work in one day.
And, B completes the work in 21 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{21} \right)}^{th}}$ of the total work in one day.
Now, if they work together, then the fraction of total work done by them in one day must be$=\dfrac{1}{14}+\dfrac{1}{21}$
Taking LCM and then adding, we get,
$\begin{align}
& =\dfrac{1\times 3}{14\times 3}+\dfrac{1\times 2}{21\times 2} \\
& =\dfrac{3}{42}+\dfrac{2}{42} \\
& =\dfrac{3+2}{42} \\
& =\dfrac{5}{42} \\
\end{align}$
Now, B has worked alone in the last 3 days after A leaves, to complete the work.
Also, fraction of total work done by B in 3 days = $3\times \dfrac{1}{21}$
=$\dfrac{1}{7}$.
Therefore, remaining fraction of work, that A and B have completed together = $1-\dfrac{1}{7}$
Taking LCM and then subtracting,
$\begin{align}
& =\dfrac{1\times 7}{1\times 7}-\dfrac{1}{7} \\
& =\dfrac{7-1}{7} \\
& =\dfrac{6}{7} \\
\end{align}$
Here, we have,
Number of days taken by A and B together to complete \[{{\left( \dfrac{5}{42} \right)}^{th}}\] of the total work = 1 day.
Therefore, the number of days taken by A and B together to complete the whole work = $\dfrac{42}{5}$ days.
Hence, number of days taken by A and B together to complete \[{{\left( \dfrac{6}{7} \right)}^{th}}\] of the total work,
$=\dfrac{42}{5}\times \dfrac{6}{7}$ days
Simplifying, we get,
$=\dfrac{6\times 6}{5}$ days
$=\dfrac{36}{5}$ days.
Therefore, time taken to complete the whole work,
$=\dfrac{36}{5}$ days + $3$ days
Taking LCM,
$=\left( \dfrac{36}{5}+\dfrac{3\times 5}{1\times 5} \right)$ days
$=\dfrac{36+15}{5}$ days
$=\dfrac{51}{5}$ days.
$=10\dfrac{1}{5}$ days
Hence, the correct answer is option (b).
Note: In such types of questions, do not confuse fraction of work with number of works. And keep in mind that if we are considering a fraction of work, then whole work will be represented by 1.
Complete step-by-step answer:
According to question,
A completes the work in 14 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{14} \right)}^{th}}$ of the total work in one day.
And, B completes the work in 21 days if he works alone. Therefore, he must have completed ${{\left( \dfrac{1}{21} \right)}^{th}}$ of the total work in one day.
Now, if they work together, then the fraction of total work done by them in one day must be$=\dfrac{1}{14}+\dfrac{1}{21}$
Taking LCM and then adding, we get,
$\begin{align}
& =\dfrac{1\times 3}{14\times 3}+\dfrac{1\times 2}{21\times 2} \\
& =\dfrac{3}{42}+\dfrac{2}{42} \\
& =\dfrac{3+2}{42} \\
& =\dfrac{5}{42} \\
\end{align}$
Now, B has worked alone in the last 3 days after A leaves, to complete the work.
Also, fraction of total work done by B in 3 days = $3\times \dfrac{1}{21}$
=$\dfrac{1}{7}$.
Therefore, remaining fraction of work, that A and B have completed together = $1-\dfrac{1}{7}$
Taking LCM and then subtracting,
$\begin{align}
& =\dfrac{1\times 7}{1\times 7}-\dfrac{1}{7} \\
& =\dfrac{7-1}{7} \\
& =\dfrac{6}{7} \\
\end{align}$
Here, we have,
Number of days taken by A and B together to complete \[{{\left( \dfrac{5}{42} \right)}^{th}}\] of the total work = 1 day.
Therefore, the number of days taken by A and B together to complete the whole work = $\dfrac{42}{5}$ days.
Hence, number of days taken by A and B together to complete \[{{\left( \dfrac{6}{7} \right)}^{th}}\] of the total work,
$=\dfrac{42}{5}\times \dfrac{6}{7}$ days
Simplifying, we get,
$=\dfrac{6\times 6}{5}$ days
$=\dfrac{36}{5}$ days.
Therefore, time taken to complete the whole work,
$=\dfrac{36}{5}$ days + $3$ days
Taking LCM,
$=\left( \dfrac{36}{5}+\dfrac{3\times 5}{1\times 5} \right)$ days
$=\dfrac{36+15}{5}$ days
$=\dfrac{51}{5}$ days.
$=10\dfrac{1}{5}$ days
Hence, the correct answer is option (b).
Note: In such types of questions, do not confuse fraction of work with number of works. And keep in mind that if we are considering a fraction of work, then whole work will be represented by 1.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Trending doubts
Who Won 36 Oscar Awards? Record Holder Revealed

Who is the executive head of the government APresident class 10 social science CBSE

State and prove the Pythagoras theorem-class-10-maths-CBSE

What are the public facilities provided by the government? Also explain each facility

What is the minimum age for fighting the election in class 10 social science CBSE

What is the full form of POSCO class 10 social science CBSE

