$A$ can do a piece of work in $10$ days, $B$ in $12$ days and $C$ in $15$ days. All begin together but $A$ leaves the work after $2$ days and $B$ leaves the $3$ days before the work is finished. How long did the work last?
$
{\text{A}}{\text{. 7 }}days \\
{\text{B}}{\text{. 2 }}days \\
{\text{C}}{\text{. 3 }}days \\
{\text{D}}{\text{. 8 }}days \\
$
Answer
639.6k+ views
Hint –For such types of questions, the approach should be to read the question carefully and put all your effort in understanding the question and write what is given as it will help us to analyse the question intricately. This will then help us to lead towards the desired answer.
Complete step-by-step answer:
According to question,
$A's$ one day’s work $ = \dfrac{1}{{10}}$
$B's$ one day’s work $ = \dfrac{1}{{12}}$
$C's$ one day’s work $ = \dfrac{1}{{15}}$
$A,B{\text{ and }}C's$ one day’s work $ = \dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}$
$ \Rightarrow \dfrac{{\left( {6 + 5 + 4} \right)}}{{60}} = \dfrac{{15}}{{60}} = \dfrac{1}{4}$
$A,B{\text{ and }}C's$ two day’s work $ = \dfrac{1}{4} \times 2 = \dfrac{1}{2}$
But $B$ leaves \[3\] days before the work gets finished, so $C$ does the remaining work alone.
$C's$ $3$ day’s work $ = \dfrac{1}{{15}} \times 3 = \dfrac{1}{5}$
Then work done in $2 + 3$ days $ = \dfrac{1}{2} + \dfrac{1}{5} = \dfrac{7}{{10}}$
Work done by $B + C$ together $ = 1 - \dfrac{7}{{10}} = \dfrac{3}{{10}}$
$\left( {B + C} \right)'s$ one day work $ = \dfrac{1}{{12}} + \dfrac{1}{{15}} = \dfrac{9}{{60}} = \dfrac{3}{{20}}$
So number of days worked by $B$ and $C$ together $ = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2$ days
So $A,B,C$ work for $2$ days,
$B,C$ work for $2$ days,
$C$ works for $3$ days.
Then total work done $ = 2 + 3 + 2 = 7$ days
$\therefore $ work will last for $7$ days.
Note – As you know, this is a work-time problem so there are many approaches to solve these types of problems. Here we first find the days, where work is done by all three i.e. $2$ and then days where $C$ works alone i.e. $3$. So, this equals $5$ days and now we have to find out the number of days in which remaining work is completed i.e. by $B{\text{ and }}C$ then we will add up all and get our required answer. Then match that sum of days with that one particular given option.
Complete step-by-step answer:
According to question,
$A's$ one day’s work $ = \dfrac{1}{{10}}$
$B's$ one day’s work $ = \dfrac{1}{{12}}$
$C's$ one day’s work $ = \dfrac{1}{{15}}$
$A,B{\text{ and }}C's$ one day’s work $ = \dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}$
$ \Rightarrow \dfrac{{\left( {6 + 5 + 4} \right)}}{{60}} = \dfrac{{15}}{{60}} = \dfrac{1}{4}$
$A,B{\text{ and }}C's$ two day’s work $ = \dfrac{1}{4} \times 2 = \dfrac{1}{2}$
But $B$ leaves \[3\] days before the work gets finished, so $C$ does the remaining work alone.
$C's$ $3$ day’s work $ = \dfrac{1}{{15}} \times 3 = \dfrac{1}{5}$
Then work done in $2 + 3$ days $ = \dfrac{1}{2} + \dfrac{1}{5} = \dfrac{7}{{10}}$
Work done by $B + C$ together $ = 1 - \dfrac{7}{{10}} = \dfrac{3}{{10}}$
$\left( {B + C} \right)'s$ one day work $ = \dfrac{1}{{12}} + \dfrac{1}{{15}} = \dfrac{9}{{60}} = \dfrac{3}{{20}}$
So number of days worked by $B$ and $C$ together $ = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2$ days
So $A,B,C$ work for $2$ days,
$B,C$ work for $2$ days,
$C$ works for $3$ days.
Then total work done $ = 2 + 3 + 2 = 7$ days
$\therefore $ work will last for $7$ days.
Note – As you know, this is a work-time problem so there are many approaches to solve these types of problems. Here we first find the days, where work is done by all three i.e. $2$ and then days where $C$ works alone i.e. $3$. So, this equals $5$ days and now we have to find out the number of days in which remaining work is completed i.e. by $B{\text{ and }}C$ then we will add up all and get our required answer. Then match that sum of days with that one particular given option.
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred

Master Class 7 Social Science: Engaging Questions & Answers for Success

Master Class 7 Science: Engaging Questions & Answers for Success

Master Class 7 Maths: Engaging Questions & Answers for Success

Class 7 Question and Answer - Your Ultimate Solutions Guide

Master Class 9 Social Science: Engaging Questions & Answers for Success

Trending doubts
Full Form of IASDMIPSIFSIRSPOLICE class 7 social science CBSE

Convert 200 Million dollars in rupees class 7 maths CBSE

How many thousands make a crore class 7 maths CBSE

When phenolphthalein is added toNaOH the colour of class 7 chemistry CBSE

Find HCF and LCM of 510 and 92 by applying the prime class 7 maths CBSE

How many 5digit numbers are there in all class 7 maths CBSE


