Answer
Verified
421.5k+ views
Hint –For such types of questions, the approach should be to read the question carefully and put all your effort in understanding the question and write what is given as it will help us to analyse the question intricately. This will then help us to lead towards the desired answer.
Complete step-by-step answer:
According to question,
$A's$ one day’s work $ = \dfrac{1}{{10}}$
$B's$ one day’s work $ = \dfrac{1}{{12}}$
$C's$ one day’s work $ = \dfrac{1}{{15}}$
$A,B{\text{ and }}C's$ one day’s work $ = \dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}$
$ \Rightarrow \dfrac{{\left( {6 + 5 + 4} \right)}}{{60}} = \dfrac{{15}}{{60}} = \dfrac{1}{4}$
$A,B{\text{ and }}C's$ two day’s work $ = \dfrac{1}{4} \times 2 = \dfrac{1}{2}$
But $B$ leaves \[3\] days before the work gets finished, so $C$ does the remaining work alone.
$C's$ $3$ day’s work $ = \dfrac{1}{{15}} \times 3 = \dfrac{1}{5}$
Then work done in $2 + 3$ days $ = \dfrac{1}{2} + \dfrac{1}{5} = \dfrac{7}{{10}}$
Work done by $B + C$ together $ = 1 - \dfrac{7}{{10}} = \dfrac{3}{{10}}$
$\left( {B + C} \right)'s$ one day work $ = \dfrac{1}{{12}} + \dfrac{1}{{15}} = \dfrac{9}{{60}} = \dfrac{3}{{20}}$
So number of days worked by $B$ and $C$ together $ = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2$ days
So $A,B,C$ work for $2$ days,
$B,C$ work for $2$ days,
$C$ works for $3$ days.
Then total work done $ = 2 + 3 + 2 = 7$ days
$\therefore $ work will last for $7$ days.
Note – As you know, this is a work-time problem so there are many approaches to solve these types of problems. Here we first find the days, where work is done by all three i.e. $2$ and then days where $C$ works alone i.e. $3$. So, this equals $5$ days and now we have to find out the number of days in which remaining work is completed i.e. by $B{\text{ and }}C$ then we will add up all and get our required answer. Then match that sum of days with that one particular given option.
Complete step-by-step answer:
According to question,
$A's$ one day’s work $ = \dfrac{1}{{10}}$
$B's$ one day’s work $ = \dfrac{1}{{12}}$
$C's$ one day’s work $ = \dfrac{1}{{15}}$
$A,B{\text{ and }}C's$ one day’s work $ = \dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}$
$ \Rightarrow \dfrac{{\left( {6 + 5 + 4} \right)}}{{60}} = \dfrac{{15}}{{60}} = \dfrac{1}{4}$
$A,B{\text{ and }}C's$ two day’s work $ = \dfrac{1}{4} \times 2 = \dfrac{1}{2}$
But $B$ leaves \[3\] days before the work gets finished, so $C$ does the remaining work alone.
$C's$ $3$ day’s work $ = \dfrac{1}{{15}} \times 3 = \dfrac{1}{5}$
Then work done in $2 + 3$ days $ = \dfrac{1}{2} + \dfrac{1}{5} = \dfrac{7}{{10}}$
Work done by $B + C$ together $ = 1 - \dfrac{7}{{10}} = \dfrac{3}{{10}}$
$\left( {B + C} \right)'s$ one day work $ = \dfrac{1}{{12}} + \dfrac{1}{{15}} = \dfrac{9}{{60}} = \dfrac{3}{{20}}$
So number of days worked by $B$ and $C$ together $ = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2$ days
So $A,B,C$ work for $2$ days,
$B,C$ work for $2$ days,
$C$ works for $3$ days.
Then total work done $ = 2 + 3 + 2 = 7$ days
$\therefore $ work will last for $7$ days.
Note – As you know, this is a work-time problem so there are many approaches to solve these types of problems. Here we first find the days, where work is done by all three i.e. $2$ and then days where $C$ works alone i.e. $3$. So, this equals $5$ days and now we have to find out the number of days in which remaining work is completed i.e. by $B{\text{ and }}C$ then we will add up all and get our required answer. Then match that sum of days with that one particular given option.
Recently Updated Pages
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Find the values of other five trigonometric functions class 10 maths CBSE
Trending doubts
State the differences between manure and fertilize class 8 biology CBSE
Why are xylem and phloem called complex tissues aBoth class 11 biology CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Difference Between Plant Cell and Animal Cell
What would happen if plasma membrane ruptures or breaks class 11 biology CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
What precautions do you take while observing the nucleus class 11 biology CBSE
What would happen to the life of a cell if there was class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE