Answer
Verified
373.2k+ views
Hint:
Here we are given the time period when each one of $A, B, C$ can complete the work individually. So we can find one day's work each and then according to the question, we can find the $2{\text{ day}}$ work of A and we also know that C works for the last three days alone. So we can find this work also and now with the leftover work we can find the total days also.
Complete step by step solution:
We are given here that A can do a piece of work in $10$ days, B in $12$ days and C in $15$ days.
We know that if the person completes work in $m{\text{ days}}$ then his one day work$ = \dfrac{1}{m}$
So we know A completes work in $10{\text{ days}}$ individually
So A’s one day work$ = \dfrac{1}{{10}}$
Similarly B’s one day work$ = \dfrac{1}{{12}}$
C’s one day work$ = \dfrac{1}{{15}}$
So we can find one day work when all are working together$ = $one day work of $(A + B + C)$
$ = \left( {\dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}} \right)$
LCM of $10,12,15{\text{ is 120}}$ so making the denominators common which is $120$
One day work when all work together$ = \dfrac{{12 + 10 + 8}}{{120}} = \dfrac{{30}}{{120}} = \dfrac{1}{4}$
We know that all of them worked for two days together.
So $(A + B + C)'{\text{s}}$ two day work$ = {\text{their one day work}} \times {\text{2}} = \dfrac{1}{4}(2) = \dfrac{1}{2}$$ - - - (1)$
We also know that B also leaves three days before the work ends. So it means that for the last $3{\text{ days}}$ only C has worked.
So C’s three day work$ = C'{\text{s one day work}} \times 3 = \dfrac{1}{{15}}(3) = \dfrac{1}{5}$$ - - - (2)$
So we can add equation (1) and (2) to get the total work that has been completed..
So we get the work done till now$\dfrac{1}{2} + \dfrac{1}{5} = \dfrac{{5 + 2}}{{10}} = \dfrac{7}{{10}}$
Now we get that $\dfrac{7}{{10}}$ of the work has been completed.
Hence the work left$ = 1 - \dfrac{7}{{10}} = \dfrac{{10 - 7}}{{10}} = \dfrac{3}{{10}}$
So we can say that this leftover work has been done by $B{\text{ and }}C$
Now $(B + C)'s$ one day work$ = \dfrac{1}{{12}} + \dfrac{1}{{15}} = \dfrac{{5 + 4}}{{60}} = \dfrac{9}{{60}} = \dfrac{3}{{20}}$
Work done by $B{\text{ and }}C = \dfrac{3}{{10}}$
So we know that ${\text{total work done}} = {\text{one day's work}} \times {\text{number of days taken}}$
Substituting the values we get:
$
\dfrac{3}{{10}} = \dfrac{3}{{20}} \times {\text{number of days taken}} \\
{\text{number of days}} = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2{\text{ days}} \\
$
Hence we can say that total days to complete$ = (2 + 2 + 3) = 7{\text{ days}}$
Hence option A is correct.
Note:
Here in these types of problems, we need to find the one day work of a person and then proceed in the proper way as shown. We must know that ${\text{total work done}} = {\text{one day's work}} \times {\text{number of days taken}}$
Here we are given the time period when each one of $A, B, C$ can complete the work individually. So we can find one day's work each and then according to the question, we can find the $2{\text{ day}}$ work of A and we also know that C works for the last three days alone. So we can find this work also and now with the leftover work we can find the total days also.
Complete step by step solution:
We are given here that A can do a piece of work in $10$ days, B in $12$ days and C in $15$ days.
We know that if the person completes work in $m{\text{ days}}$ then his one day work$ = \dfrac{1}{m}$
So we know A completes work in $10{\text{ days}}$ individually
So A’s one day work$ = \dfrac{1}{{10}}$
Similarly B’s one day work$ = \dfrac{1}{{12}}$
C’s one day work$ = \dfrac{1}{{15}}$
So we can find one day work when all are working together$ = $one day work of $(A + B + C)$
$ = \left( {\dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}} \right)$
LCM of $10,12,15{\text{ is 120}}$ so making the denominators common which is $120$
One day work when all work together$ = \dfrac{{12 + 10 + 8}}{{120}} = \dfrac{{30}}{{120}} = \dfrac{1}{4}$
We know that all of them worked for two days together.
So $(A + B + C)'{\text{s}}$ two day work$ = {\text{their one day work}} \times {\text{2}} = \dfrac{1}{4}(2) = \dfrac{1}{2}$$ - - - (1)$
We also know that B also leaves three days before the work ends. So it means that for the last $3{\text{ days}}$ only C has worked.
So C’s three day work$ = C'{\text{s one day work}} \times 3 = \dfrac{1}{{15}}(3) = \dfrac{1}{5}$$ - - - (2)$
So we can add equation (1) and (2) to get the total work that has been completed..
So we get the work done till now$\dfrac{1}{2} + \dfrac{1}{5} = \dfrac{{5 + 2}}{{10}} = \dfrac{7}{{10}}$
Now we get that $\dfrac{7}{{10}}$ of the work has been completed.
Hence the work left$ = 1 - \dfrac{7}{{10}} = \dfrac{{10 - 7}}{{10}} = \dfrac{3}{{10}}$
So we can say that this leftover work has been done by $B{\text{ and }}C$
Now $(B + C)'s$ one day work$ = \dfrac{1}{{12}} + \dfrac{1}{{15}} = \dfrac{{5 + 4}}{{60}} = \dfrac{9}{{60}} = \dfrac{3}{{20}}$
Work done by $B{\text{ and }}C = \dfrac{3}{{10}}$
So we know that ${\text{total work done}} = {\text{one day's work}} \times {\text{number of days taken}}$
Substituting the values we get:
$
\dfrac{3}{{10}} = \dfrac{3}{{20}} \times {\text{number of days taken}} \\
{\text{number of days}} = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2{\text{ days}} \\
$
Hence we can say that total days to complete$ = (2 + 2 + 3) = 7{\text{ days}}$
Hence option A is correct.
Note:
Here in these types of problems, we need to find the one day work of a person and then proceed in the proper way as shown. We must know that ${\text{total work done}} = {\text{one day's work}} \times {\text{number of days taken}}$
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Trending doubts
State the differences between manure and fertilize class 8 biology CBSE
Why are xylem and phloem called complex tissues aBoth class 11 biology CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Difference Between Plant Cell and Animal Cell
What would happen if plasma membrane ruptures or breaks class 11 biology CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
What precautions do you take while observing the nucleus class 11 biology CBSE
What would happen to the life of a cell if there was class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE