
A can do a job in 10 days and B in 20 days. They work together, but 4 days before the finish of the job, A left. How many days did they work together?
(A) 6
(B) \[\dfrac{16}{3}\]
(C) 8
(D) 14
Answer
596.4k+ views
Hint: It is given that A can do a job in 10 days and B in 20 days. The part of the work done by A and B in 1 day is \[\dfrac{1}{10}\] and \[\dfrac{1}{20}\] respectively. Now, calculate the part of the work done by B in 4 days. The part of the work done when A and B worked together is \[\dfrac{4}{5}\] . Now, calculate the part of work done in 1 day when A and B worked together. Then, calculate one part of the work done when A and B worked together. Now, get the number of days to finish \[\dfrac{4}{5}\] part of the work.
Complete step-by-step answer:
According to the question, we have been given that,
The time taken by A to finish the whole part of a work = 10 days.
Using the unitary method, calculating,
The part of work done by A in 1 day = \[\dfrac{1}{10}\] ……………………………..(1)
We have also been given the time taken by B to finish the whole part of a work = 20 days.
Using the unitary method, calculating,
The part of work done by B in 1 day = \[\dfrac{1}{20}\] ……………………………..(2)
We have also been given that A left the job 4 days before the finish of the job.
It means that B alone worked for 4 days.
From equation (2), we have the part of the work done by B in 1 day.
Using the unitary method, calculating,
The part of the work done by B in 4 days = \[4\times \dfrac{1}{20}=\dfrac{1}{5}\] ………………………………..(3)
In the whole part of work, some part of work is done by alone B while some part of the work is one by A and B together.
The remaining part of the work that was done when A and B worked together = \[1-\dfrac{1}{5}=\dfrac{5-1}{5}=\dfrac{4}{5}\] ……………………………(4)
The part of work done in 1 day when A and B worked together = \[\dfrac{1}{10}+\dfrac{1}{20}=\dfrac{2+1}{20}=\dfrac{3}{20}\] …………………………….(5)
It means that \[\dfrac{3}{20}\] part of the work is done 1 day when A and B work together.
Now, using the unitary method, calculating,
The time required to finish the work when A and B worked together = \[\dfrac{20}{3}\] days ……………………………(6)
From equation (4), we have the part of the work done when A and B worked together.
Now, using the unitary method, calculating,
The number of days taken to finish \[\dfrac{4}{5}\] part of the work when A and B worked together = \[\dfrac{4}{5}\times \dfrac{20}{3}=\dfrac{16}{3}\] …………………………….(7)
Hence, the number of days when A and B worked together is \[\dfrac{16}{3}\] days.
Note: In this question, one might make a silly mistake while calculating the part of work done in 1 day when A and B worked together and calculate it by the product of the part of work done by A in 1 day and the part of work done by B. This is wrong. The correct way to calculate the part of the work done in 1 day when A and B worked together is the summation of the part of work done by A in 1 day and the part of work done by B.
Complete step-by-step answer:
According to the question, we have been given that,
The time taken by A to finish the whole part of a work = 10 days.
Using the unitary method, calculating,
The part of work done by A in 1 day = \[\dfrac{1}{10}\] ……………………………..(1)
We have also been given the time taken by B to finish the whole part of a work = 20 days.
Using the unitary method, calculating,
The part of work done by B in 1 day = \[\dfrac{1}{20}\] ……………………………..(2)
We have also been given that A left the job 4 days before the finish of the job.
It means that B alone worked for 4 days.
From equation (2), we have the part of the work done by B in 1 day.
Using the unitary method, calculating,
The part of the work done by B in 4 days = \[4\times \dfrac{1}{20}=\dfrac{1}{5}\] ………………………………..(3)
In the whole part of work, some part of work is done by alone B while some part of the work is one by A and B together.
The remaining part of the work that was done when A and B worked together = \[1-\dfrac{1}{5}=\dfrac{5-1}{5}=\dfrac{4}{5}\] ……………………………(4)
The part of work done in 1 day when A and B worked together = \[\dfrac{1}{10}+\dfrac{1}{20}=\dfrac{2+1}{20}=\dfrac{3}{20}\] …………………………….(5)
It means that \[\dfrac{3}{20}\] part of the work is done 1 day when A and B work together.
Now, using the unitary method, calculating,
The time required to finish the work when A and B worked together = \[\dfrac{20}{3}\] days ……………………………(6)
From equation (4), we have the part of the work done when A and B worked together.
Now, using the unitary method, calculating,
The number of days taken to finish \[\dfrac{4}{5}\] part of the work when A and B worked together = \[\dfrac{4}{5}\times \dfrac{20}{3}=\dfrac{16}{3}\] …………………………….(7)
Hence, the number of days when A and B worked together is \[\dfrac{16}{3}\] days.
Note: In this question, one might make a silly mistake while calculating the part of work done in 1 day when A and B worked together and calculate it by the product of the part of work done by A in 1 day and the part of work done by B. This is wrong. The correct way to calculate the part of the work done in 1 day when A and B worked together is the summation of the part of work done by A in 1 day and the part of work done by B.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
What is the median of the first 10 natural numbers class 10 maths CBSE

Which women's tennis player has 24 Grand Slam singles titles?

Who is the Brand Ambassador of Incredible India?

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

A moving boat is observed from the top of a 150 m high class 10 maths CBSE

