
A and B together can do a piece of work in 12 days which B and C together do in 16 days. After A has been working at it for 5 days, B for 7 days, C finished it in 13 days. In how much time C alone will do the work?
Answer
499.8k+ views
Hint:First we find the one day work for A, B and C.Here a given that the work doing by A and B together and also B and C together so we can split the work of A’s, B’s and C’s Finally, we will find time taken by C to complete the work.
Complete step-by-step answer:
Here, it is given that,
A and B together can do a piece of work in 12 days and B and C together do in 16 days
A works for 5 days, B works for 7 days than C completes the remaining work in 13 days
Let’s solve this question arithmetically:
As A and B can finish the work in 12 days’ time, hence
(A + B)’s one day’s work =
Similarly
(B + C)’s one day’s work =
Now, A’s 5 days’ work + B’s 7 days’ work + C’s 13 days’ work = 1
A’s 5 days’ work + B’s 5 days’ work + B’s 2 days’ work + C’s 2 days’ work + C’s 11 days’ work = 1
Or {(A + B)’s 5 days’ work} + {(B + C)’s 2 days’ work} + C’s 11 days’ work = 1
i.e. + C’s 11 days’ work = 1
or C’s 11 days’ work
or C’s 11 days’ work
or C’s 11 days’ work
or C’s 1 day’s work
Therefore, C alone can finish the complete work in 24 days.
Note:Mathematically we say that if A can complete a work in n days, work done by A in day is . And if A can complete part of the work in day, then A will complete the work in n days.
Complete step-by-step answer:
Here, it is given that,
A and B together can do a piece of work in 12 days and B and C together do in 16 days
A works for 5 days, B works for 7 days than C completes the remaining work in 13 days
Let’s solve this question arithmetically:
As A and B can finish the work in 12 days’ time, hence
(A + B)’s one day’s work =
Similarly
(B + C)’s one day’s work =
Now, A’s 5 days’ work + B’s 7 days’ work + C’s 13 days’ work = 1
A’s 5 days’ work + B’s 5 days’ work + B’s 2 days’ work + C’s 2 days’ work + C’s 11 days’ work = 1
Or {(A + B)’s 5 days’ work} + {(B + C)’s 2 days’ work} + C’s 11 days’ work = 1
i.e.
or C’s 11 days’ work
or C’s 11 days’ work
or C’s 11 days’ work
or C’s 1 day’s work
Therefore, C alone can finish the complete work in 24 days.
Note:Mathematically we say that if A can complete a work in n days, work done by A in
Recently Updated Pages
Express the following as a fraction and simplify a class 7 maths CBSE

The length and width of a rectangle are in ratio of class 7 maths CBSE

The ratio of the income to the expenditure of a family class 7 maths CBSE

How do you write 025 million in scientific notatio class 7 maths CBSE

How do you convert 295 meters per second to kilometers class 7 maths CBSE

Write the following in Roman numerals 25819 class 7 maths CBSE

Trending doubts
Where did Netaji set up the INA headquarters A Yangon class 10 social studies CBSE

A boat goes 24 km upstream and 28 km downstream in class 10 maths CBSE

Why is there a time difference of about 5 hours between class 10 social science CBSE

The British separated Burma Myanmar from India in 1935 class 10 social science CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

What are the public facilities provided by the government? Also explain each facility
