Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store

A and B together can do a piece of work in 12 days which B and C together do in 16 days. After A has been working at it for 5 days, B for 7 days, C finished it in 13 days. In how much time C alone will do the work?

seo-qna
Last updated date: 17th Jun 2024
Total views: 412.8k
Views today: 9.12k
Answer
VerifiedVerified
412.8k+ views
Hint:First we find the one day work for A, B and C.Here a given that the work doing by A and B together and also B and C together so we can split the work of A’s, B’s and C’s Finally, we will find time taken by C to complete the work.

Complete step-by-step answer:
Here, it is given that,
A and B together can do a piece of work in 12 days and B and C together do in 16 days
A works for 5 days, B works for 7 days than C completes the remaining work in 13 days
Let’s solve this question arithmetically:
As A and B can finish the work in 12 days’ time, hence
(A + B)’s one day’s work = \[\dfrac{1}{{12}}\]
Similarly
(B + C)’s one day’s work = \[\dfrac{1}{{16}}\]
Now, A’s 5 days’ work + B’s 7 days’ work + C’s 13 days’ work = 1
A’s 5 days’ work + B’s 5 days’ work + B’s 2 days’ work + C’s 2 days’ work + C’s 11 days’ work = 1
Or {(A + B)’s 5 days’ work} + {(B + C)’s 2 days’ work} + C’s 11 days’ work = 1
i.e. $\dfrac{5}{12} + \dfrac{2}{16}$ + C’s 11 days’ work = 1
or C’s 11 days’ work \[ = 1 - \left( {\dfrac{5}{{12}} + \dfrac{2}{{16}}} \right)\]
or C’s 11 days’ work \[ = 1 - \dfrac{{13}}{{24}}\]
or C’s 11 days’ work \[ = \dfrac{{11}}{{24}}\]
or C’s 1 day’s work \[ = \dfrac{{11}}{{24}} \times \dfrac{1}{{11}} = \dfrac{1}{{24}}\]
Therefore, C alone can finish the complete work in 24 days.

Note:Mathematically we say that if A can complete a work in n days, work done by A in \[1\] day is \[\dfrac{1}{n}\]. And if A can complete \[\dfrac{1}{n}\] part of the work in \[1\] day, then A will complete the work in n days.