Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store

A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days. How long does it take if they work on it together?
(a) 14 days
(b) 30 days
(c) 20 days
(d) 18 days

seo-qna
Last updated date: 23rd Apr 2024
•
Total views: 399.6k
•
Views today: 10.99k
Answer
VerifiedVerified
399.6k+ views
Hint: To solve this question we consider that the total amount of work is 100%. Then, we will find the percentage of work done by A and B is one day, percentage of work done by B and C in one day and percentage of work done by A and C in one day. Then, with this information we will find the percentage of work done in one day when all of them work together and then find the number of days required to complete the work.

Complete step by step solution:
A and B require 40 days to complete 100 % work. So, percentage of work completed by A and B in one day can found out as:
A + B 🡪 $\dfrac{100\%}{40}=2.5\%.......\left( 1 \right)$
B and C required 30 days to complete 100 % work. So, percentage of work completed by B and C in one day can found out as:
 B + C 🡪 $\dfrac{100\%}{30}=3.33\%.......\left( 2 \right)$
C and A required 24 days to complete 100 % work. So, percentage of work completed by C and A in one day can found out as:
 C + A 🡪 $\dfrac{100\%}{24}=4.16\%.......\left( 3 \right)$
Now add (1), (2) and (3) and find the value of A + B + C.
\[\begin{align}
  & \Rightarrow 2A+2B+2C=\left( 2.5+1.33+4.16 \right)\% \\
 & \Rightarrow 2\left( A+B+C \right)=10\% \\
 & \Rightarrow A+B+C=5\% \\
\end{align}\]
So, 5 % of work is completed in one day if A, B and C work together.
Therefore, the number of days to complete the work is $\dfrac{100}{5}=20$.
Therefore, option (c) is the correct option.

Note: Most of the Work-time questions can be solved by finding the work done in unit time. Students can also take the LCM of days instead of 100% to represent the full piece of work.

Recently Updated Pages