
A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days. How long does it take if they work on it together?
(a) 14 days
(b) 30 days
(c) 20 days
(d) 18 days
Answer
584.4k+ views
Hint: To solve this question we consider that the total amount of work is 100%. Then, we will find the percentage of work done by A and B is one day, percentage of work done by B and C in one day and percentage of work done by A and C in one day. Then, with this information we will find the percentage of work done in one day when all of them work together and then find the number of days required to complete the work.
Complete step by step solution:
A and B require 40 days to complete 100 % work. So, percentage of work completed by A and B in one day can found out as:
A + B 🡪 $\dfrac{100\%}{40}=2.5\%.......\left( 1 \right)$
B and C required 30 days to complete 100 % work. So, percentage of work completed by B and C in one day can found out as:
B + C 🡪 $\dfrac{100\%}{30}=3.33\%.......\left( 2 \right)$
C and A required 24 days to complete 100 % work. So, percentage of work completed by C and A in one day can found out as:
C + A 🡪 $\dfrac{100\%}{24}=4.16\%.......\left( 3 \right)$
Now add (1), (2) and (3) and find the value of A + B + C.
\[\begin{align}
& \Rightarrow 2A+2B+2C=\left( 2.5+1.33+4.16 \right)\% \\
& \Rightarrow 2\left( A+B+C \right)=10\% \\
& \Rightarrow A+B+C=5\% \\
\end{align}\]
So, 5 % of work is completed in one day if A, B and C work together.
Therefore, the number of days to complete the work is $\dfrac{100}{5}=20$.
Therefore, option (c) is the correct option.
Note: Most of the Work-time questions can be solved by finding the work done in unit time. Students can also take the LCM of days instead of 100% to represent the full piece of work.
Complete step by step solution:
A and B require 40 days to complete 100 % work. So, percentage of work completed by A and B in one day can found out as:
A + B 🡪 $\dfrac{100\%}{40}=2.5\%.......\left( 1 \right)$
B and C required 30 days to complete 100 % work. So, percentage of work completed by B and C in one day can found out as:
B + C 🡪 $\dfrac{100\%}{30}=3.33\%.......\left( 2 \right)$
C and A required 24 days to complete 100 % work. So, percentage of work completed by C and A in one day can found out as:
C + A 🡪 $\dfrac{100\%}{24}=4.16\%.......\left( 3 \right)$
Now add (1), (2) and (3) and find the value of A + B + C.
\[\begin{align}
& \Rightarrow 2A+2B+2C=\left( 2.5+1.33+4.16 \right)\% \\
& \Rightarrow 2\left( A+B+C \right)=10\% \\
& \Rightarrow A+B+C=5\% \\
\end{align}\]
So, 5 % of work is completed in one day if A, B and C work together.
Therefore, the number of days to complete the work is $\dfrac{100}{5}=20$.
Therefore, option (c) is the correct option.
Note: Most of the Work-time questions can be solved by finding the work done in unit time. Students can also take the LCM of days instead of 100% to represent the full piece of work.
Recently Updated Pages
What were the main features of Sulhikul class 10 social studies CBSE

Find the area of the following figure class 10 maths CBSE

Write short notes to show what you know about Vernacular class 10 social studies CBSE

Write a Pythagorean triplet whose one member is A 6 class 10 maths CBSE

What will happen if all the carnivores are removed class 10 biology CBSE

State one prudential reason and one moral reason for class 10 social science CBSE

Trending doubts
The shortest day of the year in India

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

What is the missing number in the sequence 259142027 class 10 maths CBSE

