
A and B can do a job in $12\,days$ and B and C can do it in $16\,days$. After A has been working for $5\,days$ and B for $7\,days$, C finishes rest of work in $13\,days$, in how many days can C do the above work alone .
$
a)\,\,18\,days \\
b)\,\,36\,days \\
c)\,\,48\,days \\
d)\,\,24\,days \\
$
Answer
593.7k+ views
Hint: Assume A takes $a$ days, B takes $b$ days and C takes $c$ days to finish the work, then one day work for A, B and C is $\dfrac{1}{a},\dfrac{1}{b},\dfrac{1}{c}$ respectively.
Now you are given three conditions, solve them and get the answer
Complete step-by-step answer: Here according to question, A and B can do the job in $12\,days$ and the same job is done by B and C in $16\,days$.
So, let A alone do the work in $a\,days$
Let B alone do the work in $b\,days$
Let C alone do the work in $c\,days$
So we can say that one day work for A, B and C is $\dfrac{1}{a},\dfrac{1}{b},\dfrac{1}{c}$ respectively.
So first it is given that A and B can do the job in $12\,days$
$\therefore \dfrac{1}{a} + \dfrac{1}{b} = \dfrac{1}{{12}}$ $ \to \left( 1 \right)$
Also it is said that B and C can do it in $16\,days$
$\therefore \,\dfrac{1}{b} + \dfrac{1}{c} = \dfrac{1}{{16}}$ $ \to \left( 2 \right)$
And after that question says that if A works for $5\,days$ and B works for $7\,days$ but after A and B has completed the rest work has been completed by C then $13\,days$.
$\therefore \dfrac{5}{a} + \dfrac{7}{b} + \dfrac{{13}}{c} = 1$ $ \to \left( 3 \right)$
Mow we have three equations and three variables,
Now let’s add equation (1) and equation (2)
$\therefore \dfrac{1}{a} + \dfrac{1}{b}$$ + \,\dfrac{1}{b} + \dfrac{1}{c}$$ = \dfrac{1}{{12}} + \dfrac{1}{{16}}$
$\dfrac{1}{a} + \dfrac{2}{b} + \dfrac{1}{c} = \dfrac{7}{{48}}$
Now if we multiply the first equation with $5$ and the second equation with $2$ and add them we will get
$
5\left( {\dfrac{1}{a} + \dfrac{1}{b}} \right) + 2\left( {\dfrac{1}{b} + \dfrac{1}{c}} \right) = \dfrac{5}{{12}} + \dfrac{2}{{16}} \\
\dfrac{5}{a} + \dfrac{7}{b} + \dfrac{2}{c} = \dfrac{{26}}{{48}}\,\,\,\,\,\,\,\,\, \to \left( 4 \right) \\
$
Now if we subtract equation (4) from equation (3)
$
\left( {\dfrac{5}{a} + \dfrac{7}{b} + \dfrac{{13}}{c}} \right) - \left( {\dfrac{5}{a} + \dfrac{7}{b} + \dfrac{2}{c}} \right) = 1 - \dfrac{{26}}{{48}} \\
\dfrac{{11}}{c} = \dfrac{{48 - 26}}{{48}} \\
c = \dfrac{{11 \times 48}}{{22}} \\
c = 24\,days \\
$
Hence we can say that C alone will take $24\,days$ to complete the work.
Note: If this type of question is given you have to assume the total days to complete the work by A, B & C and then generate equations by using their one day work that is $\dfrac{1}{a},\,\dfrac{1}{b},\,\dfrac{1}{c}$ respectively.
Now you are given three conditions, solve them and get the answer
Complete step-by-step answer: Here according to question, A and B can do the job in $12\,days$ and the same job is done by B and C in $16\,days$.
So, let A alone do the work in $a\,days$
Let B alone do the work in $b\,days$
Let C alone do the work in $c\,days$
So we can say that one day work for A, B and C is $\dfrac{1}{a},\dfrac{1}{b},\dfrac{1}{c}$ respectively.
So first it is given that A and B can do the job in $12\,days$
$\therefore \dfrac{1}{a} + \dfrac{1}{b} = \dfrac{1}{{12}}$ $ \to \left( 1 \right)$
Also it is said that B and C can do it in $16\,days$
$\therefore \,\dfrac{1}{b} + \dfrac{1}{c} = \dfrac{1}{{16}}$ $ \to \left( 2 \right)$
And after that question says that if A works for $5\,days$ and B works for $7\,days$ but after A and B has completed the rest work has been completed by C then $13\,days$.
$\therefore \dfrac{5}{a} + \dfrac{7}{b} + \dfrac{{13}}{c} = 1$ $ \to \left( 3 \right)$
Mow we have three equations and three variables,
Now let’s add equation (1) and equation (2)
$\therefore \dfrac{1}{a} + \dfrac{1}{b}$$ + \,\dfrac{1}{b} + \dfrac{1}{c}$$ = \dfrac{1}{{12}} + \dfrac{1}{{16}}$
$\dfrac{1}{a} + \dfrac{2}{b} + \dfrac{1}{c} = \dfrac{7}{{48}}$
Now if we multiply the first equation with $5$ and the second equation with $2$ and add them we will get
$
5\left( {\dfrac{1}{a} + \dfrac{1}{b}} \right) + 2\left( {\dfrac{1}{b} + \dfrac{1}{c}} \right) = \dfrac{5}{{12}} + \dfrac{2}{{16}} \\
\dfrac{5}{a} + \dfrac{7}{b} + \dfrac{2}{c} = \dfrac{{26}}{{48}}\,\,\,\,\,\,\,\,\, \to \left( 4 \right) \\
$
Now if we subtract equation (4) from equation (3)
$
\left( {\dfrac{5}{a} + \dfrac{7}{b} + \dfrac{{13}}{c}} \right) - \left( {\dfrac{5}{a} + \dfrac{7}{b} + \dfrac{2}{c}} \right) = 1 - \dfrac{{26}}{{48}} \\
\dfrac{{11}}{c} = \dfrac{{48 - 26}}{{48}} \\
c = \dfrac{{11 \times 48}}{{22}} \\
c = 24\,days \\
$
Hence we can say that C alone will take $24\,days$ to complete the work.
Note: If this type of question is given you have to assume the total days to complete the work by A, B & C and then generate equations by using their one day work that is $\dfrac{1}{a},\,\dfrac{1}{b},\,\dfrac{1}{c}$ respectively.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
What is the median of the first 10 natural numbers class 10 maths CBSE

Which women's tennis player has 24 Grand Slam singles titles?

Who is the Brand Ambassador of Incredible India?

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

A moving boat is observed from the top of a 150 m high class 10 maths CBSE

