
24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besides 12 men and 6 women?
Answer
516.3k+ views
Hint: The total amount of work to be done remains constant irrespective of the factor of who is doing the work. Let the work capacities of the male workers and female workers be x and y, respectively. So, the total work to be finished comes to be $24\times 16x$ , in terms of x and $18y\times 32$ , in terms of y.
Complete step-by-step solution -
To start with the solution, we let the work done by a male worker per day be x, and the work done by a female worker per day be y.
Total work done in n number days is given by:
$n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
Now, try to interpret the statement given in the question in mathematical terms using the above formula, we get:
$\text{Total work that needs to be completed=24}\times \text{16x}$ .
Also;
$\text{Total work that needs to be completed=18}\times \text{32y}$ .
Total work is independent of the number of workers and the type of worker doing the work.
$\therefore 24\times 16x=18\times 32y$
$\Rightarrow 2x=3y$
$\Rightarrow \dfrac{2x}{3}=y............(i)$
Now we let the number of additional male workers required to be p to finish the work in the next two days after 12 men and 6 women have worked for 16 days.
$\text{Total work that needs to be completed = }n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
$\Rightarrow \text{Total work that needs to be completed = 16}\left( 12x+6y \right)+2\left( 12x+px \right)$ .
Substituting Total work from equation (i).
$\text{24}\times \text{16x = 16}\left( 12x+6y \right)+2\left( 12x+px \right)$
On substituting the value of y from equation (i), we get:
$\text{24}\times \text{16x = 16}\left( 12x+\dfrac{2}{3}\times 6x \right)+2\left( 12x+px \right)$
$\Rightarrow \text{24}\times \text{16x = 16}\left( 12x+4x \right)+2\left( 12x+px \right)$
$\Rightarrow \text{24}\times \text{16x = 16}\times \text{16x}+2\left( 12x+px \right)$
$\Rightarrow 8\times \text{16x = }2\left( 12x+px \right)$
$\Rightarrow 64\text{x =}\left( 12+p \right)x$
$\therefore p=52\text{ male workers}$ .
Therefore, we can say that the answer to the above question is 52 men.
Note: In this question, including work, have two things to be wisely selected. One is the elements of the problem that you are treating as variables, and the other is the unit of work. You can either let work done per unit time of each worker as variables or the total work to be a variable. The choice of unit and element for variable decides the complexity of solving.
Complete step-by-step solution -
To start with the solution, we let the work done by a male worker per day be x, and the work done by a female worker per day be y.
Total work done in n number days is given by:
$n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
Now, try to interpret the statement given in the question in mathematical terms using the above formula, we get:
$\text{Total work that needs to be completed=24}\times \text{16x}$ .
Also;
$\text{Total work that needs to be completed=18}\times \text{32y}$ .
Total work is independent of the number of workers and the type of worker doing the work.
$\therefore 24\times 16x=18\times 32y$
$\Rightarrow 2x=3y$
$\Rightarrow \dfrac{2x}{3}=y............(i)$
Now we let the number of additional male workers required to be p to finish the work in the next two days after 12 men and 6 women have worked for 16 days.
$\text{Total work that needs to be completed = }n\times \sum{\left( \text{work capacity of each worker working} \right)\text{.}}$
$\Rightarrow \text{Total work that needs to be completed = 16}\left( 12x+6y \right)+2\left( 12x+px \right)$ .
Substituting Total work from equation (i).
$\text{24}\times \text{16x = 16}\left( 12x+6y \right)+2\left( 12x+px \right)$
On substituting the value of y from equation (i), we get:
$\text{24}\times \text{16x = 16}\left( 12x+\dfrac{2}{3}\times 6x \right)+2\left( 12x+px \right)$
$\Rightarrow \text{24}\times \text{16x = 16}\left( 12x+4x \right)+2\left( 12x+px \right)$
$\Rightarrow \text{24}\times \text{16x = 16}\times \text{16x}+2\left( 12x+px \right)$
$\Rightarrow 8\times \text{16x = }2\left( 12x+px \right)$
$\Rightarrow 64\text{x =}\left( 12+p \right)x$
$\therefore p=52\text{ male workers}$ .
Therefore, we can say that the answer to the above question is 52 men.
Note: In this question, including work, have two things to be wisely selected. One is the elements of the problem that you are treating as variables, and the other is the unit of work. You can either let work done per unit time of each worker as variables or the total work to be a variable. The choice of unit and element for variable decides the complexity of solving.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Trending doubts
When Sambhaji Maharaj died a 11 February 1689 b 11 class 8 social science CBSE

How many ounces are in 500 mL class 8 maths CBSE

Advantages and disadvantages of science

1 meter is equal to how many feet class 8 maths CBSE

In Indian rupees 1 trillion is equal to how many c class 8 maths CBSE

What led to the incident of Bloody Sunday in Russia class 8 social science CBSE
