Courses
Courses for Kids
Free study material
Offline Centres
More
Store Icon
Store
seo-qna
SearchIcon
banner

2 women and 5 men can finish a piece of embroidery in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the embroidery and that taken by 1 man alone?

Answer
VerifiedVerified
501k+ views
like imagedislike image
Hint: Start by assuming the number of days taken by men and women for the work as some variable, Then compute the work done by men , women in one day , this gives us their efficiency. Form the equations using them as per the statement given in the question and solve for the values of variables.

Complete step-by-step answer:
Let us consider , 1 woman can finish the embroidery work in ‘x’ days and 1 man can finish it in ‘y’ days.
So , 1 woman’s one day work =1x
Similarly , 1 man’s one day work =1y
According to the statement in the question,
One day work of 2 women and 5 men =2x+5y=14
One day work of 3 women and 6 men =3x+6y=13
Let 1x=a and 1y=b
Now, 2a+5b=14eqn.1
3a+6b=13eqn.2
Multiply eqn.1 by 3 and eqn.2 by 2, Then subtract them eqn.1 – eqn.2 , we get
3b=112b=136
Putting b=136 in eqn.1 , we get
22a+5(136)=14
Multiply by 36 both side
72a+5=9
Taking 5 to right side
72a=95a=118
Now ,Substituting the values to get x and y . We get,
a=1x=118,b=1y=136
So, One woman can finish the embroidery work in 18days and one man can finish the work in 36 days.

Note: Similar questions can be asked with a slight twist by adding or removing people midway of the project. In that case form equations till the time of adding or removing keeping in mind the amount of work completed or needs to be completed, In this way we can work with complex problems also.