
2 women and 5 men can finish a piece of embroidery in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the embroidery and that taken by 1 man alone?
Answer
573k+ views
Hint: Start by assuming the number of days taken by men and women for the work as some variable, Then compute the work done by men , women in one day , this gives us their efficiency. Form the equations using them as per the statement given in the question and solve for the values of variables.
Complete step-by-step answer:
Let us consider , 1 woman can finish the embroidery work in ‘x’ days and 1 man can finish it in ‘y’ days.
So , 1 woman’s one day work $ = \dfrac{1}{x}$
Similarly , 1 man’s one day work $ = \dfrac{1}{y}$
According to the statement in the question,
One day work of 2 women and 5 men $ = \dfrac{2}{x} + \dfrac{5}{y} = \dfrac{1}{4}$
One day work of 3 women and 6 men $ = \dfrac{3}{x} + \dfrac{6}{y} = \dfrac{1}{3}$
Let $\dfrac{1}{x} = a$ and $\dfrac{1}{y} = b$
Now, $2a + 5b = \dfrac{1}{4} \to eqn.1$
$3a + 6b = \dfrac{1}{3} \to eqn.2$
Multiply eqn.1 by 3 and eqn.2 by 2, Then subtract them eqn.1 – eqn.2 , we get
$3b = \dfrac{1}{{12}} \Rightarrow b = \dfrac{1}{{36}}$
Putting $b = \dfrac{1}{{36}}$ in eqn.1 , we get
$22a + 5\left( {\dfrac{1}{{36}}} \right) = \dfrac{1}{4}$
Multiply by 36 both side
$72a + 5 = 9$
Taking 5 to right side
$
72a = 9 - 5 \\
\Rightarrow a = \dfrac{1}{{18}} \\
$
Now ,Substituting the values to get x and y . We get,
$a = \dfrac{1}{x} = \dfrac{1}{{18}},b = \dfrac{1}{y} = \dfrac{1}{{36}}$
So, One woman can finish the embroidery work in 18days and one man can finish the work in 36 days.
Note: Similar questions can be asked with a slight twist by adding or removing people midway of the project. In that case form equations till the time of adding or removing keeping in mind the amount of work completed or needs to be completed, In this way we can work with complex problems also.
Complete step-by-step answer:
Let us consider , 1 woman can finish the embroidery work in ‘x’ days and 1 man can finish it in ‘y’ days.
So , 1 woman’s one day work $ = \dfrac{1}{x}$
Similarly , 1 man’s one day work $ = \dfrac{1}{y}$
According to the statement in the question,
One day work of 2 women and 5 men $ = \dfrac{2}{x} + \dfrac{5}{y} = \dfrac{1}{4}$
One day work of 3 women and 6 men $ = \dfrac{3}{x} + \dfrac{6}{y} = \dfrac{1}{3}$
Let $\dfrac{1}{x} = a$ and $\dfrac{1}{y} = b$
Now, $2a + 5b = \dfrac{1}{4} \to eqn.1$
$3a + 6b = \dfrac{1}{3} \to eqn.2$
Multiply eqn.1 by 3 and eqn.2 by 2, Then subtract them eqn.1 – eqn.2 , we get
$3b = \dfrac{1}{{12}} \Rightarrow b = \dfrac{1}{{36}}$
Putting $b = \dfrac{1}{{36}}$ in eqn.1 , we get
$22a + 5\left( {\dfrac{1}{{36}}} \right) = \dfrac{1}{4}$
Multiply by 36 both side
$72a + 5 = 9$
Taking 5 to right side
$
72a = 9 - 5 \\
\Rightarrow a = \dfrac{1}{{18}} \\
$
Now ,Substituting the values to get x and y . We get,
$a = \dfrac{1}{x} = \dfrac{1}{{18}},b = \dfrac{1}{y} = \dfrac{1}{{36}}$
So, One woman can finish the embroidery work in 18days and one man can finish the work in 36 days.
Note: Similar questions can be asked with a slight twist by adding or removing people midway of the project. In that case form equations till the time of adding or removing keeping in mind the amount of work completed or needs to be completed, In this way we can work with complex problems also.
Recently Updated Pages
Two men on either side of the cliff 90m height observe class 10 maths CBSE

Cutting of the Chinese melon means A The business and class 10 social science CBSE

Show an aquatic food chain using the following organisms class 10 biology CBSE

How is gypsum formed class 10 chemistry CBSE

If the line 3x + 4y 24 0 intersects the xaxis at t-class-10-maths-CBSE

Sugar present in DNA is A Heptose B Hexone C Tetrose class 10 biology CBSE

Trending doubts
Why is there a time difference of about 5 hours between class 10 social science CBSE

What is the median of the first 10 natural numbers class 10 maths CBSE

Indias first jute mill was established in 1854 in A class 10 social science CBSE

Indias first jute mill was established in 1854 in A class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths

