$10$ men working $6$ hours a day, can complete a work in $18$ days. How many hours a day must $15$ men work, to complete the same work in $12$ days?
A) $4$
B) $5$
C) $6$
D) $7$
Answer
505.5k+ views
Hint: Always convert the time taken all together by the people working along with the count of the people and the number of hours taken and then frame the equation according to the work to be done by the desired number of people and the days of working. Place the values and simplify for the required resultant value.
Complete step by step solution:
Given that: $10$men working $6$hours a day, can complete a work in $18$days
Can be expressed as:
In $18$days, man work $ = 6 \times 10$hours $ = 60$hours
If work is done to complete in one day $ = 6 \times 10 \times 18$hours
To complete the same work in one day by $15$men $ = \dfrac{{6 \times 10 \times 18}}{{15}}$hours a day
Now, the same work done in $12$ days by $15$men $ = \dfrac{{6 \times 10 \times 18}}{{12 \times 15}}$hours a day
Simplify the above expression, removing common factors from the numerator and the denominator.
Work done in $12$ days by $15$men $ = 6$hours a day
Therefore, $15$ men working $6$ hours a day, can complete the work in $12$ days. So, option (C) is the correct answer.
Note:
Understand the data given in the question clearly, then frame the equations accordingly and simplify the expressions accordingly. Always convert the total time required to complete the work by the given number of men. Then convert the time taken by the desired number of men. Be good in division and multiples and remember that the common factor from the numerator and the denominator cancels each other.
Complete step by step solution:
Given that: $10$men working $6$hours a day, can complete a work in $18$days
Can be expressed as:
In $18$days, man work $ = 6 \times 10$hours $ = 60$hours
If work is done to complete in one day $ = 6 \times 10 \times 18$hours
To complete the same work in one day by $15$men $ = \dfrac{{6 \times 10 \times 18}}{{15}}$hours a day
Now, the same work done in $12$ days by $15$men $ = \dfrac{{6 \times 10 \times 18}}{{12 \times 15}}$hours a day
Simplify the above expression, removing common factors from the numerator and the denominator.
Work done in $12$ days by $15$men $ = 6$hours a day
Therefore, $15$ men working $6$ hours a day, can complete the work in $12$ days. So, option (C) is the correct answer.
Note:
Understand the data given in the question clearly, then frame the equations accordingly and simplify the expressions accordingly. Always convert the total time required to complete the work by the given number of men. Then convert the time taken by the desired number of men. Be good in division and multiples and remember that the common factor from the numerator and the denominator cancels each other.
Recently Updated Pages
Why is there a time difference of about 5 hours between class 10 social science CBSE

In cricket, what is a "pink ball" primarily used for?

In cricket, what is the "new ball" phase?

In cricket, what is a "death over"?

What is the "Powerplay" in T20 cricket?

In cricket, what is a "super over"?

Trending doubts
What is BLO What is the full form of BLO class 8 social science CBSE

Citizens of India can vote at the age of A 18 years class 8 social science CBSE

Full form of STD, ISD and PCO

Right to vote is a AFundamental Right BFundamental class 8 social science CBSE

Summary of the poem Where the Mind is Without Fear class 8 english CBSE

What is the difference between rai and mustard see class 8 biology CBSE