Given, A, B, and C can reap a field in $15\dfrac{3}{4}$ days, B, C, and D in 14 days, C, D, and A in 18 days, and D, A, and B in 21 days. In what time A, B, C, and D together reap it?
Answer
567.9k+ views
Hint: To solve this question we consider that the total amount of work is 100%. Then, we will find the percentage of work done by A, B, and C in one day, the percentage of work done by B, C, and D in one day, the percentage of work done by C, D, and A in one day, and the percentage of work done by D, A and B in one day. Then, with this information, we will find the percentage of work done in one day when A works alone and then find the number of days required to complete the work.
Complete step by step answer:
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete 100 % work. So, the percentage of work completed by A, B, and C in one day can found out as:
$ \Rightarrow A + B + C = \dfrac{{100\% }}{{\dfrac{{63}}{4}}}$
Cancel out the common factor,
$ \Rightarrow A + B + C = 6.35\% $ ….. (1)
B, C, and D required 14 days to complete 100 % work. So, the percentage of work completed by B, C, and D in one day can found out as:
$ \Rightarrow B + C + D = \dfrac{{100\% }}{{14}}$
Cancel out the common factor,
$ \Rightarrow B + C + D = 7.14\% $ ….. (2)
C, D, and A required 18 days to complete 100 % work. So, the percentage of work completed by C, D, and A in one day can found out as:
$ \Rightarrow C + D + A = \dfrac{{100\% }}{{18}}$
Cancel out the common factor,
$ \Rightarrow C + D + A = 5.55\% $ ….. (3)
D, A, and B required 21 days to complete 100 % work. So, the percentage of work completed by D, A, and B in one day can found out as:
$ \Rightarrow D + A + B = \dfrac{{100\% }}{{21}}$
Cancel out the common factor,
$ \Rightarrow D + A + B = 4.76\% $ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$ \Rightarrow 3A + 3B + 3C = 6.35\% + 7.14\% + 5.55\% + 4.76\% $
Add the terms on the right side,
$ \Rightarrow 3\left( {A + B + C + D} \right) = 23.8\% $
Divide both sides by 3,
$ \Rightarrow A + B + C + D = 7.93\% $
So, 7.93% of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{{100}}{{7.93}} = 12.6 = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Note:
This question can be solved in another way.
Step by step answer: -
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete the work. So, the work completed by A, B, and C in one day can found out as:
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{{\dfrac{{63}}{4}}}$
Multiply 4 in the numerator,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{4}{{63}}$ ….. (1)
B, C, and D required 14 days to complete the work. So, the work completed by B, C, and D in one day can found out as:
$ \Rightarrow \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{1}{{14}}$ ….. (2)
C, D, and A required 18 days to complete the work. So, the work completed by C, D, and A in one day can found out as:
$ \Rightarrow \dfrac{1}{C} + \dfrac{1}{D} + \dfrac{1}{A} = \dfrac{1}{{18}}$ ….. (3)
D, A, and B required 21 days to complete the work. So, the work completed by D, A, and B in one day can found out as:
$ \Rightarrow \dfrac{1}{D} + \dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{{21}}$ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$\dfrac{3}{A} + \dfrac{3}{B} + \dfrac{3}{C} + \dfrac{3}{D} = \dfrac{4}{{63}} + \dfrac{1}{{14}} + \dfrac{1}{{18}} + \dfrac{1}{{21}}$
Take LCM on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{8 + 9 + 7 + 6}}{{126}}$
Add the terms on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{30}}{{126}}$
Cancel out the common factors,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{5}{{21}}$
Divide both sides by 3,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{5}{{63}}$
So, $\dfrac{5}{{63}}$ of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{1}{{\dfrac{5}{{63}}}} = \dfrac{{63}}{5} = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Complete step by step answer:
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete 100 % work. So, the percentage of work completed by A, B, and C in one day can found out as:
$ \Rightarrow A + B + C = \dfrac{{100\% }}{{\dfrac{{63}}{4}}}$
Cancel out the common factor,
$ \Rightarrow A + B + C = 6.35\% $ ….. (1)
B, C, and D required 14 days to complete 100 % work. So, the percentage of work completed by B, C, and D in one day can found out as:
$ \Rightarrow B + C + D = \dfrac{{100\% }}{{14}}$
Cancel out the common factor,
$ \Rightarrow B + C + D = 7.14\% $ ….. (2)
C, D, and A required 18 days to complete 100 % work. So, the percentage of work completed by C, D, and A in one day can found out as:
$ \Rightarrow C + D + A = \dfrac{{100\% }}{{18}}$
Cancel out the common factor,
$ \Rightarrow C + D + A = 5.55\% $ ….. (3)
D, A, and B required 21 days to complete 100 % work. So, the percentage of work completed by D, A, and B in one day can found out as:
$ \Rightarrow D + A + B = \dfrac{{100\% }}{{21}}$
Cancel out the common factor,
$ \Rightarrow D + A + B = 4.76\% $ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$ \Rightarrow 3A + 3B + 3C = 6.35\% + 7.14\% + 5.55\% + 4.76\% $
Add the terms on the right side,
$ \Rightarrow 3\left( {A + B + C + D} \right) = 23.8\% $
Divide both sides by 3,
$ \Rightarrow A + B + C + D = 7.93\% $
So, 7.93% of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{{100}}{{7.93}} = 12.6 = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Note:
This question can be solved in another way.
Step by step answer: -
Given: - A, B, and C can reap a field in $15\dfrac{3}{4}$ days.
B, C, and D can reap a field in 14 days,
C, D, and A can reap a field in 18 days.
D, A, and B can reap a field in 21 days.
A, B, and C require $15\dfrac{3}{4}$ days to complete the work. So, the work completed by A, B, and C in one day can found out as:
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{{\dfrac{{63}}{4}}}$
Multiply 4 in the numerator,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{4}{{63}}$ ….. (1)
B, C, and D required 14 days to complete the work. So, the work completed by B, C, and D in one day can found out as:
$ \Rightarrow \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{1}{{14}}$ ….. (2)
C, D, and A required 18 days to complete the work. So, the work completed by C, D, and A in one day can found out as:
$ \Rightarrow \dfrac{1}{C} + \dfrac{1}{D} + \dfrac{1}{A} = \dfrac{1}{{18}}$ ….. (3)
D, A, and B required 21 days to complete the work. So, the work completed by D, A, and B in one day can found out as:
$ \Rightarrow \dfrac{1}{D} + \dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{{21}}$ ….. (4)
Now add equation (1), (2), (3), and (4) and find the value of A + B + C + D.
$\dfrac{3}{A} + \dfrac{3}{B} + \dfrac{3}{C} + \dfrac{3}{D} = \dfrac{4}{{63}} + \dfrac{1}{{14}} + \dfrac{1}{{18}} + \dfrac{1}{{21}}$
Take LCM on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{8 + 9 + 7 + 6}}{{126}}$
Add the terms on the right side,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{{30}}{{126}}$
Cancel out the common factors,
$ \Rightarrow 3\left( {\dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D}} \right) = \dfrac{5}{{21}}$
Divide both sides by 3,
$ \Rightarrow \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} + \dfrac{1}{D} = \dfrac{5}{{63}}$
So, $\dfrac{5}{{63}}$ of work is completed in one day if A, B, C, and D work together.
Therefore, the number of days to complete the work is,
$\therefore \dfrac{1}{{\dfrac{5}{{63}}}} = \dfrac{{63}}{5} = 12\dfrac{3}{5}$
Hence, the number of days to complete the work is $12\dfrac{3}{5}$ days.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

Who Won 36 Oscar Awards? Record Holder Revealed

What is the median of the first 10 natural numbers class 10 maths CBSE

Why is it 530 pm in india when it is 1200 afternoon class 10 social science CBSE

Select the word that is correctly spelled a Twelveth class 10 english CBSE

Why is there a time difference of about 5 hours between class 10 social science CBSE

