A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in
(a) 3 days
(b) 7 days
(c) 4 days
(d) 6 days
Answer
681.6k+ views
Hint: Find the units of work done by each of them per day then we can find number of units of total work. Do this by using per day fraction of work.
\[Per\text{ }day\text{ }fraction\text{ }=\text{ }\dfrac{1}{Time\text{ }taken}\]
Complete step-by-step answer:
They will work together for 2 days and finish the work.
Case 1: Let the time taken by A to finish a piece of work be a. Then the per day fraction of work done by A will be $\left( \dfrac{1}{a} \right)$
Case 2: Let the time taken by B to finish a piece of work be b. Then the per day fraction of work done by B will be $\left( \dfrac{1}{b} \right)$
Case 3: Let the time taken by C to finish a piece of work be c. Then the per day fraction of work done by C will be $\left( \dfrac{1}{c} \right)$
So,
Total per day fraction of work will be sum of all cases
Total per day fraction of work = (Case 1) + (Case 2) + (Case 3)
Total per day fraction of work = $\dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c}$
We know:
(Total time).(Total per day fraction of work) = 1
Here 1 implies that work is completed.
So, by substituting 2 days into equation, we get:
$2\left( \dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c} \right)=1.........(i)$
Given:
A take twice as much time as B.
A take thrice as much time as C.
By using above conditions, we get:
a = 2b and a = 3c
By substituting these into equation(i), we get
$2\left( \dfrac{1}{a}+\dfrac{1}{\dfrac{a}{2}}+\dfrac{1}{\dfrac{a}{3}} \right)=1$
By solving this, we get:
$2\left( \dfrac{1}{a}+\dfrac{2}{a}+\dfrac{3}{a} \right)=1$
By taking least common multiple and then adding the fractions, we get:
$2\left( \dfrac{6}{a} \right)=1$
By multiplying both sides with a, we get:
$\dfrac{12}{a}.a=a$
a = 12
By using given conditions, we found relation between a and b:
a = 2b
By substituting value of a, we get:
12 = 2b
By dividing 2 on both sides, we get:
$b=\dfrac{12}{2}=6$
Therefore, it takes 6 days for B to complete the work alone.
Option (d) is correct.
Note: Do not confuse time taken and per day fraction of work. The simple relation is stated in the hint.
\[Per\text{ }day\text{ }fraction\text{ }=\text{ }\dfrac{1}{Time\text{ }taken}\]
Complete step-by-step answer:
They will work together for 2 days and finish the work.
Case 1: Let the time taken by A to finish a piece of work be a. Then the per day fraction of work done by A will be $\left( \dfrac{1}{a} \right)$
Case 2: Let the time taken by B to finish a piece of work be b. Then the per day fraction of work done by B will be $\left( \dfrac{1}{b} \right)$
Case 3: Let the time taken by C to finish a piece of work be c. Then the per day fraction of work done by C will be $\left( \dfrac{1}{c} \right)$
So,
Total per day fraction of work will be sum of all cases
Total per day fraction of work = (Case 1) + (Case 2) + (Case 3)
Total per day fraction of work = $\dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c}$
We know:
(Total time).(Total per day fraction of work) = 1
Here 1 implies that work is completed.
So, by substituting 2 days into equation, we get:
$2\left( \dfrac{1}{a}+\dfrac{1}{b}+\dfrac{1}{c} \right)=1.........(i)$
Given:
A take twice as much time as B.
A take thrice as much time as C.
By using above conditions, we get:
a = 2b and a = 3c
By substituting these into equation(i), we get
$2\left( \dfrac{1}{a}+\dfrac{1}{\dfrac{a}{2}}+\dfrac{1}{\dfrac{a}{3}} \right)=1$
By solving this, we get:
$2\left( \dfrac{1}{a}+\dfrac{2}{a}+\dfrac{3}{a} \right)=1$
By taking least common multiple and then adding the fractions, we get:
$2\left( \dfrac{6}{a} \right)=1$
By multiplying both sides with a, we get:
$\dfrac{12}{a}.a=a$
a = 12
By using given conditions, we found relation between a and b:
a = 2b
By substituting value of a, we get:
12 = 2b
By dividing 2 on both sides, we get:
$b=\dfrac{12}{2}=6$
Therefore, it takes 6 days for B to complete the work alone.
Option (d) is correct.
Note: Do not confuse time taken and per day fraction of work. The simple relation is stated in the hint.
Recently Updated Pages
What is BLO What is the full form of BLO class 8 social science CBSE

Explain the Treaty of Vienna of 1815 class 10 social science CBSE

10 examples of friction in our daily life

Draw a diagram of nephron and explain its structur class 11 biology CBSE

Write structures of the following compounds i 2 Chloro3methylpentane class 11 chemistry CBSE

A Paragraph on Pollution in about 100-150 Words

Trending doubts
List of coprime numbers from 1 to 100 class 7 maths CBSE

The plural of Chief is Chieves A True B False class 7 english CBSE

The founder of Jainism was A Rishabhadev B Neminath class 7 social science CBSE

Collective noun a of sailors class 7 english CBSE

Differentiate between weather and climate How do they class 7 social science CBSE

Write a short note on the great bath of MohenjoDar class 7 social science CBSE


