
A is thrice as efficient as B and B is twice as efficient as C. If A, B and C work together how long will they take to complete a job which B completes in 10 days?
${\text{A}}{\text{. }}\dfrac{{20}}{9}$ days
${\text{B}}{\text{. }}\dfrac{{11}}{9}$ days
${\text{C}}{\text{. }}3$ days
${\text{D}}{\text{. }}$None of these
Answer
618k+ views
Hint: Here, we will proceed by finding out the number of days taken by A, B and C separately to complete the work or job and then we will use the unitary method to find out the amount of the work done by A, B and C separately in 1 day.
Complete step-by-step answer:
Given, B finishes the total work in 10 days.
i.e., Number of days taken by B to finish the work = 10 days
Given that A is thrice as efficient as B.
So, Number of days taken by A to finish the work = $\dfrac{{{\text{Number of days taken by B to finish the work}}}}{3} = \dfrac{{10}}{3}$ days
Amount of the work done by B in 1 day = $\dfrac{1}{{10}}$
Amount of the work done by A in 1 day = $\dfrac{1}{{\left( {\dfrac{{10}}{3}} \right)}} = \dfrac{3}{{10}}$
Also, given that B is twice efficient as C.
So, Number of days taken by B to finish the work = $\dfrac{{{\text{Number of days taken by C to finish the work}}}}{2}$
$ \Rightarrow $Number of days taken by C to finish the work = 2(Number of days taken by B to finish the work)
$ \Rightarrow $Number of days taken by C to finish the work = 2(10) = 20 days
Amount of the work done by C in 1 day = $\dfrac{1}{{20}}$
As we know that,
Amount of work done in 1 day when A, B and C work together = (Amount of the work done by A in 1 day) + (Amount of the work done by B in 1 day) + (Amount of the work done by C in 1 day)
$ \Rightarrow $Amount of work done in 1 day when A, B and C work together $ = \dfrac{3}{{10}} + \dfrac{1}{{10}} + \dfrac{1}{{20}} = \dfrac{{\left( {3 \times 2} \right) + \left( {1 \times 2} \right) + 1}}{{20}} = \dfrac{{6 + 2 + 1}}{{20}} = \dfrac{9}{{20}}$
Number of days taken to finish the work when A, B and C work together = $\dfrac{1}{{\dfrac{9}{{20}}}} = \dfrac{{20}}{9}$ days
Hence, option A is correct.
Note: In this particular problem, A is thrice as efficient as B means that the number of days taken by B is three times the number of days taken by A to finish the work. Here, we have used a unitary method in order to convert the number of days taken into the piece of work or the amount of work done in 1 day.
Complete step-by-step answer:
Given, B finishes the total work in 10 days.
i.e., Number of days taken by B to finish the work = 10 days
Given that A is thrice as efficient as B.
So, Number of days taken by A to finish the work = $\dfrac{{{\text{Number of days taken by B to finish the work}}}}{3} = \dfrac{{10}}{3}$ days
Amount of the work done by B in 1 day = $\dfrac{1}{{10}}$
Amount of the work done by A in 1 day = $\dfrac{1}{{\left( {\dfrac{{10}}{3}} \right)}} = \dfrac{3}{{10}}$
Also, given that B is twice efficient as C.
So, Number of days taken by B to finish the work = $\dfrac{{{\text{Number of days taken by C to finish the work}}}}{2}$
$ \Rightarrow $Number of days taken by C to finish the work = 2(Number of days taken by B to finish the work)
$ \Rightarrow $Number of days taken by C to finish the work = 2(10) = 20 days
Amount of the work done by C in 1 day = $\dfrac{1}{{20}}$
As we know that,
Amount of work done in 1 day when A, B and C work together = (Amount of the work done by A in 1 day) + (Amount of the work done by B in 1 day) + (Amount of the work done by C in 1 day)
$ \Rightarrow $Amount of work done in 1 day when A, B and C work together $ = \dfrac{3}{{10}} + \dfrac{1}{{10}} + \dfrac{1}{{20}} = \dfrac{{\left( {3 \times 2} \right) + \left( {1 \times 2} \right) + 1}}{{20}} = \dfrac{{6 + 2 + 1}}{{20}} = \dfrac{9}{{20}}$
Number of days taken to finish the work when A, B and C work together = $\dfrac{1}{{\dfrac{9}{{20}}}} = \dfrac{{20}}{9}$ days
Hence, option A is correct.
Note: In this particular problem, A is thrice as efficient as B means that the number of days taken by B is three times the number of days taken by A to finish the work. Here, we have used a unitary method in order to convert the number of days taken into the piece of work or the amount of work done in 1 day.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
What is the median of the first 10 natural numbers class 10 maths CBSE

Which women's tennis player has 24 Grand Slam singles titles?

Who is the Brand Ambassador of Incredible India?

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

A moving boat is observed from the top of a 150 m high class 10 maths CBSE

