Answer
Verified
371.7k+ views
Hint:
Here, we will find the number of days that the work lasts. First, we will find the work done by A, B and C in one day. Since all work together for 2 days, we will find the total work done by all the three in 2 days. Since B leaves three days before the work gets finished, so we will find work done by C in 3 days. Then we will subtract the work done by these from the total work to get the work done by B and C will be found. Then we will find the number of days worked by B and C. Then we will get the number of days that the work has lasted.
Complete step by step solution:
We are given that A can do the work in \[10\] days, B can do the work in \[12\] days and C can do the work in \[15\] days.
Now, we will find the work done by A, B, C in one day,
A’s one day work \[ = \dfrac{1}{{10}}\]
B’s one day work \[ = \dfrac{1}{{12}}\]
C’s one day work \[ = \dfrac{1}{{15}}\]
Now, we will total work done by A, B, C all together in one day
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}\]
The L.C.M of the denominators \[5 \times 2 \times 2 \times 3 = 60\]
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{1}{{10}} \times \dfrac{6}{6} + \dfrac{1}{{12}} \times \dfrac{5}{5} + \dfrac{1}{{15}} \times \dfrac{4}{4}\]
Adding the numerators of like terms, we have
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{{6 + 4 + 5}}{{60}}\]
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{{15}}{{60}}\]
By simplification, we have
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{1}{4}\]
Now ,we will find the work done by all the three in \[{\rm{2 days}}\]
\[\left( {A + B + C} \right)\]’s two days’ work \[ = \dfrac{1}{4} \times 2 = \dfrac{1}{2}\]
\[ \Rightarrow \left( {A + B + C} \right)\]’s two days’ work \[ = \dfrac{1}{2}\]
But B leaves \[{\rm{3 days}}\]before the work gets finished, so C does the remaining work alone
C’s 3 days’ work \[ = \dfrac{1}{{15}} \times 3 = \dfrac{1}{5}\]
Now, we will find the work done in the first \[{\rm{2 days}}\]by all the three and the last \[{\rm{3 days}}\]by C alone
Work done in 5 days\[ = \dfrac{1}{2} + \dfrac{1}{5}\]
\[ \Rightarrow \] Work done in 5 days \[ = \dfrac{1}{2} \times \dfrac{5}{5} + \dfrac{1}{5} \times \dfrac{2}{2}\]
\[ \Rightarrow \] Work done in 5 days \[ = \dfrac{7}{{10}}\]
Since the total work done is \[1\], we will find the work done by B and C by subtracting the work done in \[{\rm{5 days}}\] from the total work done.
Work done by B and C together \[ = 1 - \dfrac{7}{{10}}\]
By cross multiplying, we have
\[ \Rightarrow \] Work done by B and C together \[ = \dfrac{{10 - 7}}{{10}}\]
Work done by B and C together \[ = \dfrac{3}{{10}}\]
Now, we will find the work done by B and C in one day
One-day work of both B and C\[ = \dfrac{1}{{12}} + \dfrac{1}{{15}}\]
Taking LCM of terms, we get
\[ \Rightarrow \]One-day work of both B and C \[ = \dfrac{1}{{12}} \times \dfrac{5}{5} + \dfrac{1}{{15}} \times \dfrac{4}{4} = \dfrac{{5 + 4}}{{60}}\]
Simplifying the terms, we get
\[ \Rightarrow \]One-day work of both B and C \[ = \dfrac{9}{{60}}\]
\[ \Rightarrow \]One-day work of both B and C \[ = \dfrac{3}{{20}}\]
Now, to find the number of days worked by B and C, we will divide the total work done by B and C by the work done by B and C in one day
\[ \Rightarrow \]Number of days worked by both B and C together\[ = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2\] days
Now we will find the number of days by adding the days worked by all the three days worked by B and C, days worked by C alone.
\[ \Rightarrow \] Total work done by A, B and C \[ = 2 + 3 + 2 = 7\] days
Therefore, the work has lasted for\[{\text{7 days}}\].
Note:
Time and work problems deal with the simultaneous performance involving the efficiency of an individual or a group and the time taken by them to complete a piece of work. Work is the effort applied to produce a deliverable or accomplish a task. A certain amount of time (T) is taken to complete a certain work (W). The number of units of work done per unit time is called the rate of work (R). Hence, Work (W) \[ = \] Rate (R) Time (T)
Here, we will find the number of days that the work lasts. First, we will find the work done by A, B and C in one day. Since all work together for 2 days, we will find the total work done by all the three in 2 days. Since B leaves three days before the work gets finished, so we will find work done by C in 3 days. Then we will subtract the work done by these from the total work to get the work done by B and C will be found. Then we will find the number of days worked by B and C. Then we will get the number of days that the work has lasted.
Complete step by step solution:
We are given that A can do the work in \[10\] days, B can do the work in \[12\] days and C can do the work in \[15\] days.
Now, we will find the work done by A, B, C in one day,
A’s one day work \[ = \dfrac{1}{{10}}\]
B’s one day work \[ = \dfrac{1}{{12}}\]
C’s one day work \[ = \dfrac{1}{{15}}\]
Now, we will total work done by A, B, C all together in one day
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{1}{{10}} + \dfrac{1}{{12}} + \dfrac{1}{{15}}\]
The L.C.M of the denominators \[5 \times 2 \times 2 \times 3 = 60\]
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{1}{{10}} \times \dfrac{6}{6} + \dfrac{1}{{12}} \times \dfrac{5}{5} + \dfrac{1}{{15}} \times \dfrac{4}{4}\]
Adding the numerators of like terms, we have
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{{6 + 4 + 5}}{{60}}\]
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{{15}}{{60}}\]
By simplification, we have
\[ \Rightarrow \left( {A + B + C} \right)\]’s one day work \[ = \dfrac{1}{4}\]
Now ,we will find the work done by all the three in \[{\rm{2 days}}\]
\[\left( {A + B + C} \right)\]’s two days’ work \[ = \dfrac{1}{4} \times 2 = \dfrac{1}{2}\]
\[ \Rightarrow \left( {A + B + C} \right)\]’s two days’ work \[ = \dfrac{1}{2}\]
But B leaves \[{\rm{3 days}}\]before the work gets finished, so C does the remaining work alone
C’s 3 days’ work \[ = \dfrac{1}{{15}} \times 3 = \dfrac{1}{5}\]
Now, we will find the work done in the first \[{\rm{2 days}}\]by all the three and the last \[{\rm{3 days}}\]by C alone
Work done in 5 days\[ = \dfrac{1}{2} + \dfrac{1}{5}\]
\[ \Rightarrow \] Work done in 5 days \[ = \dfrac{1}{2} \times \dfrac{5}{5} + \dfrac{1}{5} \times \dfrac{2}{2}\]
\[ \Rightarrow \] Work done in 5 days \[ = \dfrac{7}{{10}}\]
Since the total work done is \[1\], we will find the work done by B and C by subtracting the work done in \[{\rm{5 days}}\] from the total work done.
Work done by B and C together \[ = 1 - \dfrac{7}{{10}}\]
By cross multiplying, we have
\[ \Rightarrow \] Work done by B and C together \[ = \dfrac{{10 - 7}}{{10}}\]
Work done by B and C together \[ = \dfrac{3}{{10}}\]
Now, we will find the work done by B and C in one day
One-day work of both B and C\[ = \dfrac{1}{{12}} + \dfrac{1}{{15}}\]
Taking LCM of terms, we get
\[ \Rightarrow \]One-day work of both B and C \[ = \dfrac{1}{{12}} \times \dfrac{5}{5} + \dfrac{1}{{15}} \times \dfrac{4}{4} = \dfrac{{5 + 4}}{{60}}\]
Simplifying the terms, we get
\[ \Rightarrow \]One-day work of both B and C \[ = \dfrac{9}{{60}}\]
\[ \Rightarrow \]One-day work of both B and C \[ = \dfrac{3}{{20}}\]
Now, to find the number of days worked by B and C, we will divide the total work done by B and C by the work done by B and C in one day
\[ \Rightarrow \]Number of days worked by both B and C together\[ = \dfrac{3}{{10}} \times \dfrac{{20}}{3} = 2\] days
Now we will find the number of days by adding the days worked by all the three days worked by B and C, days worked by C alone.
\[ \Rightarrow \] Total work done by A, B and C \[ = 2 + 3 + 2 = 7\] days
Therefore, the work has lasted for\[{\text{7 days}}\].
Note:
Time and work problems deal with the simultaneous performance involving the efficiency of an individual or a group and the time taken by them to complete a piece of work. Work is the effort applied to produce a deliverable or accomplish a task. A certain amount of time (T) is taken to complete a certain work (W). The number of units of work done per unit time is called the rate of work (R). Hence, Work (W) \[ = \] Rate (R) Time (T)
Recently Updated Pages
Three beakers labelled as A B and C each containing 25 mL of water were taken A small amount of NaOH anhydrous CuSO4 and NaCl were added to the beakers A B and C respectively It was observed that there was an increase in the temperature of the solutions contained in beakers A and B whereas in case of beaker C the temperature of the solution falls Which one of the following statements isarecorrect i In beakers A and B exothermic process has occurred ii In beakers A and B endothermic process has occurred iii In beaker C exothermic process has occurred iv In beaker C endothermic process has occurred
The branch of science which deals with nature and natural class 10 physics CBSE
The Equation xxx + 2 is Satisfied when x is Equal to Class 10 Maths
Define absolute refractive index of a medium
Find out what do the algal bloom and redtides sign class 10 biology CBSE
Prove that the function fleft x right xn is continuous class 12 maths CBSE
Trending doubts
State the differences between manure and fertilize class 8 biology CBSE
Why are xylem and phloem called complex tissues aBoth class 11 biology CBSE
Difference between Prokaryotic cell and Eukaryotic class 11 biology CBSE
Difference Between Plant Cell and Animal Cell
What would happen if plasma membrane ruptures or breaks class 11 biology CBSE
Give 10 examples for herbs , shrubs , climbers , creepers
What precautions do you take while observing the nucleus class 11 biology CBSE
What would happen to the life of a cell if there was class 11 biology CBSE
Change the following sentences into negative and interrogative class 10 english CBSE