
A and B can do work in 8 days. B and C can do the same work in 12 days. A, B, and C can together finish it in 6 days. A and C together will do it in:
(a) 4 days
(b) 6 days
(c) 8 days
(d) 12 days
Answer
615.6k+ views
Hint: Calculate the one day work of A and B together, B and C together and A, B, and C together by using the fact that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$. Simplify the equations by rearranging them to calculate the one day work of A and C, and thus, the number of days taken by A and C to complete the work.
Complete step-by-step answer:
We have data regarding the number of days taken by A and B, B and C and A, B, and C to finish the work. We have to calculate the number of days taken by A and C to finish the work.
We know that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$.
We know that A and B can complete the work in 8 days.
Thus, one day work of A and B is $A+B=\dfrac{1}{8}.....\left( 1 \right)$.
We know that B and C can complete the work in 12 days.
Thus, one day work of B and C is $B+C=\dfrac{1}{12}.....\left( 2 \right)$.
We know that A, B, and C can complete the work in C days.
Thus, one day work of A, B, and C is $A+B+C=\dfrac{1}{6}.....\left( 3 \right)$.
Adding equation (1) and (2), we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}$.
Simplifying the above equation by taking LCM, we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}=\dfrac{3+2}{24}=\dfrac{5}{24}.....\left( 4 \right)$.
Subtracting equation (3) from equation (4), we have $\left( A+2B+C \right)-\left( A+B+C \right)=\dfrac{5}{24}-\dfrac{1}{6}$.
Simplifying the above equation by taking LCM, we have $B=\dfrac{5-4}{24}=\dfrac{1}{24}.....\left( 5 \right)$.
Substituting equation (5) in equation (3), we have $A+\dfrac{1}{24}+C=\dfrac{1}{6}$.
Rearranging the terms of the above equation, we have $A+C=\dfrac{1}{6}-\dfrac{1}{24}=\dfrac{4-1}{24}=\dfrac{3}{24}=\dfrac{1}{8}$.
Thus, one day work of A and C is $\dfrac{1}{8}$.
Hence, A and C take 8 days to complete the work, which is option (c).
Note: One must observe that this is not a question based on the unitary method. As the number of workers increases, the days taken to complete the given work decreases. This is because the number of days and amount of work are inversely proportional to each other. If we use a unitary method to solve this question, we will get an incorrect answer.
Complete step-by-step answer:
We have data regarding the number of days taken by A and B, B and C and A, B, and C to finish the work. We have to calculate the number of days taken by A and C to finish the work.
We know that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$.
We know that A and B can complete the work in 8 days.
Thus, one day work of A and B is $A+B=\dfrac{1}{8}.....\left( 1 \right)$.
We know that B and C can complete the work in 12 days.
Thus, one day work of B and C is $B+C=\dfrac{1}{12}.....\left( 2 \right)$.
We know that A, B, and C can complete the work in C days.
Thus, one day work of A, B, and C is $A+B+C=\dfrac{1}{6}.....\left( 3 \right)$.
Adding equation (1) and (2), we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}$.
Simplifying the above equation by taking LCM, we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}=\dfrac{3+2}{24}=\dfrac{5}{24}.....\left( 4 \right)$.
Subtracting equation (3) from equation (4), we have $\left( A+2B+C \right)-\left( A+B+C \right)=\dfrac{5}{24}-\dfrac{1}{6}$.
Simplifying the above equation by taking LCM, we have $B=\dfrac{5-4}{24}=\dfrac{1}{24}.....\left( 5 \right)$.
Substituting equation (5) in equation (3), we have $A+\dfrac{1}{24}+C=\dfrac{1}{6}$.
Rearranging the terms of the above equation, we have $A+C=\dfrac{1}{6}-\dfrac{1}{24}=\dfrac{4-1}{24}=\dfrac{3}{24}=\dfrac{1}{8}$.
Thus, one day work of A and C is $\dfrac{1}{8}$.
Hence, A and C take 8 days to complete the work, which is option (c).
Note: One must observe that this is not a question based on the unitary method. As the number of workers increases, the days taken to complete the given work decreases. This is because the number of days and amount of work are inversely proportional to each other. If we use a unitary method to solve this question, we will get an incorrect answer.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 Science: Engaging Questions & Answers for Success

Trending doubts
What is the median of the first 10 natural numbers class 10 maths CBSE

Which women's tennis player has 24 Grand Slam singles titles?

Who is the Brand Ambassador of Incredible India?

Why is there a time difference of about 5 hours between class 10 social science CBSE

Write a letter to the principal requesting him to grant class 10 english CBSE

State and prove converse of BPT Basic Proportionality class 10 maths CBSE

