A and B can do work in 8 days. B and C can do the same work in 12 days. A, B, and C can together finish it in 6 days. A and C together will do it in:
(a) 4 days
(b) 6 days
(c) 8 days
(d) 12 days
Answer
678.9k+ views
Hint: Calculate the one day work of A and B together, B and C together and A, B, and C together by using the fact that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$. Simplify the equations by rearranging them to calculate the one day work of A and C, and thus, the number of days taken by A and C to complete the work.
Complete step-by-step answer:
We have data regarding the number of days taken by A and B, B and C and A, B, and C to finish the work. We have to calculate the number of days taken by A and C to finish the work.
We know that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$.
We know that A and B can complete the work in 8 days.
Thus, one day work of A and B is $A+B=\dfrac{1}{8}.....\left( 1 \right)$.
We know that B and C can complete the work in 12 days.
Thus, one day work of B and C is $B+C=\dfrac{1}{12}.....\left( 2 \right)$.
We know that A, B, and C can complete the work in C days.
Thus, one day work of A, B, and C is $A+B+C=\dfrac{1}{6}.....\left( 3 \right)$.
Adding equation (1) and (2), we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}$.
Simplifying the above equation by taking LCM, we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}=\dfrac{3+2}{24}=\dfrac{5}{24}.....\left( 4 \right)$.
Subtracting equation (3) from equation (4), we have $\left( A+2B+C \right)-\left( A+B+C \right)=\dfrac{5}{24}-\dfrac{1}{6}$.
Simplifying the above equation by taking LCM, we have $B=\dfrac{5-4}{24}=\dfrac{1}{24}.....\left( 5 \right)$.
Substituting equation (5) in equation (3), we have $A+\dfrac{1}{24}+C=\dfrac{1}{6}$.
Rearranging the terms of the above equation, we have $A+C=\dfrac{1}{6}-\dfrac{1}{24}=\dfrac{4-1}{24}=\dfrac{3}{24}=\dfrac{1}{8}$.
Thus, one day work of A and C is $\dfrac{1}{8}$.
Hence, A and C take 8 days to complete the work, which is option (c).
Note: One must observe that this is not a question based on the unitary method. As the number of workers increases, the days taken to complete the given work decreases. This is because the number of days and amount of work are inversely proportional to each other. If we use a unitary method to solve this question, we will get an incorrect answer.
Complete step-by-step answer:
We have data regarding the number of days taken by A and B, B and C and A, B, and C to finish the work. We have to calculate the number of days taken by A and C to finish the work.
We know that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$.
We know that A and B can complete the work in 8 days.
Thus, one day work of A and B is $A+B=\dfrac{1}{8}.....\left( 1 \right)$.
We know that B and C can complete the work in 12 days.
Thus, one day work of B and C is $B+C=\dfrac{1}{12}.....\left( 2 \right)$.
We know that A, B, and C can complete the work in C days.
Thus, one day work of A, B, and C is $A+B+C=\dfrac{1}{6}.....\left( 3 \right)$.
Adding equation (1) and (2), we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}$.
Simplifying the above equation by taking LCM, we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}=\dfrac{3+2}{24}=\dfrac{5}{24}.....\left( 4 \right)$.
Subtracting equation (3) from equation (4), we have $\left( A+2B+C \right)-\left( A+B+C \right)=\dfrac{5}{24}-\dfrac{1}{6}$.
Simplifying the above equation by taking LCM, we have $B=\dfrac{5-4}{24}=\dfrac{1}{24}.....\left( 5 \right)$.
Substituting equation (5) in equation (3), we have $A+\dfrac{1}{24}+C=\dfrac{1}{6}$.
Rearranging the terms of the above equation, we have $A+C=\dfrac{1}{6}-\dfrac{1}{24}=\dfrac{4-1}{24}=\dfrac{3}{24}=\dfrac{1}{8}$.
Thus, one day work of A and C is $\dfrac{1}{8}$.
Hence, A and C take 8 days to complete the work, which is option (c).
Note: One must observe that this is not a question based on the unitary method. As the number of workers increases, the days taken to complete the given work decreases. This is because the number of days and amount of work are inversely proportional to each other. If we use a unitary method to solve this question, we will get an incorrect answer.
Recently Updated Pages
Master Class 10 Computer Science: Engaging Questions & Answers for Success

Differentiate between voluntary action and reflex class 10 biology CBSE

The uses of bleaching powder are A It is used bleaching class 10 chemistry CBSE

Fill in the blanks with abstract nouns of the words class 10 english CBSE

How many threedigit numbers are there class 10 maths CBSE

What is a reflex arc class 10 biology CBSE

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

The highest dam in India is A Bhakra dam B Tehri dam class 10 social science CBSE

10 examples of evaporation in daily life with explanations

What is the full form of POSCO class 10 social science CBSE

Make a sketch of the human nerve cell What function class 10 biology CBSE

What is FYM class 10 biology CBSE

