A and B can do work in 8 days. B and C can do the same work in 12 days. A, B, and C can together finish it in 6 days. A and C together will do it in:
(a) 4 days
(b) 6 days
(c) 8 days
(d) 12 days
Answer
683.1k+ views
Hint: Calculate the one day work of A and B together, B and C together and A, B, and C together by using the fact that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$. Simplify the equations by rearranging them to calculate the one day work of A and C, and thus, the number of days taken by A and C to complete the work.
Complete step-by-step answer:
We have data regarding the number of days taken by A and B, B and C and A, B, and C to finish the work. We have to calculate the number of days taken by A and C to finish the work.
We know that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$.
We know that A and B can complete the work in 8 days.
Thus, one day work of A and B is $A+B=\dfrac{1}{8}.....\left( 1 \right)$.
We know that B and C can complete the work in 12 days.
Thus, one day work of B and C is $B+C=\dfrac{1}{12}.....\left( 2 \right)$.
We know that A, B, and C can complete the work in C days.
Thus, one day work of A, B, and C is $A+B+C=\dfrac{1}{6}.....\left( 3 \right)$.
Adding equation (1) and (2), we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}$.
Simplifying the above equation by taking LCM, we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}=\dfrac{3+2}{24}=\dfrac{5}{24}.....\left( 4 \right)$.
Subtracting equation (3) from equation (4), we have $\left( A+2B+C \right)-\left( A+B+C \right)=\dfrac{5}{24}-\dfrac{1}{6}$.
Simplifying the above equation by taking LCM, we have $B=\dfrac{5-4}{24}=\dfrac{1}{24}.....\left( 5 \right)$.
Substituting equation (5) in equation (3), we have $A+\dfrac{1}{24}+C=\dfrac{1}{6}$.
Rearranging the terms of the above equation, we have $A+C=\dfrac{1}{6}-\dfrac{1}{24}=\dfrac{4-1}{24}=\dfrac{3}{24}=\dfrac{1}{8}$.
Thus, one day work of A and C is $\dfrac{1}{8}$.
Hence, A and C take 8 days to complete the work, which is option (c).
Note: One must observe that this is not a question based on the unitary method. As the number of workers increases, the days taken to complete the given work decreases. This is because the number of days and amount of work are inversely proportional to each other. If we use a unitary method to solve this question, we will get an incorrect answer.
Complete step-by-step answer:
We have data regarding the number of days taken by A and B, B and C and A, B, and C to finish the work. We have to calculate the number of days taken by A and C to finish the work.
We know that if someone finishes the work in ‘x’ days, then the one day work of that person is $\dfrac{1}{x}$.
We know that A and B can complete the work in 8 days.
Thus, one day work of A and B is $A+B=\dfrac{1}{8}.....\left( 1 \right)$.
We know that B and C can complete the work in 12 days.
Thus, one day work of B and C is $B+C=\dfrac{1}{12}.....\left( 2 \right)$.
We know that A, B, and C can complete the work in C days.
Thus, one day work of A, B, and C is $A+B+C=\dfrac{1}{6}.....\left( 3 \right)$.
Adding equation (1) and (2), we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}$.
Simplifying the above equation by taking LCM, we have $A+2B+C=\dfrac{1}{8}+\dfrac{1}{12}=\dfrac{3+2}{24}=\dfrac{5}{24}.....\left( 4 \right)$.
Subtracting equation (3) from equation (4), we have $\left( A+2B+C \right)-\left( A+B+C \right)=\dfrac{5}{24}-\dfrac{1}{6}$.
Simplifying the above equation by taking LCM, we have $B=\dfrac{5-4}{24}=\dfrac{1}{24}.....\left( 5 \right)$.
Substituting equation (5) in equation (3), we have $A+\dfrac{1}{24}+C=\dfrac{1}{6}$.
Rearranging the terms of the above equation, we have $A+C=\dfrac{1}{6}-\dfrac{1}{24}=\dfrac{4-1}{24}=\dfrac{3}{24}=\dfrac{1}{8}$.
Thus, one day work of A and C is $\dfrac{1}{8}$.
Hence, A and C take 8 days to complete the work, which is option (c).
Note: One must observe that this is not a question based on the unitary method. As the number of workers increases, the days taken to complete the given work decreases. This is because the number of days and amount of work are inversely proportional to each other. If we use a unitary method to solve this question, we will get an incorrect answer.
Recently Updated Pages
Write any three differences between metals and nonmetals class 10 social science CBSE

Amit standing on a horizontal plane finds a bird flying class 10 maths CBSE

Two circles of radii 5 cm and 3 cm intersect at two class 10 maths CBSE

Solve the following i John and Jivanti together have class 10 maths CBSE

What is the relation between orthocenter circumcentre class 10 maths CBSE

Two plane mirrors are inclined at 70circ A ray incident class 10 physics CBSE

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

1 GB equals how many MB?

10 examples of evaporation in daily life with explanations

What is the full form of POSCO class 10 social science CBSE

Which is the hottest planet in the Solar system A Earth class 10 social science CBSE

Name any four life processes in living things class 10 biology CBSE

