150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
Answer
634.8k+ views
Hint: Here the drop in the number of workers remains constant everyday, so the concept of arithmetic progression is used to find the number of days in which the work can be completed.
Complete step-by-step answer:
Let the work finish in n days when the workers stopped dropping so that the total number of workers who worked all these days is the sum of A.P.
$ \Rightarrow 150 + 146 + 142 + .......n$
We know the formula of finding the sum of first n terms
$
\Rightarrow \dfrac{n}{2}[2a + (n - 1) \times d] \\
\Rightarrow \dfrac{n}{2}[2(150) + (n - 1)( - 4)] \\
\Rightarrow n(152 - 2n) \to (1) \\
$
If the workers had not dropped, then the work would have finished in ‘n-8’ days with 150 workers on each day i.e.., $150(n - 8) \to (2)$
Now
$
n(152 - 2n) = 150(n - 8) \\
\Rightarrow {n^2} - n - 600 = 0 \\
\Rightarrow {n^2} - 25n + 24n - 600 = 0 \\
\Rightarrow n(n - 25) + 24(n - 25) = 0 \\
\Rightarrow (n - 25)(n + 24) = 0 \\
$
Number of days cannot be negative so we won’t consider n=-24.
$
\Rightarrow (n - 25) = 0 \\
\Rightarrow n = 25 \\
$
Answer is 25 days.
The work will be complete in 25 days.
Note: If the specific number of workers dropped continuously then there would be a series. Find the series and apply the sum of first n terms in A.P. series after that follow some simple logic to get the number of days in which the work will be completed.
Complete step-by-step answer:
Let the work finish in n days when the workers stopped dropping so that the total number of workers who worked all these days is the sum of A.P.
$ \Rightarrow 150 + 146 + 142 + .......n$
We know the formula of finding the sum of first n terms
$
\Rightarrow \dfrac{n}{2}[2a + (n - 1) \times d] \\
\Rightarrow \dfrac{n}{2}[2(150) + (n - 1)( - 4)] \\
\Rightarrow n(152 - 2n) \to (1) \\
$
If the workers had not dropped, then the work would have finished in ‘n-8’ days with 150 workers on each day i.e.., $150(n - 8) \to (2)$
Now
$
n(152 - 2n) = 150(n - 8) \\
\Rightarrow {n^2} - n - 600 = 0 \\
\Rightarrow {n^2} - 25n + 24n - 600 = 0 \\
\Rightarrow n(n - 25) + 24(n - 25) = 0 \\
\Rightarrow (n - 25)(n + 24) = 0 \\
$
Number of days cannot be negative so we won’t consider n=-24.
$
\Rightarrow (n - 25) = 0 \\
\Rightarrow n = 25 \\
$
Answer is 25 days.
The work will be complete in 25 days.
Note: If the specific number of workers dropped continuously then there would be a series. Find the series and apply the sum of first n terms in A.P. series after that follow some simple logic to get the number of days in which the work will be completed.
Recently Updated Pages
Master Class 11 Social Science: Engaging Questions & Answers for Success

Master Class 11 Physics: Engaging Questions & Answers for Success

Master Class 11 Maths: Engaging Questions & Answers for Success

Master Class 11 Economics: Engaging Questions & Answers for Success

Master Class 11 Computer Science: Engaging Questions & Answers for Success

Master Class 11 Chemistry: Engaging Questions & Answers for Success

Trending doubts
One Metric ton is equal to kg A 10000 B 1000 C 100 class 11 physics CBSE

There are 720 permutations of the digits 1 2 3 4 5 class 11 maths CBSE

1 Quintal is equal to a 110 kg b 10 kg c 100kg d 1000 class 11 physics CBSE

State and prove Bernoullis theorem class 11 physics CBSE

Difference Between Prokaryotic Cells and Eukaryotic Cells

Which among the following are examples of coming together class 11 social science CBSE

