10 men can finish the construction of a hut in 8 days. How many men are needed to finish the same in half day.
(A) 80
(B) 100
(C) 120
(D) 160
Answer
640.8k+ views
Hint: Time and work problems deal with the simultaneous performance involving the efficiency of an individual or a group and the time taken by them to complete a piece of work.
We will use the following formula to solve the above given question.
Formula used: The relation between the number of people working $(M)$, the number of days worked $(D)$, the number of hours worked per day $(H)$ and the quantity of work $(W)$ for two different cases is given below :
$\dfrac{{{M_1} \times {D_1} \times {H_1}}}{{{W_1}}} = \dfrac{{{M_2} \times {D_2} \times {H_2}}}{{{W_2}}}$
Complete step by step answer:
For condition 1
Total number of men, ${M_1} = 10$
Total number of days, ${D_1} = 8$ days
For condition 2
Let, total number of men $ = {M_2}$
Total working days, ${D_2} = \dfrac{1}{2}$
In given question work is same $({W_1} = {W_2})$
So, by using the relation between M, D and W, we can calculate the number of men ${M_2}$.
$\dfrac{{{N_1} \times {D_1} \times {H_1}}}{{{W_1}}} = \dfrac{{{N_2} \times {D_2} \times {H_2}}}{{{W_2}}}$
or,
${M_1} \times {D_1} = {M_2} \times {D_2}$
$($as ${W_1} = {W_2}$ and we can assume that ${H_1} = {H_2})$
$10 \times 8 = {M_2} \times \dfrac{1}{2}$
${M_2} = 10 \times 8 \times 2$
${M_2} = 160$
Therefore, 160 mens can finish the same work in $\dfrac{1}{2}$ day.
Note: We can solve this problem by a simple method also.
10 men finished in 8 days.
So, to complete the work in 1 day we need $ = 10 \times 8men = 80men$.
So, to complete it in $\dfrac{1}{2}$ day we need $ = $ double of men power doing the work in one day.
i.e., $80 \times 2 = 160men$.
We will use the following formula to solve the above given question.
Formula used: The relation between the number of people working $(M)$, the number of days worked $(D)$, the number of hours worked per day $(H)$ and the quantity of work $(W)$ for two different cases is given below :
$\dfrac{{{M_1} \times {D_1} \times {H_1}}}{{{W_1}}} = \dfrac{{{M_2} \times {D_2} \times {H_2}}}{{{W_2}}}$
Complete step by step answer:
For condition 1
Total number of men, ${M_1} = 10$
Total number of days, ${D_1} = 8$ days
For condition 2
Let, total number of men $ = {M_2}$
Total working days, ${D_2} = \dfrac{1}{2}$
In given question work is same $({W_1} = {W_2})$
So, by using the relation between M, D and W, we can calculate the number of men ${M_2}$.
$\dfrac{{{N_1} \times {D_1} \times {H_1}}}{{{W_1}}} = \dfrac{{{N_2} \times {D_2} \times {H_2}}}{{{W_2}}}$
or,
${M_1} \times {D_1} = {M_2} \times {D_2}$
$($as ${W_1} = {W_2}$ and we can assume that ${H_1} = {H_2})$
$10 \times 8 = {M_2} \times \dfrac{1}{2}$
${M_2} = 10 \times 8 \times 2$
${M_2} = 160$
Therefore, 160 mens can finish the same work in $\dfrac{1}{2}$ day.
Note: We can solve this problem by a simple method also.
10 men finished in 8 days.
So, to complete the work in 1 day we need $ = 10 \times 8men = 80men$.
So, to complete it in $\dfrac{1}{2}$ day we need $ = $ double of men power doing the work in one day.
i.e., $80 \times 2 = 160men$.
Recently Updated Pages
Master Class 10 Maths: Engaging Questions & Answers for Success

Master Class 10 English: Engaging Questions & Answers for Success

Master Class 10 General Knowledge: Engaging Questions & Answers for Success

Class 10 Question and Answer - Your Ultimate Solutions Guide

Master Class 10 Computer Science: Engaging Questions & Answers for Success

Master Class 10 Social Science: Engaging Questions & Answers for Success

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

10 examples of evaporation in daily life with explanations

What is the full form of POSCO class 10 social science CBSE

Write short note on buckyball class 10 chemistry CBSE

Write a report on a Bus accident class 10 english CBSE

Five things I will do to build a great India class 10 english CBSE

